Southeastern Natural Gas Co. v. Vititoe Constr., Inc.

2011 Ohio 1844
Ohio Court of Appeals·Decided April 14, 2011·No. 10CAE070053·Published

Opinion

[Cite as Southeastern Natural Gas Co. v. Vititoe Constr., Inc., 2011-Ohio-1844.]

COURT OF APPEALS DELAWARE COUNTY, OHIO FIFTH APPELLATE DISTRICT

SOUTHEASTERN NATURAL GAS : JUDGES: COMPANY : Hon. Sheila G. Farmer, P.J. : Hon. Julie A. Edwards, J. Plaintiff-Appellee : Hon. Patricia A. Delaney, J. : -vs- : : Case No. 10CAE070053 VITITOE CONSTRUCTION, INC. : : Defendant-Appellant : OPINION

CHARACTER OF PROCEEDING: Appeal from the Court of Common Pleas, Case No. 08CVH091211

JUDGMENT: Affirmed

DATE OF JUDGMENT ENTRY: April 14, 2011

APPEARANCES:

For Plaintiff-Appellee For Defendant-Appellant

JOHN K. KELLER CRAIG G. PELINI JOHN M. KUHL RAYMOND C. MUELLER 52 East Gay Street 8040 Cleveland Avenue, NW P.O. Box 1008 Suite 400 Columbus, OH 43216-1008 North Canton, OH 44720

For Amicus Curiae Ohio Gas Association

ANDREW J. SONDERMAN 175 South 3rd Street Suite 900 Columbus, OH 43215 Delaware County, Case No. 10CAE070053 2

Farmer, P.J.

{¶1} On November 19, 2007, appellant, Vititoe Construction, Inc., was

performing construction work on a public improvement project when a trackhoe operator

struck and damaged an underground gas line owned by appellee, Southwestern Natural

Gas Company.

{¶2} On September 10, 2008, appellee filed a complaint against appellant for

negligence. A bench trial commenced on May 25, 2010. By judgment entry filed June

18, 2010, the trial court found in favor of appellee as against appellant in the amount of

$123,862.73, finding appellant had actual notice of the gas line and was responsible for

the damage under R.C. 153.64.

{¶3} Appellant filed an appeal and this matter is now before this court for

consideration. Assignments of error are as follows:

I

{¶4} "THE TRIAL COURT ERRED IN ITS INTERPRETATION OF R.C.

§153.64(D), WHEN IT CONSTRUED THE STATUTE TO MEAN THAT APPELLANT

WAS RESPONSIBLE FOR DAMAGES TO APPELLEE'S GAS LINE, DESPITE

HAVING FOUND THAT APPELLEE HAD FAILED TO MARK ITS GAS LINES IN

ACCORDANCE WITH THE MANDATORY PROVISIONS OF R.C. §153.64(C)."

II

{¶5} "THE TRIAL COURT ERRED IN HOLDING THAT UNDER THE

PROVISIONS OF R.C. §153.64, THE COMPARATIVE NEGLIGENCE OF APPELLEE

WAS IRRELEVANT." Delaware County, Case No. 10CAE070053 3

{¶6} Appellant claims the trial court erred in granting judgment to appellee. We

disagree.

{¶7} Specifically, appellant argues the trial court's finding that it had "actual

notice" was incorrect as "actual notice" under R.C. 153.64(D) must be narrowly

construed. Said statute states the following in pertinent part:

{¶8} "(C) The contractor to whom a contract for a public improvement is

awarded or its subcontractor, at least two working days, excluding Saturdays, Sundays,

and legal holidays, prior to commencing construction operations in the construction area

which may involve underground utility facilities, shall cause notice to be given to the

registered underground utility protection services and the owners of underground utility

facilities shown on the plans and specifications who are not members of a registered

underground utility protection service, in writing, by telephone, or in person. Where

notice is given in writing by certified mail, the return receipt, signed by any person to

whom the notice is delivered, shall be conclusive proof of notice. The owner of the

underground utility facility, within forty-eight hours, excluding Saturdays, Sundays, and

legal holidays, after notice is received, shall stake, mark, or otherwise designate the

location of the underground utility facilities in the construction area in such a manner as

to indicate their course together with the approximate depth at which they were

installed. The marking or locating shall be coordinated to stay approximately two days

ahead of the planned construction.

{¶9} "(D) If the public authority fails to comply with the requirements of division

(B) of this section, the contractor to whom the work is awarded or its subcontractor Delaware County, Case No. 10CAE070053 4

complies with the requirements of division (C) of this section, and the contractor or its

subcontractor encounters underground utility facilities in the construction area that

would have been shown on the plans and specifications for such improvement had the

registered underground utility protection service or owner of the underground utility

facility who is not a member of a registered underground utility protection service whose

name, address, and telephone number is provided by the public authority been

contacted, then the contractor, upon notification to the public authority, is entitled to an

increase to the contract price for itself or its subcontractor for any additional work that

must be undertaken or additional time that will be required and is entitled to an

extension of the completion date of the contract for the period of time of any delays to

the construction of the public improvement.

{¶10} "***

{¶11} "Any public authority who complies with the requirements of division (B) of

this section and any contractor or its subcontractor who complies with the requirements

of division (C) of this section shall not be responsible to the owner of the underground

utility facility if underground utility lines are encountered not as marked in accordance

with the provisions of division (C) of this section by the owner of the underground utility

facility, unless the contractor or its subcontractor has actual notice of the underground

utility facility. Except as noted in this division, this section does not affect rights

between the contractor or its subcontractor and the owner of the underground utility

facility for failure to mark or erroneously marking utility lines. The public authority shall

not make as a requirement of any contract for public improvement any change in

responsibilities between the public authority and the owners of the underground utility Delaware County, Case No. 10CAE070053 5

facilities in connection with damage, injury, or loss to any property in connection with

underground utility facilities."

{¶12} In its judgment entry filed June 18, 2010, the trial court included the

following interpretation of the evidence vis-à-vis R.C. 153.64(D):

{¶13} "The statute does not require the contractor to have actual knowledge of

the specific location of the utility in order to be responsible for the damaged line. A

contractor only needs to have actual notice 'of the underground utility facility'. In this

situation, it is not a matter of OUPS mis-marking the gas line and the contractor hitting

the line in relying on the recently placed markings. Here there were no markings made

after the most recent request by the contractor. Yet, the contractor relied on OUPS lack

of markings as determining no gas line existed. No confirmation was made as to

whether OUPS or Southeastern did appear and not mark. Certainly, the responsibility

and duty lies with the contractor to ensure the lack of markings means no utilities;

particularly since Mike Vititoe had knowledge from the plans of a gas line and he was

told that there was a gas line albeit outside the work area and a permanent marker

existed on the date of the accident and perhaps two permanent markers existed at the

beginning of the project. Further, OUPS and or Southeastern had marked the lines at

the beginning of the construction project."

Free access — add to your briefcase to read the full text and ask questions with AI

Southeastern Natural Gas Co. v. Vititoe Constr., Inc., 2011 Ohio 1844 (Ohio Ct. App. 2011).

2011 Ohio 1844 (Southeastern Natural Gas Co. v. Vititoe Constr., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Myers v. Garson
614 N.E.2d 742 (Ohio Supreme Court, 1993)
Myers v. Garson
1993 Ohio 9 (Ohio Supreme Court, 1993)