Southeastern Conn. v. Dept. of Public Ut., No. Cv95 0555212 (Jan. 7, 1997)

1997 Conn. Super. Ct. 210-II
CourtConnecticut Superior Court
DecidedJanuary 7, 1997
DocketNos. CV95 0555212, CV95 0555202
StatusUnpublished

This text of 1997 Conn. Super. Ct. 210-II (Southeastern Conn. v. Dept. of Public Ut., No. Cv95 0555212 (Jan. 7, 1997)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeastern Conn. v. Dept. of Public Ut., No. Cv95 0555212 (Jan. 7, 1997), 1997 Conn. Super. Ct. 210-II (Colo. Ct. App. 1997).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION These two administrative appeals have been consolidated inasmuch as they arise out of the same decision of the Department of Public Utility Control (DPUC). The appellant in one case is Connecticut Light and Power (CLP), and in the other, the appellants are Southeastern Connecticut Regional Resources Recovery Authority (SCRRRA), American Ref-fuel Company (Ref-fuel) and Air Products and Chemicals, Inc. (Air Products). The respective appellants' interests are in conflict to each other.

Most of the salient facts in these two appeals are not in dispute. SCCRA generates electricity through a trash-to-energy plant. It is a political subdivision of the State of Connecticut which functions as a resource recovery authority pursuant to Connecticut General Statutes 7-273a et. seq. In anticipation of the construction and operation of the plant, SCCRA entered into an agreement with CLP for its purchase of electricity generated by the plant.

One of the oversight areas of the DPUC is the review and approval or rejection of agreements entered into between CLP and any private producers of electricity. (16-243a). Air Products, (a parent company of Ref-Fuel), and Ref-Fuel, were parties to the agreement as the operators of the plant. CLP is a public utility which, as a public service company, is regulated by the DPUC. The agreement between the parties was submitted to DPUC for approval by petition dated June 8, 1987. Approval was granted by the DPUC on October 6, 1987. It is this approved agreement which became the centerpiece of the instant controversy. CT Page 211

The Decision approving the Agreement between the parties described the Project, as follows:

The Facility will be designed to dispose of residential, commercial and non-hazardous industrial municipal solid waste (MSW) generated in the member municipalities of SCRRA pursuant to municipal service contracts between the member municipalities and SCRRRA. The solid waste will be burned through the use of a mass-burning grate system and boiler combination to produce steam to energize turbines which will generate electricity. The Project's electricity will be used to operate the Facility and made available for sale to CLP.

The Facility will have an approximate gross output of 16.0 MW and a net output for sale of about 13.85 MW. The Facility will process approximately 180,000 tons of MSW annually at a rate f 600 tons per day assuming 500 Btu per pound of waste. SCRRRA expects that the Facility will operate seven days a week, 365 days a year. With an availability factor of 82%. (Emphasis added).

The 1987 decision by DPUS resolved two questions essential to the determination of this appeal.

"1. Whether CLP must purchase the entire electric energy output pursuant to C.G.S. 16-243e;

2. Whether CLP must purchase a portion of the electric energy output at a front loaded rate equaling CLP's full avoid costs over the life of the contract. . . ."

In consideration of these questions, the DPUC reviewed the statutory language of C.G.S. 16-243e.1

After substantial written consideration of the positions of the respective parties, DPUC found as a matter of fact that ". . . SCRRRA has agreed to sell all of its output to CLP, and will make efforts to maximize on-peak production." It also ruled: CT Page 212

"In regard to the applicability of C.G.S. 16-243e, the Department hereby rules that payments at the municipal rate are applicable to this case. Payments to the Project shall be made at that rate for the first 20 years of its operation, and at the Company's Block 2 rate for the remaining five years."

Per the 1987 DPUC decision, CLP and the generating parties entered into an agreement consistent with the DPUC decision. That agreement is the Electric Energy Purchase Agreement (EEPA). The plant was built. There is no dispute between the parties that the plant was built pursuant to the plans and specifications and so certified by the parties' respective engineers, to DPUC.

