Southeastern Chester County Refuse Authority v. Board of Supervisors of London Grove Township

916 A.2d 1237, 2007 Pa. Commw. LEXIS 55
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 8, 2007
StatusPublished
Cited by4 cases

This text of 916 A.2d 1237 (Southeastern Chester County Refuse Authority v. Board of Supervisors of London Grove Township) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeastern Chester County Refuse Authority v. Board of Supervisors of London Grove Township, 916 A.2d 1237, 2007 Pa. Commw. LEXIS 55 (Pa. Ct. App. 2007).

Opinion

OPINION BY

President Judge COLINS.

Before the Court is the appeal of the Southeastern Chester County Refuse Authority (Authority) from the order of the Court of Common Pleas of Chester County (trial court). The trial court affirmed the decision of the London Grove Township (Township) Board of Supervisors (Board) that denied the Authority’s application for a conditional use of land for a proposed expansion of its existing landfill. We affirm. 2

On August 13, 2003, the Authority filed its application for conditional use approval with the Board to expand the landfill at the existing site. The subject of the Authority’s application is a 67 acre portion of a 188 acre tract of land located in the Township; the actual landfill cell as proposed would encompass 37 acres of the 67 acres; the remaining acreage would be used for ancillary support services, monitoring, perimeter roads, maintenance, visual and noise screening areas, a pump house, leachate management facilities, and stormwater facilities.

The Authority proposes to develop the landfill cell with setbacks of 100 feet and a maximum height of 140 feet; however, the Township zoning ordinance (ordinance) prescribes a minimum setback of 200 feet and a maximum height of 40 feet. In conjunction with its application, the Authority also filed with the Township’s Zoning Hearing Board (ZHB) a challenge to the validity of the setback and height restrictions and a request for variance.

An initial public hearing on the conditional use application was advertised and scheduled for October 22, 2003, 70 days after the application was filed. Hearings were concluded on April 13, 2005; testimony was taken over nineteen nights, spanning a period of 17 months, with a total of 38 hours of testimony by 3 Authority casein-chief witnesses, 5 Township witnesses, and 1 Authority rebuttal witness. On August 26, 2004, during the Township’s presentation of its case, a hearing was adjourned and reconvened 48 days later, and on December 20, 2004, during the Authority’s rebuttal, a hearing was adjourned and reconvened 93 days later. The elapsed *1239 time of the Authority’s presentation of its case-in-chief was 165 days, over 6 nights of hearings; the elapsed time of the Township’s presentation was 210 days, over 9 nights. The Authority’s rebuttal ended 114 days later, over 3 nights of testimony. On August 11, 2005, the Board denied the conditional use application. On September 1, 2005, the Authority appealed to the trial court, raising the following five issues: i) Whether the Authority is entitled to a deemed approval; ii) Whether the Authority proved all express standards and criteria under the ordinance for conditional use approval except for the height and setback dimensions; iii) Whether the Authority’s conditional use application was appropriately denied as the Authority’s proposed use failed to satisfy the height and setback requirements of the ordinance; iv) Whether the Township reached its decision in bad faith; and v) Whether the Authority was denied due process and a fair hearing by virtue of representation of the Township by counsel in opposition to the application.

In the separate action before the ZHB, the Authority’s validity challenge and request for a variance was denied on January 12, 2005. The Authority appealed, and the ZHB’s decision was upheld by the trial court. The Authority appealed, and our Court en bane affirmed the trial court on May 5, 2006. 3 The Authority has filed a petition for allowance of appeal to the Supreme Court.

Sub judice, the trial court affirmed the Board, holding that: i) the Authority was not entitled to a deemed approval as it waived any claim to such; and ii) the remaining issues were denied as moot in light of our Court’s decision on the Authority’s related land use appeal. The trial court applied our decision in Wistuk v. Lower Mt. Bethel Township Zoning Hearing Board, 887 A.2d 343 (Pa.Cmwlth.2005), petition for alloivance of appeal granted, 588 Pa. 745, 902 A.2d 970 (2006), in ruling that the Authority waived the statutory time limits in section 908(1.2) of the Municipalities Planning Code 4 (MPC) and the deemed approvals did not operate.

*1240 In its appeal, the Authority alleges that the Board failed: i) to commence the hearing within 60 days of the filing date of the application, ii) in two instances, to complete the presentation of the case within 45 days of the prior hearing, and iii) to complete the presentation of the case in opposition to the application within 100 days; in so doing, the Board failed to meet the deadlines required by the MPC and is entitled to a deemed approval. The Authority argues that the Wistuk decision, and the trial court’s application of that decision were wrong; the Authority argues that Wistuk improperly relied on Hogan v. Pequea Township Zoning Hearing Board, 162 Pa.Cmwlth. 282, 638 A.2d 464 (1994), petition for allowance of appeal denied, 538 Pa. 651, 647 A.2d 905 (1994), a case decided before the 2002 amendment of the MPC that placed specific time limits on the duration of zoning hearings. 5 In Hogan, an applicant was held to have waived his right to a deemed approval by failing to object to an announced additional hearing date beyond the 45-day limit where oral argument was allowed; in Wistuk, the township zoning board held its last hearing and announced that the record was closed, but legal arguments could be submitted via briefs for approximately three weeks, up until the date when the board would resume solely to deliberate, with no testimony or oral arguments permitted, and the board issued its written decision 59 days after the last hearing. The applicant in Wistuk argued that her case was factually different from Hogan in that no oral argument was allowed at the meeting subsequent to the last hearing. Our Court in Wistuk opined that since the applicant did not object to the post-hearing briefing period, or question the effect of the briefing offered by the board on the 45-day decision period, her rights, like the applicant in Hogan, were waived. 6

The Authority further contends that the basic assumption underlying both Hogan and Wistuk — that the Court may fashion a body of law governing the waiver of the deemed approval provisions of the MPC when those provisions themselves already *1241 contain express language that specify how the time periods in § 908(1.2) may be waived — is wrong. The Authority asserts Wistuk must be reconsidered, and the procedural provisions of the MPC strictly construed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WeCare Organics, LLC v. Zoning Hearing Bd. of Schuylkill County
954 A.2d 684 (Commonwealth Court of Pennsylvania, 2008)
Wistuk v. Lower Mt. Bethel Township Zoning Hearing Board
925 A.2d 768 (Supreme Court of Pennsylvania, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
916 A.2d 1237, 2007 Pa. Commw. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeastern-chester-county-refuse-authority-v-board-of-supervisors-of-pacommwct-2007.