South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission

261 F.2d 915, 1958 U.S. App. LEXIS 5381, 27 P.U.R.3d 198
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 19, 1958
Docket7745
StatusPublished
Cited by9 cases

This text of 261 F.2d 915 (South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Carolina Generating Company v. Federal Power Commission and Georgia Public Service Commission, 261 F.2d 915, 1958 U.S. App. LEXIS 5381, 27 P.U.R.3d 198 (4th Cir. 1958).

Opinion

SOPER, Circuit Judge.

On the prior appeal in this case, 4 Cir., 249 F.2d 755, we had before us a decision and order of the Federal Power Commission of October 24, 1956, 16 F.P.C. 52, which reduced the contract rate at which the Generating Company, a South Carolina corporation, furnished electric energy to Georgia Power Company, a Georgia corporation, from the Urquhart plant on the Savannah River near North Augusta, South Carolina. The rate was reduced from $22.50 to $21.948 per KWH per annum. We held that the Commission had the power to alter the rate fixed by the contract and to impose a new rate based upon the cost of service, and then considered specific objections that the new rate was unjust and unreasonable and did not afford a fair return to the producer. These objections related to:

(1) the amount allowed the utility for interest on funds used by the utility during the course of construction;

(2) the elimination from the contract of an automatic escalator clause designed to increase or decrease the rate in case of variations between the estimated and actual amount of investment and of expenses of operation of the plant; and

(3) the amount allowed by the Commission in its computation of income taxes which was fixed at the amount paid by the Generating Company as a separate entity rather than the amount paid by the corporate system as a whole, of which the Generating Company was a wholly owned subsidiary.

Upon an examination of the Commission’s opinion, we did not find a completely satisfactory explanation of its *917 essential findings on these points and accordingly, in conformity with the practice approved in Colorado-Wyoming Gas Co. v. F.P.C., 324 U.S. 626, 634, 65 S.Ct. 850, 89 L.Ed. 1235, we suspended the Commission’s order and remanded the case for further explanations. In response thereto the Commission filed a supplemental opinion and order on June 2, 1958, in which it offered additional explanations and reaffirmed its prior order. As to the matter of interest, the Commission explained that the allowance of interest at 6 per cent on the funds used during construction rather than the larger rate normally expected by investors upon an investment was in accord with established accounting practices and the decision of the courts. We accept this explanation.

As to the elimination of the escalator clause, the Commission pointed out that the contract adjustment clause related to variable factors of the contract rate and therefore could not be applied to the rate determined by the Commission on the basis of cost of service; and also that the Generating Company could at any time submit to the Commission a requirement or proposal for an adjustment clause that would reflect changes in cost of service. We accept this explanation.

We find, however, no adequate explanation of the Commission’s position on the income tax matter. Nothwithstanding the fact that the Generating Company is merely a subsidiary corporation of an electric utility system, the Commission, in computing the cost of supplying the electric service, took into account only the income taxes which the Generating Company is obliged to pay as a separate corporate entity but failed to include the additional tax incurred by the corporate system as a whole because of the establishment and operation of the subsidiary body. As will appear from our earlier opinion, the Federal income taxes of the subsidiary corporation were $217,434 and the State income taxes $43,854, or a total of $261,288; but the taxes calculated on the system as a whole amounted to: Federal income taxes $398,002 and State income taxes $53,377, or a total of $450,379.

The additional tax burden on the system as a whole was caused by the circumstances under which the project was undertaken. It was initiated by the South Carolina Electric and Gas Company (E&G), a South Carolina corporation; and the Generating Company was incorporated as a fully owned subsidiary of E&G to put the project into effect. The plant had a rated capacity of 150,000 KW, which was supplied under contract between the Generating Company and the consumers as follows:

30.000 KW to E. 1. du Pont de Ne-mours & Company, primary contractor of the Atomic Energy Commission at its Savannah Hydrogen-Bomb Project,

45.000 KW to E&G, the parent body for distribution to its customers in South Carolina, and

75.000 KW to Georgia Power Company for distribution to its customers in Georgia.

The rate fixed by the contracts with these consumers consisted of an energy charge of $.00315 per KWH, which is not in dispute, plus a capacity charge. In the du Pont contract the capacity charge was fixed at $15.30 per KW per annum to which was added a fixed charge of $3.70 per KW, resulting in a total capacity charge of $19.00 per KW per an-num. In the Georgia Power contract $7.20 per KW per annum was added to the basic capacity charge of $15.30 per KW per annum. The contract with the parent company (E&G) provided for a total capacity charge of $15.30 per KW per annum with no additional fixed charge. The larger price charged to Georgia Power was not due to greater costs of service but was fixed by contract between E&G and Georgia Power, wherein it was agreed that the net saving of $600,000 per annum made by Georgia Power by purchasing energy from the Urquhart plant rather than building and operating a generating plant of its own should be divided between E&G and Georgia Power.

*918 It is shown in our prior opinion' that this arrangement was advantageous to all parties concerned. Georgia Power, whose contract alone came within the jurisdiction of the Federal Power Commission, paid a higher contract rate than the others but it saved the substantial amount indicated above.

The Generating Company was incorporated as a subsidiary of E&G to construct and operate the plant because it was found that the low rates demanded by du Pont for the energy furnished to it would not be possible under conventional utility financing, since the bonded debt of E&G was restricted by its mortgage to 60 per cent of the total of any additions to its property. To meet this situation the Generating Company was formed with a debt ratio of 75 per cent in mortgage bonds and 15 per cent in ten-year notes, and with 10 per cent in common stock, all of which was purchased by E&G. This method of financing provided money at a low cost and made possible the lower rates acceptable to du Pont. It also resulted in lower income taxes of the Generating Company since its high interest payments were deductible from its taxable income. But, on the other hand, the income tax of E&G was increased because it was obliged to maintain a low debt ratio and a high common equity ratio in order to protect its financial standing and market the system’s securities. This need was accentuated when the project was undertaken, for it then became necessary for the parent company to guarantee debt principal and interest and commitment fees of the undertaking, and also to provide funds for investment in the common stock of the subsidiary by the sale of equity securities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Water Service Co. v. Public Utilities Commission
412 N.E.2d 397 (Ohio Supreme Court, 1980)
Mystic Valley Gas Co. v. Department of Public Utilities
269 N.E.2d 233 (Massachusetts Supreme Judicial Court, 1971)
Cities of Lexington v. Federal Power Commission
295 F.2d 109 (Fourth Circuit, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
261 F.2d 915, 1958 U.S. App. LEXIS 5381, 27 P.U.R.3d 198, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-carolina-generating-company-v-federal-power-commission-and-georgia-ca4-1958.