South Louisiana Cement, Inc. v. Van Aalst Bulk Handling, B.V.

383 F.3d 297, 2004 U.S. App. LEXIS 18162, 2004 WL 1903311
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 26, 2004
Docket03-31184
StatusPublished
Cited by21 cases

This text of 383 F.3d 297 (South Louisiana Cement, Inc. v. Van Aalst Bulk Handling, B.V.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Louisiana Cement, Inc. v. Van Aalst Bulk Handling, B.V., 383 F.3d 297, 2004 U.S. App. LEXIS 18162, 2004 WL 1903311 (5th Cir. 2004).

Opinion

DeMOSS, Circuit Judge:

This is an appeal from the district court’s order sending all the claims and counterclaims in this litigation to arbitration, including the counterclaims of a non-signatory to the arbitration agreement who wanted to participant in the arbitration. The district court has not dismissed the case but rather stayed the proceedings pending the arbitration and administratively closed the case. We hold that because the district court ordered arbitration and there is no final decision, the orders are not immediately appealable and therefore this Court lacks jurisdiction.

BACKGROUND

This case arises out of the business relationships between Plaintiff-Counter De-fendanh-Appellant South Louisiana Cement, Inc. (hereafter “SLC”), Defendanb-Counter Claimant-Appellee PBC Services, Inc. (hereafter “PBC”), and Defendant Appellee Van Aalst Bulk Handling, B.V. (hereafter ‘Van Aalst”).

PBC is a Louisiana corporation based in Houma, Louisiana. The principal business of PBC is the leasing and operating of equipment to unload bulk cargo from vessels, particularly bulk cement. SLC is also a Louisiana corporation based in Port Allen, Louisiana. PBC and SLC have a business relationship going back several years. In 2001, the two corporations had an oral agreement under which PBC would provide the equipment and labor to unload bulk cement from vessels for SLC. For these services, SLC would pay a price per ton unloaded and would also guarantee a certain amount of work to be performed by PBC, expressed in a minimum of tons of bulk cement. In 2002, the two corporations entered into a written contract which, inter alia, required PBC to assist SLC in purchasing its own bulk cargo unloading equipment (“units”) from Van Aalst and to operate, and provide labor, fuel, repairs, and maintenance for, SLC’s purchased equipment. The written contract provided that SLC would pay PBC at the rate of $200,000 per annum per unit (based on *299 100,000 tons per annum at $2.00 per ton). If the tonnage were to exceed 200,000 combined from both units, then SLC would compensate PBC at $2.00 per ton for the tons in excess of 200,000.

Van Aalst is a limited liability company of the Netherlands. Van Aalst is a part owner of PBC. In 2002, SLC and Van Aalst entered into two contracts for the purchase of two used pneumatic ship un-loaders. The contracts provided for a limited warranty on certain components of the unloaders for a period of 12 months commencing after delivery. Both contracts also contained an express arbitration agreement which covered “any dispute ... arising out of or related to” the contract. The unloaders allegedly began experiencing mechanical problems shortly after SLC put them into service. Relations between SLC and Van Aalst and SLC and PBC deteriorated rapidly from that point. Litigation and this appeal ensued.

The litigation began in the United States District Court for the Eastern District of Louisiana on December 6, 2002. PBC filed suit against SLC alleging that SLC had breached an oral agreement to provide the minimum guaranteed tonnage agreed to between the parties and also alleged that SLC had breached its written contract to pay PBC as specified in the 2002 contract. In its answer to PBC’s amended complaint, SLC requested the Eastern District to abstain from ruling on the nonpayment claim, asserting that some of the unpaid invoices were the subject of a subsequently filed state court suit. SLC filed that related suit on April 2, 2002, in state court in Baton Rouge against co-defendant Van Aalst for breach of a warranty (pertaining to the bulk offloading equipment bought by SLC from Van Aalst) and, in the alternative, against PBC for failure to maintain and repair the unloaders. The suit was removed to the United States District Court for the Middle District of Louisiana on June 4, 2003. In its answer, Van Aalst asserted the defense that the failure of the unloaders was due to improper maintenance, thus implicating the 2002 contract between PBC and SLC. On October 6, 2003, PBC filed an answer and counterclaim in the Middle District litigation asserting an affirmative defense of set off against monies owed by SLC and asserting counterclaims for SLC’s failure to meet the minimum-tonnage guarantee and failure to make payments due. PBC voluntarily dismissed its action in the Eastern District on the grounds that it had asserted the same claims in the Middle District by counterclaim and that all claims arising from the business relationship of the three parties would, therefore, be pending before one court.

