Southeast Contractors, Inc. v. H. & R. Construction Co.

228 So. 2d 463, 284 Ala. 712, 1969 Ala. LEXIS 1176
CourtSupreme Court of Alabama
DecidedNovember 20, 1969
Docket6 Div. 535
StatusPublished
Cited by2 cases

This text of 228 So. 2d 463 (Southeast Contractors, Inc. v. H. & R. Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southeast Contractors, Inc. v. H. & R. Construction Co., 228 So. 2d 463, 284 Ala. 712, 1969 Ala. LEXIS 1176 (Ala. 1969).

Opinion

SIMPSON, Justice.

In March, 1964, Southeast Contractors, Inc. entered into a contract with the State of Alabama to perform all the work and labor and to furnish and deliver all the materials to construct the public road in Tuscaloosa County referred to as the 15th Street Project.

Simultaneously Southeast Contractors, Inc. as principal, and National Union Fire Insurance .Company of Pittsburgh, Pennsyl[715]*715vania, as surety, executed a payment bond which is the basis of this suit, and a bond for the performance of the project.

In February, 1964, H. & R. Construction Company, Inc. began negotiations with Southeast Contractors, Inc. concerning subcontracts on the project. On March 2, 1964, the appellee entered into a written subcontract with the appellant contractor, which provided that the appellee as subcontractor would furnish all labor and materials for completing sanitary sewers and a bridge in connection with the project for a consideration of $54,280.21. The appellant contractor’s charge to the State of Alabama for the identical items was $76,-772.55. On March 13, 1964, the appellee subcontracted in writing with the appellant contractor to furnish the material only on various bid items covering roadway and storm sewer pipe. The amount of this second subcontract was $21,479.85. The appellant’s general contract with the State of Alabama calls for appellant to be paid $27,199.85 for the identical items covered by this second subcontract.

In addition to the written subcontracts, the two contractors orally agreed that appellee’s president, James Ray Cox, would serve as appellant contractor’s job superintendent at a salary of $150.00 per week plus an additional $50.00 to be on the site personally. Cox served in this capacity for approximately six weeks but was paid only $800.00. $500.00 of this was later deducted by the appellant.

The appellee and the appellant contractor also had an oral agreement for the appellee to perform and to be paid for excavation work not included in the written subcontract. Appellee performed or paid to have performed all storm sewer and bridge excavation work on the project and his claim amounted to 4,855 cubic yards at $2.75 per cubic yard.

Additionally, the appellee and the appellant contractor had an oral agreement that appellant would furnish the forms for the culverts and catch basins on the project. Appellant contractor failed to furnish adequate forms and such forms were obtained and furnished by the appellee at a sum of $3,276.40.

In addition, at the request of the appellant contractor, the appellee cleaned out the storm sewers and the bridge culvert, and it is the appellee’s contention that it was entitled to payment for this work, and a reasonable charge for this work was ass'erted to be $2,600.00 for cleaning the storm sewer and $875.00 for cleaning the bridge culvert.

Also, the complaint claimed $1,400.00 for sand furnished by the appellee for foundation material, which was not specifically covered by its contract. It also claimed $275.00 for additional excavation work done at the request of the appellant contractor; and $800.00 for the removal of a structure from a part of the property. ■

The appellee claimed that the full amount to which it was entitled under the subcontract was $74,918.45. It conceded that it had been paid approximately $57,000.00 and that a balance remained due under the subcontract and the extra items claimed in the amount of $27,758.60. The jury returned a verdict in favor of the appellee in the amount of $25,980.00.

The appellants filed a motion for a new trial, which was denied. This appeal is from the final judgment.

The record in this case exceeds 1,500 pages in length and consists of some seven transcript volumes. The appellant . has made more then 100 assignments of error. However, these assignments are not all argued, and many of the assignments are repetitive. We will consider only those categories of assignments which have been argued in brief.

It is first argued by the appellants that the trial court erred in refusing to give several written requests for the affirmative charge. It is the contention of the appellants that the defendants were [716]*716entitled to the general affirmative charge because the appellee (plaintiff) failed to prove that the person purporting to sign the bond sued upon as attorney in fact for National Union Fire Insurance Company of Pittsburgh, Pennsylvania, had written authority from the surety to execute the bond in suit on its behalf. It is the contention of the appellants that the statute of frauds requires that the bond must be subscribed on behalf of the defendant surety by some person authorized in writing to bind the defendant.

It is true that the statute of frauds, Title 20, § 3(3), Code of Alabama, 1940 Recompiled 1958, requires such authority to be in writing. However, it is equally true in this state that under the provisions of Title 7, § 375, Code of Alabama, 1940, every instrument, the foundation of a suit, purporting to be signed by the defendant, his partner, agent, or attorney in fact, must be received in evidence without proof of execution, unless the execution is denied by plea verified by affidavit. Likewise, Title 7, § 226, Code of Alabama, 1940, requires that plea denying the execution by the defendant, his agent or attorney, or partner, of any instrument in writing, the foundation of a suit must be verified by affidavit. In this case the pleading was in short by consent. This court has repeatedly held that a plea in short by consent with leave to give in evidence any matter which, if well pleaded, would be admissible in defense, does not permit proof of defensive matter required by the law of this state to be interposed by a verified special plea. Johnston v. Isley, 240 Ala. 217, 198 So. 348; Emergency Aid Insurance Company v. Dobbs, 263 Ala. 594, 83 So.2d 335.

The appellants, therefore, can take nothing from these assignments of error.

The appellants cite a great many cases to support the proposition that the trial court erred in refusing the affirmative charge on this ground: However, an examination of those cases will indicate that in each one where the trial court was reversed for failure to give the affirmative charge, a special verified plea had been filed raising the statute of frauds.

While it is true that the filing of a special plea raising the statute of frauds, which plea is required to be verified under our statute, places the burden on the plaintiff with respect to compliance with the statute of frauds, nothing in our law requires the plaintiff to discharge this obligation under a plea of the general issue, or under a plea of the general issue in short by consent. It would be grossly unfair to give the affirmative charge on this ground against the plaintiff, when the plaintiff has never been apprised, by special verified plea, that it had the burden of proving compliance.

The appellants contend that the case of Southern Life and Health Insurance Company v. Whitfield, 238 Ala. 243, 190 So. 276 (1939) stands for the proposition that although the absence of a verified plea raising the statute of frauds relieves the plaintiff from proving the execution of the bond sued upon, the plaintiff still has the burden of proving the existence of the bond as an essential element of its prima facie case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Murray v. Alabama Power Co.
413 So. 2d 1109 (Supreme Court of Alabama, 1982)
State v. Waller
395 So. 2d 37 (Supreme Court of Alabama, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
228 So. 2d 463, 284 Ala. 712, 1969 Ala. LEXIS 1176, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southeast-contractors-inc-v-h-r-construction-co-ala-1969.