South Carolina Generating Co. v. Federal Power Commission

249 F.2d 755
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 23, 1957
DocketNos. 7391, 7393
StatusPublished
Cited by3 cases

This text of 249 F.2d 755 (South Carolina Generating Co. v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Carolina Generating Co. v. Federal Power Commission, 249 F.2d 755 (4th Cir. 1957).

Opinions

SOPER, Circuit Judge.

South Carolina Generating Company and the South Carolina Public Service Commission filed these petitions for review of an order of the Federal Power Commission reducing rates on the wholesale purchase of electric energy established in a long-term contract negotiated at arm’s length in interstate commerce between the Generating Company, the selling utility, and the Georgia Power Company, the purchasing utility.

The Generating Company is a South Carolina corporation formed to construct and operate a steam electric generating station known as Plant Urquhart, located near North Augusta, South Carolina, on the Savannah River. The Urquhart plant as originally built had a rated capacity of 150,000 KW made up of two 75,000 KW generators. The entire capital stock of the Generating Company is owned by the South Carolina Electric and Gas Company (E & G), a South Carolina electric utility, which distributes and sells electric energy in a large area of South Carolina. Georgia Power Company (Georgia Company), an intervener here, generates and distributes energy throughout the State of Georgia. The South Carolina Public Service Commission is charged with general utility regulation within South Carolina; its counterpart in Georgia is the Georgia Public Service Commission, a respondent in both cases.

E & G, in common with most other utilities in the electric power industry, experienced a substantial increase in business during the post-war years, and during this period had frequently been confronted with the necessity of adding to its generating capacity. In the summer of 1950, plans were being studied for the purpose of locating additional facilities for E & G in its service area in the western central portion of the state, special consideration being given to a site near Brancheville, South Carolina, and certain plant equipment was on order for delivery in August, 1952. Before final plans were completed and a definite site chosen, the Atomic Energy Commission announced that the Savannah River Hydrogen Bomb Project would be located about fifty miles west of the Brancheville site under consideration. The location of the project in E & G’s service area would be of substantial economic benefit to the utility, since the Project would require large quantities of dependable energy and would bring with it additional commercial and residential consumers. Accordingly, E & G advised E. I. du Pont de Nemours and Company, prime contractor for the A.E.C., that it was prepared to construct additional facilities in the area of the proposed Project which could supply the A.E.C.’s power requirements. The initial rates proposed by E & G during negotiation were rejected by du Pont as excessive. Lower rates, however, would have been impossible under conventional utility financing, since E & G’s mortgage, like most utility mortgages, restricted bonded indebtedness to 60 per cent of the total of any property additions. Money to finance the proposed power facilities was needed at a low cost in order to make possible the low rates required by du Pont. To overcome this obstacle, the Generating Company was formed by E & G for the purpose of financing construction of the steam generating station at Urquhart, which could supply the required capacity to A.E.C. The new corporation was financed on a debt ratio of 90 per cent — 75 per cent in mortgage bonds, 15 per cent in ten-year notes, and the remaining 10 per cent in common stock which was purchased by E & G. This high debt financing provided money at a low cost and made possible lower rates to A.E.C., and consequently, du Pont agreed to accept a capacity of 30,000 KW from one of the generating units to be constructed at the new plant. The financing of the Generating Company was made possible [758]*758by certain commitments and guarantees of E & G hereinafter more fully described.

The Georgia Company at about the same time was also in need of additional power and was contemplating the construction of a one unit steam station near Augusta, Georgia, on the Savannah River across from the Urquhart site. Officials of E & G notified the Georgia Company of their plans to build the two unit 150,000 KW capacity at Urquhart, financed through the Generating Company. Both utilities instituted independent cost studies to determine whether the cost of purchasing the required capacity for the Augusta area from the Generating Company would result in savings to the Georgia Company over the costs entailed in constructing their own facilities to supply the additional capacity. Thereupon, on November 19, 1951, after some negotiation, a long-term contract for the sale of the capacity of one of the 75,000 KW units to be built at the Urquhart plant was entered into between the Georgia Company and the Generating Company. On the same day, E & G contracted to purchase the remainder of the capacity of the other unit not required by the A.E. C., amounting to 45,000 KW. Nearly a year and a half later, on March 9, 1954, after the Urquhart plant was put into operation, du Pont executed a contract with the Generating Company for the purchase of 30,000 KW to which E & G was made a party.

The Georgia Power contract, the one in issue here, is for a period of twenty-five years, and provides for a two-part rate consisting of an energy charge and a capacity charge. The energy charge, which is not in dispute, is based upon fuel and maintenance costs plus taxes not related to income and is established initially in the contract at the rate of $.00315 per KWH. The capacity charge, computed on a KW basis, is divided into three components. The first is a finance component designed to provide interest and amortization of the 90 per cent debt n twenty-five years and an 8 per cent return on equity, and results in a figure of $10.50 per KW per annum. The second is an operations component including operating, administrative, and general expenses not included in the energy charge, which amounts to $4.80 per KW per annum. The total of these components constitutes the basic capacity charge of $15.30 per KW per annum. To this basic capacity charge is added the third component, a fixed charge of $7.20 per KW per annum, which does not relate to any costs on the books of the Generating Company but was designed to divide equally between the Generating Company and the Georgia Company the savings accruing, to the Georgia Company from the agreement as compared with the costs of construction and operation of a generating station of its own. Thus, the contract provides for a total capacity of $22.50 per KW per annum.

The net savings to the Georgia Company as a result of this contract were estimated at $5.38 per KW per annum in capacity costs, or a total of $403,-500.00 per annum. Annual savings in respect of the fuel or maintenance were estimated at between $175,000.00 and $200,000.00. Thus total savings to the Georgia Company through the purchase of its requirements from the Generating Company amounts to approximately $600,000.00 each year.

Among the other provisions of the contract is an article which subjects the capacity charge to an escalation formula for variations between the estimated and the actual investment and between the estimated and the actual expenses and taxes. Similar provisions are made in regard to the energy charge. In addition, a “recapture clause” provides that upon twelve months’ notice the Generating Company may reduce the total contract capacity of the Georgia Company by 25,000 KW, and on thirty months' notice it may terminate the agreement and recapture the entire contract capacity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
249 F.2d 755, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-carolina-generating-co-v-federal-power-commission-ca4-1957.