From January, 1992 through December, 1993, the plant had a permit to burn to a limit of 600 tons per day. On December 9, 1993 they received a rise in that limit to 689 tons per day. The output of the plant has fairly consistently exceeded 16.00 MW gross output and 13.85 MW net output for sale after December, 1993, measured monthly. Measured monthly it never exceeded 13.95 MW, but did when measured in smaller increments. CLP claimed the right in the instant controversy to pay the 16-243e rate to 13.85 MW and to pay the avoided cost rate (Rate 980) to output above 13.85 MW.2 The DPUC concurred with CLP. The first of these appeals is from that decision. In the same decision, DPUC ruled that the calculation to determine the proper payment should be performed on an "average monthly" basis rather than the hourly basis (as had been requested by CLP. Thus CLP brought the second of the consolidated appeals before this court.

The standard of review for these administrative appeals is found at C.G.S. 4-183:

The standard of review for these administrative appeals is found at C.G.S. 4-183:

The court shall not substitute tits judgment for that of the agency as to the weight of evidence on questions of fact. The court shall affirm the decision of the agency unless the court finds that substantial rights of the person appealing have been prejudiced because the administrative findings inferences, conclusions, or decisions are: (1) In violation of constitutional or statutory provisions; (2) in excess of the statutory CT Page 213 authority of the agency; (3) made upon unlawful procedure; (4) affected by other error of law; (5) clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record; or (6) arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.

I.
Appeal of SCRRRA, Ref-Fuel and Air Products

The appellants challenge the decision of the DPUC regarding the rate above 13.85 MW production on several bases: 16-243a(b) provides "Each electric public service company . . . shall (1) Purchase any electrical energy and capacity made available, directly by a private power producer. . . ." This statute's language has remained unchanged during all times relevant to this action. SCRRRA constitutes a private power producer under C.G.S. 16-243b and 22a-260.

(1) They claim the decision is in violation of C.G.S. 16-243e;

(2) That it was made upon unlawful procedure, to wit: the conclusion that energy generated above 13.85 MW was to due to energy savings procedures, without the allowance of testimony;

(3) That it improperly interpreted the agreement (EEPA) between the parties.

Connecticut General Statute The statute at issue, C.G.S. 16-243e has undergone amendment during the pendency of this action. At the time of the issuance of the 1987 DPUC decision and the signing of the EEPA, the statute, in salient part, read: "Any electric company, as defined in section 16-1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Collins v. Sears, Roebuck & Co.
321 A.2d 444 (Supreme Court of Connecticut, 1973)
Connecticut Co. v. DIVISION 425
164 A.2d 413 (Supreme Court of Connecticut, 1960)
Texaco, Inc. v. Rogow
190 A.2d 48 (Supreme Court of Connecticut, 1963)
Sutton v. Lopes
513 A.2d 139 (Supreme Court of Connecticut, 1986)
Schlumberger Technology Corp. v. Dubno
521 A.2d 569 (Supreme Court of Connecticut, 1987)
City of New Haven v. Freedom of Information Commission
535 A.2d 1297 (Supreme Court of Connecticut, 1988)
Connecticut Light & Power Co. v. Department of Public Utility Control
554 A.2d 1089 (Supreme Court of Connecticut, 1989)
Ceci v. National Indemnity Co.
622 A.2d 545 (Supreme Court of Connecticut, 1993)
Gateway Co. v. DiNoia
654 A.2d 342 (Supreme Court of Connecticut, 1995)
Snydergeneral Corp. v. Lee Parcel 6 Associates Ltd. Partnership
681 A.2d 1008 (Connecticut Appellate Court, 1996)
McCarthy v. Lopes
479 U.S. 964 (Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
1997 Conn. Super. Ct. 210-II, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeastern-conn-v-dept-of-public-ut-no-cv95-0555212-jan-7-1997-connsuperct-1997.