Southard v. Higbee

290 P. 633, 107 Cal. App. 674, 1930 Cal. App. LEXIS 327
CourtCalifornia Court of Appeal
DecidedAugust 15, 1930
DocketDocket No. 402.
StatusPublished

This text of 290 P. 633 (Southard v. Higbee) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southard v. Higbee, 290 P. 633, 107 Cal. App. 674, 1930 Cal. App. LEXIS 327 (Cal. Ct. App. 1930).

Opinion

BARNARD, J.

The plaintiffs, as contractors, built a house for the defendant for a specified sum as set forth in a written agreement. This action was filed to recover $1496.47 for work and service performed and materials furnished, in supplying and constructing certain extras in connection with the erection of such residence. The defendant answered denying all of the allegations in the plaintiffs’ complaint and through ten counterclaims, sought damages for an alleged failure of the plaintiffs to construct said residence in accordance with the contract. The trial court found that there was due to the plaintiffs for extras the sum of $1139.96, further found in favor of the defendant upon certain of the counterclaims, awarding damages in the total sum of $1519.50, and gave judgment in favor of the defendant for the difference, amounting to $379.54. Prom this judgment the plaintiffs have appealed, the questions involved being.almost entirely of fact rather than of law.

It is first contended that the court erred in reducing the demand of the appellants in the amount of $104, which represented the amount paid by them for the installation of a heating plant, in excess of an allowance of $300 for *676 that purpose provided in the contract. The evidence shows without contradiction, that the defendant and his wife personally selected a heating plant which was priced to them by a heating contractor at $404, accepted by them and installed, and that appellants had nothing to do with this except that they paid the bill. In connection with this same matter, respondent set up a counterclaim, asking damages in the sum of $300 on the ground that the heating plant was installed by the plaintiff, that it was deficient in workmanship, and that it had to be replaced. In regard thereto, the court found as follows:

“Seventh Counterclaim.
“The Court finds that in the construction of the furnace in said building, said contract provided for an allowance of $300; and that any expense above $300 is chargeable to said defendant, and that said plaintiffs are not liable therefor; that said furnace was installed in a good workmanlike manner; and that said defendant is not entitled to recover under said seventh counterclaim.”

That finding is supported by the evidence. There is no finding to justify the court in deducting this $104 from appellants’ claim, and a careful reading of the transcript discloses no evidence that would support such a finding, had it been made. It would appear that the deduction had been made by inadvertence. There being no evidence to sustain this, and the only finding being to the contrary, it must be set aside.

The second and third specifications of error relate to the refusal of the court to allow to appellants, an item of $76.66 for compensation insurance, trucking and supervision in connection with furnishing the extras in question, and also an item of $77.54, which was claimed as a profit of ten per cent on the cost of a portion of the extras. Appellant A. M. Southard testified that he could remember no definite conversation or agreement in regard to these items. He was unable to testify as to the exact amount he claimed for compensation insurance, for trucking, or for supervision in connection with these extras, as distinguished from the main part of the job. It does not clearly appear that he was entitled to any profit as distinguished from compensation for supervision. The entire testimony is probably too indefinite to have sustained a finding in favor of appel *677 lants on those items; and in any event, the decision of the trial court cannot be disturbed under the showing made.

. It is next insisted that the court erred in allowing the respondent $300 damages because of the faulty construction of a certain terrace. It is argued that this finding is not sustained by the evidence. One of the witnesses testified that it would cost $250 to correct this defect. In addition, there was evidence that because thereof, rain had gone through to certain rooms, damaging the plaster and finish, all of which was noted by the court on a personal inspection. We think there is sufficient evidence to sustain this finding of damage.

A similar contention is made in regard to a finding that the respondent was damaged in the sum of $75 because of the improper construction of certain French doors. There is ample evidence that the doors in question were not watertight, and that respondent was compelled to employ another workman to remedy the defect.

The next and principal contention of appellants is that the court erred in finding damages for the respondent in the sum of $500 under his ninth counterclaim. As to that matter, the court found as follows:

“Ninth Counterclaim.
“The Court makes the same finding as Finding III (1) which by reference is made a part of this finding the same as though fully stated herein; and the Court further finds that in and by said contract and specifications the said plaintiffs were responsible for the correctness of the location of said building and garage; that said plaintiffs negligently and carelessly failed to place said building in the proper position on said lots, and placed said building in such position that it was necessary, in order to comply with the plans and specifications, to construct certain portions of said building as an extension of said building into and on the street adjoining said premises; all of which has caused defendant damage in the sum of $500.”

In this connection, it is also urged that the court erred in receiving into evidence a certain perspective drawing of the residence in question, and also in finding as follows: “that said contract consisted of written specifications, blue print plans, and perspective drawing of said house.” The finding that this perspective drawing of the house was *678 a part of the contract is not supported by the evidence. The uncontradicted evidence shows that it was originally planned to build this residence upon certain lots in San Diego. At that time the perspective drawing in question was made. It was then contemplated to put a garage under the main part of the house. Later, the plans were changed and the house was built upon other lots, and because of a difference in the contour of the property, the garage was then placed on the outside of the house, instead of within it. After the change in plans was made, a written contract was entered into which provided as follows: “that said buyer shall pay to A. M. Southard at San Diego, the sum of $16,051 for completed house as per blue print plans and according to specifications.” There was attached to said contract a set of six blue-print drawings, and what is apparently quite a complete set of specifications. Not only was the perspective drawing in question prepared in connection with preliminary negotiations on a different lot, and while it was intended to place the garage underneath the house rather than at its side, but all prior negotiations were merged in the written contract. The court was therefore in error in finding that the perspective drawing was a part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
290 P. 633, 107 Cal. App. 674, 1930 Cal. App. LEXIS 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southard-v-higbee-calctapp-1930.