South Port Corp. v. P. Olivier & Sons, Inc.

153 So. 825, 179 La. 233
CourtSupreme Court of Louisiana
DecidedFebruary 26, 1934
DocketNo. 32666.
StatusPublished
Cited by5 cases

This text of 153 So. 825 (South Port Corp. v. P. Olivier & Sons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Port Corp. v. P. Olivier & Sons, Inc., 153 So. 825, 179 La. 233 (La. 1934).

Opinion

BRUNOT, Justice.

This is a suit upon a contract for the purchase and sale of piling. The demand is for $2,102.85, the sum of the alleged loss: suffered by the plaintiff because the defendant refused to accept and pay for certain piles. There was judgment for the plaintiff for $897.75, with 5 per cent, per annum interest thereon from November 13,1932, until paid, and costs of the suit. From the judgment, the defendant appealed. The plaintiff has answered the appeal and prays that the judgment toe amended by increasing the amount of the *235 award to the sum prayed for, and, as thus amended, that it be affirmed.

The contract upon which the suit is based is as follows:

“December 6th, 1930.
“To Mess. P. Olivier & Sons, Lake Charles, La.
“We confirm having sold you the following: Southern Pine Line Pile, Rough Peeled.
“Original quotation on shorter lengths to apply, 401 — or less.
“Approximately 2700 Pcs. 6" tip, 10" butt, 3 feet from butt @10-%0 per linear foot.
“About 25,000 Lin Feet, of 45 ft. lengths to be shipped out immediately.
“We to be advised as to other lengths 6 to ¿ days' prior to your needing them.
“Piles to be in accordance with plans and specifications of the East Jefferson Water Works, No. 1 Project, up to 45' in length.
“Any piles delivered by us to job to be .010 per linear foot additional in price.
“It is understood and agreed that we are to furnish all piles on this job with the exception of 20,000 ■ linear feet already purchased by you elsewhere.
“Unless failure to deliver as set forth in shipment paragraph below.1
“Shipment .to be at the rate of 120 pieces or more per day beginning 12/12/30.
“All contracts conditioned upon delays and omissions due to strikes, fires and unavoidable accidents at our manufacturing aiid/or filling plants at Southport, Louisiana, and to causes beyond our control.
“Time of shipment beginning 12/12/30 as per above.
“Ship to P. Olivier & Price fob cars
Sons Armours switch
At Armours Switch, Shrewsbury, La.
Shrewsbury, La. Terms cash less 2%
10 days after deducting Freight.
Routing I. O. R. R.
“Kindly sign and return attached duplicate. “Accepted
“[Signed] P. Olivier & Sons, Inc.,
“By [Signed] F. Miller, V. P.
“Southport Corporation, Incorporated
“[Signed] J. W. Wood.”

The plaintiff alleges that prior to its receipt of written notice from the defendant, it had delivered, under the contract, 1,090 piles, for which it received payment; that it had made provision, and it should have been permitted, to deliver -the entire 2,700 piles called for by the contract; that when defendant’s written notice to cease deliveries was received, it had on hand 271 piles, the cost .of which, plus its profit thereon, totals the sum of $897.75; and that the delivery of the remaining 1,339 piles would have netted plaintiff a profit of $1,-205.10. The total of these sums is the sum sued for.

The defendant answered the suit, and, by way of reconvention, prayed for judgment, in reconvention, for $508.73. In its answer, the defendant admits the contract; it admits that the plaintiff began the delivery of piles on December S, 1930; it admits that it received and paid for 1,090 piles; and it admits that it gave the plaintiff written notice on December 18 and 19, 1930, to cease the *237 delivery of piles, -but it specially denies all other allegations of the petition, and, by way of reconvention, it alleges that plaintiff caused it to suffer the loss of 3,990 linear feet of piling at 11% cents per foot, toy shipping 45-foot length piling after verbal notice to cease shipping piling. It was on these issues- that the case was tried.

During the trial parole testimony was offered to explain the intention of the parties to the contract. The court assumed that the contract was a “firm order” for 2,700 piles, and for that reason it excluded the testimony, but after the ease was submitted it was discovered that the contract called for an approximate number of piles, and a judgment was rendered ordering the'case reopened for the reception of further evidence and appropriate orders and proceedings.

After the taking of further testimony, the case was again argued and submitted, and judgment was rendered in favor of the plaintiff and against the defendant for $1,701.51 with interest thereon at the rate of 5 per cent, per annum from November 13, 1931, and costs. On the trial of a motion for a rehearing it was ascertained that, through errors of calculation, the court had rendered judgment in favor of the plaintiff for a sum more than $'SOO in excess of the sum due it. Judgment was therefore rendered correcting these errors and reducing the award to the sum and interest stated in the first paragraph of this opinion.

With respect to the proper interpretation of the contract sued upon and the rights of the parties thereunder, the learned trial judge correctly says:

“The first essential is a correct understanding of the contract itself. It will be noticed that the piling to be furnished is to be in accordance with the plans and specifications of the water works project in which it was to toe used. Engineer Henning says that the plans and specifications were in effect at the time of the execution of the contract between the plaintiff and defendant, but that shortly thereafter a complete revision of the piling plans was ordered, without modifying the specifications. Mr. Wood, representative of the plaintiff, says that the defendant ordered forty-five foot piling, with the proviso that the lengths might be changed on a portion; and that the plaintiff took chances on the change. He explains that test piling had been driven at the time the contract was written, and Mr. Miller wrote into the contract the provision ‘original quotation on shorter lengths,’ to protect the defendant on prices already quoted for shorter and cheaper lengths.
“Mr. Stone, Engineer employed by the defendant, explains that- before December 6 test piling were driven and showed length of piling to be used in Division 7 as 45 feet, and that the piling plan for Division 8 was completed about December 29.
“Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oncale v. Aetna Cas. & Sur. Co.
417 So. 2d 471 (Louisiana Court of Appeal, 1982)
Hebert v. Police Jury of West Baton Rouge Parish
200 So. 2d 877 (Louisiana Court of Appeal, 1967)
Dupre v. Dupre
72 So. 2d 589 (Louisiana Court of Appeal, 1954)
Mente & Co. v. Roane Sugars, Inc.
6 So. 2d 731 (Supreme Court of Louisiana, 1942)
Snelling v. Adair
199 So. 782 (Supreme Court of Louisiana, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
153 So. 825, 179 La. 233, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-port-corp-v-p-olivier-sons-inc-la-1934.