South Shore Nav. Co. v. Bridgeport Dredge & Dock Co.

2 F. Supp. 513, 1932 U.S. Dist. LEXIS 1517
CourtDistrict Court, E.D. New York
DecidedDecember 13, 1932
DocketNo. 12917
StatusPublished

This text of 2 F. Supp. 513 (South Shore Nav. Co. v. Bridgeport Dredge & Dock Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Shore Nav. Co. v. Bridgeport Dredge & Dock Co., 2 F. Supp. 513, 1932 U.S. Dist. LEXIS 1517 (E.D.N.Y. 1932).

Opinion

BYERS, District Judge.

The libelant, as owner of the motor vessel known, in June, 1981, as the Patehogue, seeks to recover the damages said to have been sustained by the vessel, because it was negligently hauled out on the marine railway of the respondent at Bridgeport, Connecticut, on June 3, 1931.

The Patehogue is a passenger vessel, built in 1912, now plying between Babylon, L. I., and Fire Island, across the Great South Bay. She is of composite type construction; that is, wooden hull, with oak double 3-ineh frames, 5x6, spaced 18 inches between centers, with steel angle iron deck frames, spaced 18 inches between centers; there are steel longitudinals below deck, and three steel thwartship bulkheads; the deck is wood.

The vessel is 105- feet long, 23- feet beam, and her greatest draft is 3 feet'; she is therefore a shallow draft vessel, having twin screws.

In May, 1931, her original engines and boilers were removed, in Brooklyn, and she was placed in dry dock at Shewan’s, where the tail .shafts were drawn, examined and replaced (i. e., on deck), and general caulking and painting were done following a three-year lay-off, during which time she was out of commission. Thereafter the vessel was towed to the Wolverine Motor Works, on Johnson’s Creek, Bridgeport, Connecticut, s where two Diesel motors, weighing about 13,009 pounds each, were installed.

When the shafts had been connected, and the vessel was ready to receive her propellers, she was towed to the respondent’s yard to be hauled out on the marine railway, where the propellers were put in.place.

This was done pursuant to an exchange of letters between the parties, as follows:

“Great South Bay Marine Corp.

“New York Office

“17 Battery Place

“April 39, 1931 .

“Bridgeport Dredge- & Deck Co., 1024 Main Street, Bridgeport, .Conn.

“Gentlemen: We expect in a short time to send a boat to the Wolverine Motor Works for installation of engines and would appreciate knowing if you have any facilities available either for hauling out or docking the boat in the event that it is necessary for us to dock her. This boat is 105 feet long by about 22% feet beam and draws about 3 feet of water. She is a shallow draft twin screw boat.

“We.would appreciate knowing if you have the facilities for such work what the cost of docking would be and what you would charge for lay days.

“Thanking.you and awaiting your reply, we. remain

“Yours very truly,

“J. W. Fristik

“JRF Secretary.”

“Bridgeport Dredge & Dock Co.

“River and Harbor Work

“1024 Main Street

“Bridgeport, Conn.

“May 5, 1931.

“Great South Bay Marine Corp., 17 Battery Place, ,New York, N. Y.

“Gentlemen: Thank you for your inquiry of April 39th, with reference to a boat you are going to send to the Wolverine Motor Works shortly.

“We have a Shipyard and Dock at the Foot of Seaview Avenue, this city, that is well equipped to handle boats of your type mentioned in your letter and we will be glad to dock it when it arrives in Bridgeport if you will let us know a little ahead so that we can arrange for it.

“When other people are repairing the boat, as Wolverine will be for you, we charge [515]*515$50.00. Lay Days start noon of the day following hauling and the charge is $15.00 per day.

“Trusting that this information is what you want and that we may hear from you soon, we remain,

“Very truly yours,

“Bridgeport Dredge & Dock Company

“GWS/K G. W. Sunderlin, Secretary.

“By K”

When the work of installing the motors was nearing completion, an officer of the libelant (Thompson) and the respondent’s superintendent (Heanue) conversed about a day for docking the Patehogue, and arrived at an understanding that this would take place on June 3,1931. The latter asked if the former had docking plans, and was told that none were on hand, and they could be procured from Brooklyn.

Heanue says that ho casually stated that, if the plans were not provided, the operation of docking would be at the owner’s risk. This Thompson denies.

It is found that no such understanding as this was reached between the parties.

This does not mean that Heanue’s testimony is disbelieved, but it does mean that he did not put the matter so- dearly or plainly that Thompson understood him, or agreed to the suggestion. Nothing of the kind was presaged in the correspondence between the parties; the dimensions of the vessel as stated in the inquiry, and her shallow draft which was mentioned, suggested the shape and type of her under-side; and the fact that she had twin screws told of the struts on either side which supported the shafts.

If the operation could be undertaken only at the owner’s risk in the absence of docking plans, the owner was entitled to seasonable and more than casual notice to that effect.

The hauling took place between the hours of 2:00 and 4:30' on the afternoon of June 3rd, and is found to have been so contrived that a sag in the hull was developed in the undor-sides, near the stem, beginning at about 25 feet forward of the stern. The keel of the vessel was adequately supported by keel blocks, but the bilge blocks were not sufficiently in position aft, to sustain the strain imposed upon the structure of the vessel when her hull was lacking the support it received when afloat.

The bilge blocks were 8 in number, 4 on each side, spaced roughly 15 feet apart, beginning about 30 feet aft of the stem, and this placed the fourth one about 30 feet forward of the stern.

The overhang of the latter was supported by two substantial vertical shores, resting upon the ground, which were put in position after the vessel had been hauled; also by four supporting blocks (two on each side) aft of the bilge blocks and sustaining the counter, and inside the line of the bilge blocks. Of these latter, the forward two were put in place as the boat came out of the water, and the aft two thereafter. They were put in from each side separately.

An inspection of the under-side of the vessel revealed that the stern post, constituting the after end of the dead-wood (which rested upon a shoe which extended from the dead-wood aft to the forward under-side of the rudder) had fallen some % of an inch and caused a noticeable sag in the shoe. Thompson was present, and Heanue ealled his attention to this, and then inserted a jack under the stem post, and forced it upward into position.

The finding that there was a sag in the stem of the Patehogue as the result of placing her on the marine railway is based upon the testimony of the witness Ryan, who was engaged in his duties as a ship’s carpenter, in the cabin, while the operation was proceeding, and observed the upward thrust of some of the planks in the deck while so employed; and of Heanue, who observed evidence of strain on the day following, when the witness MacKenzie, a marine surveyor, inspected the vessel at the owner’s request; and of the witnesses Bagger and Terry, who observed evidence that one of the shafts was out of alignment when the vessel reached Shewan’s dry dock in Brooklyn, to which the vessel was taken following her experience at Bridgeport.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2 F. Supp. 513, 1932 U.S. Dist. LEXIS 1517, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-shore-nav-co-v-bridgeport-dredge-dock-co-nyed-1932.