South Lake Center Partnership v. Waker Associates, Inc.

879 P.2d 1342, 129 Or. App. 581, 1994 Ore. App. LEXIS 1203
CourtCourt of Appeals of Oregon
DecidedAugust 10, 1994
DocketC93-0004 CV; CA A79615
StatusPublished
Cited by3 cases

This text of 879 P.2d 1342 (South Lake Center Partnership v. Waker Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Lake Center Partnership v. Waker Associates, Inc., 879 P.2d 1342, 129 Or. App. 581, 1994 Ore. App. LEXIS 1203 (Or. Ct. App. 1994).

Opinion

*583 HASELTON, J.

Plaintiff South Lake Center Partnership (South Lake) appeals from a summary judgment entered for defendant Waker Associates, Inc. (Waker). It assigns error to the disposition of its “breach of contract” claim arising from Waker’s alleged deficient performance of project planning and engineering services. The trial court concluded that that claim sounded entirely in tort, not in contract and, thus, was time-barred under the general negligence statute of limitations, ORS 12.110(1). We affirm in part, reverse in part and remand.

The facts are largely undisputed. In November 1987, Spectra Novae, Ltd. (Spectra) entered into a written contract with Waker under which Waker agreed to provide engineering, surveying and planning services for the Taylor Crest Housing Project in Multnomah County. Of particular pertinence to this dispute, Waker was to prepare a design for the project, including alignment of storm drainage, sanitary and water systems, provide storm drain offset stakes at specified distances from manholes, and provide project consultation, coordination and observation/monitoring services. 1 The contract further provided that neither Spectra nor Waker was to assign its interest in the agreement or alter the terms of the contract “without written consent of the other.”

Waker began performing under the contract. Shortly thereafter, Spectra assigned its interest in the contract to South Lake and notified Waker of that assignment. Waker expressed no objection to the assignment and subsequently sent bills for its services to South Lake, and not to Spectra. South Lake fully paid those bills, and Waker accepted those payments without objection.

In October 1990, the Multnomah County Department of Environmental Services informed South Lake that storm fine “A” on the Taylor Crest project had been improperly placed, in that it was on or outside the county-approved east easement line, and would have to be relocated to conform with the county-approved construction plan. South Lake demanded that Waker undertake the relocation and, when *584 Waker refused, South Lake was obliged to retain others to perform the relocation, at an additional cost of approximately $34,000.

In January 1993, South Lake sued Waker for breach of contract and for negligence. The material allegations of South Lake’s complaint read:

“FIRST CLATM FOR. RET IFF
“(Breach of Contract)
* * * *
“5.
“Pursuant to the terms of the contract, defendant [Waker] was required to prepare a design for the development, including horizontal and vertical alignment for streets, storm drains, sanitary and water systems; prepare construction plans based on an approved preliminary plat; ánd provide sanitary sewer and storm drain offset stakes. The contract required that the services provided by defendant satisfy all public agencies having jurisdiction over the project.
<<* $ $ $ $
“7.
“On or about October 17,1990, the Multnomah County Department of Environmental Services advised plaintiff that storm line “A” of the project was not in accordance with the plans for the project approved by Multnomah County on or about June 6,1988, that the location of the storm line was on or outside of the east easement line and unacceptable to Multnomah County, that the line would have to be relocated in accordance with approved plans, and that the easement had not been properly drafted and was not consistent with the plans.
“8.
“The error and the inability of Multnomah County to approve the storm line was caused by defendant’s failure to perform its obligations under the contract, including its failure to prepare the design for the storm drainage, sanitary and water systems, failure to prepare and record the easement, failure to properly place the storm drain offset stakes and failure to provide observation of the work in progress.
*585 66* * * * *
“SECOND CLAIM FOR RELIEF “(Negligence)
66* * * * *
“13.
“Defendant was negligent in one or more of the following particulars:
“(a) In failing to properly prepare and record the easement for storm line “A” in accordance with the plans approved by Multnomah County;
“(b) In failing to properly stake the location for storm line “A” in accordance with the plans approved by Mult-nomah County;
“(c) In failing to properly design the storm drain system; and
“(d) In failing to provide proper observation for the work in process.”

Without filing an answer, Waker moved for summary judgment asserting: (1) South Lake could not sue under the contract because Waker had not consented to Spectra’s assignment of its interest to South Lake; (2) in the alternative, South Lake’s first claim for “breach of contract” sounded in tort (negligence), and not in contract, and was barred by the two-year limitation of ORS 12.110(1); 2 and (3) South Lake’s second claim for negligence was similarly time-barred. The circuit court, without ruling on the first argument, entered summary judgment on the second and third grounds.

South Lake assigns error only to the judgment against its first claim for breach of contract, asserting that that claim is subject to the six-year general contractual statute of limitations, ORS 12.080(1), 3 not ORS 12.010(1). *586 Seeurities-Intermountain, Inc. v. Sunset Fuel Co., 289 Or 243, 611 P2d 1158 (1980), guides our analysis of whether the particulars of that claim sound in contract or in tort.

In Seeurities-Intermountain, the assignee of a general contractor sued an architect and a heating subcontractor for installation of an allegedly defective heating system in an apartment complex. As in this case, the defendants sought, and obtained, summary judgment on the grounds that the plaintiffs claims were time-barred because they sounded in tort, not in contract. The Supreme Court reversed, holding that the plaintiff had alleged breaches of contractually specified standards of performance, which were distinct from a general noncontractual standard of care:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wright v. State Farm Mutual Automobile Insurance
196 P.3d 1000 (Court of Appeals of Oregon, 2008)
Soliz v. Jimenez
193 P.3d 34 (Court of Appeals of Oregon, 2008)
Duncan v. Office Depot
973 F. Supp. 1171 (D. Oregon, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
879 P.2d 1342, 129 Or. App. 581, 1994 Ore. App. LEXIS 1203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-lake-center-partnership-v-waker-associates-inc-orctapp-1994.