South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission

261 F.2d 915, 1958 U.S. App. LEXIS 5381, 27 P.U.R.3d 198
Court of Appeals for the Fourth Circuit·Decided December 19, 1958·No. 7745·Published·Cited by 9 cases

Opinion

SOPER, Circuit Judge.

On the prior appeal in this case, 4 Cir., 249 F.2d 755, we had before us a decision and order of the Federal Power Commission of October 24, 1956, 16 F.P.C. 52, which reduced the contract rate at which the Generating Company, a South Carolina corporation, furnished electric energy to Georgia Power Company, a Georgia corporation, from the Urquhart plant on the Savannah River near North Augusta, South Carolina. The rate was reduced from $22.50 to $21.948 per KWH per annum. We held that the Commission had the power to alter the rate fixed by the contract and to impose a new rate based upon the cost of service, and then considered specific objections that the new rate was unjust and unreasonable and did not afford a fair return to the producer. These objections related to:

(1) the amount allowed the utility for interest on funds used by the utility during the course of construction;

(2) the elimination from the contract of an automatic escalator clause designed to increase or decrease the rate in case of variations between the estimated and actual amount of investment and of expenses of operation of the plant; and

(3) the amount allowed by the Commission in its computation of income taxes which was fixed at the amount paid by the Generating Company as a separate entity rather than the amount paid by the corporate system as a whole, of which the Generating Company was a wholly owned subsidiary.

Upon an examination of the Commission’s opinion, we did not find a completely satisfactory explanation of its *917 essential findings on these points and accordingly, in conformity with the practice approved in Colorado-Wyoming Gas Co. v. F.P.C., 324 U.S. 626, 634, 65 S.Ct. 850, 89 L.Ed. 1235, we suspended the Commission’s order and remanded the case for further explanations. In response thereto the Commission filed a supplemental opinion and order on June 2, 1958, in which it offered additional explanations and reaffirmed its prior order. As to the matter of interest, the Commission explained that the allowance of interest at 6 per cent on the funds used during construction rather than the larger rate normally expected by investors upon an investment was in accord with established accounting practices and the decision of the courts. We accept this explanation.

As to the elimination of the escalator clause, the Commission pointed out that the contract adjustment clause related to variable factors of the contract rate and therefore could not be applied to the rate determined by the Commission on the basis of cost of service; and also that the Generating Company could at any time submit to the Commission a requirement or proposal for an adjustment clause that would reflect changes in cost of service. We accept this explanation.

We find, however, no adequate explanation of the Commission’s position on the income tax matter. Nothwithstanding the fact that the Generating Company is merely a subsidiary corporation of an electric utility system, the Commission, in computing the cost of supplying the electric service, took into account only the income taxes which the Generating Company is obliged to pay as a separate corporate entity but failed to include the additional tax incurred by the corporate system as a whole because of the establishment and operation of the subsidiary body. As will appear from our earlier opinion, the Federal income taxes of the subsidiary corporation were $217,434 and the State income taxes $43,854, or a total of $261,288; but the taxes calculated on the system as a whole amounted to: Federal income taxes $398,002 and State income taxes $53,377, or a total of $450,379.

The additional tax burden on the system as a whole was caused by the circumstances under which the project was undertaken. It was initiated by the South Carolina Electric and Gas Company (E&G), a South Carolina corporation; and the Generating Company was incorporated as a fully owned subsidiary of E&G to put the project into effect. The plant had a rated capacity of 150,000 KW, which was supplied under contract between the Generating Company and the consumers as follows:

30.000 KW to E. 1. du Pont de Ne-mours & Company, primary contractor of the Atomic Energy Commission at its Savannah Hydrogen-Bomb Project,

45.000 KW to E&G, the parent body for distribution to its customers in South Carolina, and

75.000 KW to Georgia Power Company for distribution to its customers in Georgia.

The rate fixed by the contracts with these consumers consisted of an energy charge of $.00315 per KWH, which is not in dispute, plus a capacity charge. In the du Pont contract the capacity charge was fixed at $15.30 per KW per annum to which was added a fixed charge of $3.70 per KW, resulting in a total capacity charge of $19.00 per KW per an-num. In the Georgia Power contract $7.20 per KW per annum was added to the basic capacity charge of $15.30 per KW per annum. The contract with the parent company (E&G) provided for a total capacity charge of $15.30 per KW per annum with no additional fixed charge. The larger price charged to Georgia Power was not due to greater costs of service but was fixed by contract between E&G and Georgia Power, wherein it was agreed that the net saving of $600,000 per annum made by Georgia Power by purchasing energy from the Urquhart plant rather than building and operating a generating plant of its own should be divided between E&G and Georgia Power.

*918 It is shown in our prior opinion' that this arrangement was advantageous to all parties concerned. Georgia Power, whose contract alone came within the jurisdiction of the Federal Power Commission, paid a higher contract rate than the others but it saved the substantial amount indicated above.

Free access — add to your briefcase to read the full text and ask questions with AI

South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission, 261 F.2d 915, 1958 U.S. App. LEXIS 5381, 27 P.U.R.3d 198 (4th Cir. 1958).

261 F.2d 915 (South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ohio Water Service Co. v. Public Utilities Commission
412 N.E.2d 397 (Ohio Supreme Court, 1980)
Mystic Valley Gas Co. v. Department of Public Utilities
269 N.E.2d 233 (Massachusetts Supreme Judicial Court, 1971)
Cities of Lexington v. Federal Power Commission
295 F.2d 109 (Fourth Circuit, 1961)