Southeastern Realty and Construction, Inc. v. Burdge
This text of Southeastern Realty and Construction, Inc. v. Burdge (Southeastern Realty and Construction, Inc. v. Burdge) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THIS OPINION HAS NO PRECEDENTIAL VALUE. IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.
THE STATE OF SOUTH CAROLINA
In The Court of Appeals
Southeastern Realty and Construction, Inc., Respondent,
v.
Myron Burdge and Judy Burdge, Appellants.
Appeal From Charleston County
C. Allen Gibson, Jr., Special Referee
Unpublished Opinion No. 2005-UP-622
Submitted December 1, 2005 Filed December 9, 2005
REVERSED AND REMANDED
Jon L. Austen, Ian W. Freeman, of Charleston; for Appellants.
John P. Seibels, Jr., of Charleston; for Respondent.
PER CURIAM: Myron and Judy Burdge (Appellants) appeal the special referees order denying their request for attorneys fees and costs made pursuant to a mechanics lien filed by Southeastern Realty and Construction, Inc. (Southeastern). As the prevailing party, the Burdges claim they are entitled to attorneys fees despite the dismissal of the mechanics lien due to Southeasterns failure to file a lis pendens. We reverse and remand.[1]
FACTS
On September 30, 1999, the Burdges entered into a contract with Southeastern for the construction of a residence on Wadmalaw Island. The parties agreed on a contract price of $838,979 and a period of eleven months for substantial completion of the project.
On October 9, 2001, Southeastern filed a mechanics lien, alleging the Burdges owed $107,782.42 on the contract, which included change orders. Shortly thereafter, Southeastern filed a complaint, seeking to foreclose on the mechanics lien and alleging a cause of action for breach of contract. The Burdges answered and counterclaimed, asserting causes of action for negligence, breach of contract, breach of warranty, and slander of title.[2]
Pursuant to section 29-5-10 of the mechanics lien statute, the Burdges filed an offer of settlement in the amount of $10,000.[3] In response, Southeastern offered to settle the case for $70,000. Between the times these settlement offers were filed, the parties consented to have the case tried by the special referee.
The special referee held a two-day hearing. At the conclusion of Southeasterns case, the Burdges moved for a directed verdict as to the mechanics lien action on the ground the requisite lis pendens had not been filed pursuant to section 29-5-120 of the South Carolina Code of Laws.[4] During the hearing and in a written order, the special referee granted the motion and dismissed the mechanics lien action. In so holding, the special referee found the Burdges were not entitled to attorneys fees and costs under the mechanics lien statute given there was no effective mechanics lien. The special referee further reasoned that the lack of a lis pendens could have been discovered at the time the mechanics lien was filed; thus, the Burdges waived their right to an award of attorneys fees by waiting approximately three years before raising the issue. The case proceeded on Southeasterns remaining breach of contract claim and the Burdges counterclaims.
Ultimately, the special referee entered judgment against the Burdges in the amount of $36,269.27. This award was based on the outstanding balance of $53,239.27 owed to Southeastern, which was offset by the damages in the amount of $16,970 incurred by the Burdges due to Southeasterns delay in completing the construction project. The special referee denied both parties motions for reconsideration.
The Burdges only appeal the special referees denial of their motion for attorneys fees and costs pursuant to the mechanics lien.
DISCUSSION
The Burdges argue the special referee erred in failing to award them attorneys fees and costs after dismissing Southeasterns mechanics lien. In support of this argument, the Burdges contend they: 1) were the prevailing party because the special referee granted their directed verdict motion; 2) did not waive their right to attorneys fees and costs; and 3) were entitled to attorneys fees and costs because, despite the absence of a lis pendens, they had to defend against the mechanics lien which encumbered their property. We agree.
An action to foreclose a mechanics lien is a law case in South Carolina. Adams v. B & D, Inc., 297 S.C. 416, 420, 377 S.E.2d 315, 317 (1989). In an action at law, tried without a jury, the judges findings will not be disturbed unless they are without evidentiary support. King v. PYA/Monarch, Inc., 317 S.C. 385, 388, 453 S.E.2d 885, 888 (1995). His findings are equivalent to those of a jury in an action at law. Id. at 389, 453 S.E.2d at 888. The determination regarding the amount of attorneys fees that should be awarded under the mechanics lien statute is addressed to the sound discretion of the trial judge and his decision will not be disturbed absent an abuse of discretion. D.A. Davis Constr. Co. v. Palmetto Props., Inc., 281 S.C. 415, 419, 315 S.E.2d 370, 372 (1984).
Section 29-5-20(A) requires the court to award reasonable attorneys fees and costs to the party defending against the mechanics lien if the defending party prevails in the action. Keeneys Metal Roofing, Inc. v. Palmieri, 345 S.C. 550, 553-54, 548 S.E.2d 900, 902 (Ct. App. 2001). To determine the prevailing party in a mechanics lien action, this court has explained:
In the context of statutes allowing attorney fees, our supreme court has defined a prevailing party as [t]he one who successfully prosecutes the action or successfully defends against it, prevailing on the main issue, even though not to the extent of the original contention [and] is the one in whose favor the decision or verdict is rendered and judgment entered. Heath v. County of Aiken, 302 S.C. 178, 182-83, 394 S.E.2d 709, 711 (1990)(quoting Buza v. Columbia Lumber Co., 395 P.2d 511, 514 (Alaska 1964)). Thus, the court of appeals concluded in a mechanics lien foreclosure action the party in whose favor the decision or verdict on liability is rendered is the prevailing party for purposes of awarding attorney fees. See Utilities Constr. Co. v. Wilson, 321 S.C. 244, 468 S.E.2d 1 (Ct. App. 1996). According to Heath, a party need not be successful as to all issues in order to be found a prevailing party.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Southeastern Realty and Construction, Inc. v. Burdge, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeastern-realty-and-construction-inc-v-burdge-scctapp-2005.