Previously, on August 15, 2003, Van Aalst had filed a motion to compel arbitration and a stay of litigation pending arbitration. On November 5, 2003, the Middle District granted the motion and ruled that all the claims filed in the underlying litigation, including PBC’s counterclaim, would be referred to arbitration. The ruling administratively closed the case pending a final arbitration decision. This appeal by SLC followed by Notice of Appeal filed on December 3, 2003.

DISCUSSION

Whether the district court’s orders constitute a final decision immediately appealable under 9 U.S.C. § 16.

The district court on November 5, 2003, granted Van Aalst’s motion to compel arbitration and to stay the litigation pending arbitration and ordered that all claims including SLC’s original claims and PBC’s *300 counterclaims should be arbitrated. 1 The court also denied SLC’s motion to transfer PBC’s counterclaim to the Eastern District and held that it was in the interest of justice and judicial economy to allow all the claims to be litigated at the same time in the Middle District. The court ordered the case “administratively closed pending a final arbitration decision.” Apparently, SLC attempted to continue discovery in the Middle District; and therefore on December 2, 2003, the court clarified that:

This case was administratively closed on November 5, 2003[,] because the Court granted a motion to compel arbitration. The case will remain closed until the arbitrator’s decision is received by the Court. All pending motions, including discovery motions, are stayed pending completion of the arbitration process. The Clerk will not accept any additional pleadings until the arbitrator’s decision is received by the Court.

No separate document embodying the orders has been entered as a final judgment.

Section 16 of the Federal Arbitration Act (“FAA”), 9 U.S.C. § 16, governs appellate review of arbitration orders. Congress’s intent in enacting § 16 was to favor arbitration, and it did so by authorizing immediate appeals from orders disfavoring arbitration and forbidding immediate appeals from orders favoring arbitration. Adams v. Ga. Gulf Corp., 237 F.3d 538, 540 (5th Cir.2001) (citing Forsythe Int’l, S.A. v. Gibbs Oil Co., 915 F.2d 1017, 1020 (5th Cir.1990)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Durbin v. McClendon
S.D. Mississippi, 2025
Durbin v. Walters
S.D. Mississippi, 2025
Adams v. Lumpkin
Fifth Circuit, 2023
Gross v. Keen Group Solutions
18 F.4th 836 (Fifth Circuit, 2021)
Psara Energy, Limited v. Space Shipping, Limited
946 F.3d 803 (Fifth Circuit, 2020)
Green Tree Servicing, L.L.C. v. Anthony Cha
872 F.3d 637 (Fifth Circuit, 2017)
Bordelon Marine, L.L.C. v. Bibby Subsea ROV, L.L.C.
685 F. App'x 330 (Fifth Circuit, 2017)
Garrett v. Alcorta
220 F. Supp. 3d 772 (W.D. Texas, 2016)
Patrick McCardell v. Regent Private Capital, L.L.C
520 F. App'x 259 (Fifth Circuit, 2013)
Arch Insurance v. Precision Stone, Inc.
584 F.3d 33 (Second Circuit, 2009)
Oyuela v. Seacor Marine (Nigeria), Inc.
198 F. App'x 370 (Fifth Circuit, 2006)
CitiFinancial Corp. v. Harrison
453 F.3d 245 (Fifth Circuit, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
383 F.3d 297, 2004 U.S. App. LEXIS 18162, 2004 WL 1903311, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-louisiana-cement-inc-v-van-aalst-bulk-handling-bv-ca5-2004.