Sound Ship Building Corp. v. United States

158 Ct. Cl. 1, 1962 U.S. Ct. Cl. LEXIS 177, 1962 WL 9268
CourtUnited States Court of Claims
DecidedJuly 18, 1962
DocketNo. 549-58
StatusPublished
Cited by1 cases

This text of 158 Ct. Cl. 1 (Sound Ship Building Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sound Ship Building Corp. v. United States, 158 Ct. Cl. 1, 1962 U.S. Ct. Cl. LEXIS 177, 1962 WL 9268 (cc 1962).

Opinion

Davis, Judge,

delivered the opinion of the court:

A contractor with the Bureau of Ships of the Navy Department sues for extra work performed under its contract. The parties agree that the work was done and would normally be compensable under the changes article. The single defense to payment is that the contractor while seeking extra-contractual financial relief from the Navy — in the course of performance, and before the present contractual claims had been administratively determined — induced the Navy to grant an adjustment as of grace by representing that no further legal claims of the kind now pressed would be presented. The Trial Commissioner’s findings, which we adopt (with one change in finding 19), show that the evidence does not support this defense. It must therefore be rejected.1

In June 1952 plaintiff entered into a contract with the Bureau of Ships to construct twelve diesel wood patrol boats, to be completed by September 30, 1954. During performance in 1953 and 1954, work was ordered by the Bureau which plaintiff deemed beyond the requirements of the contract, but in accordance with the accepted procedure it performed the additional work, incurring increased costs. [3]*3Bequests for extra compensation (under the standard changes article of the contract) were made for some of these additional items before the end of May 1954; as to others the requests were made thereafter and in some instances not until the early part of 1956, considerably after the completion of all work in December 1954. There is no doubt that the work was actually done.

Toward the close of May 1954, plaintiff, which was then performing for the Navy a contract to construct five steel barges as well as the patrol boat contract on which its present petition is grounded, told the Bureau of Ships that it was running into very heavy losses and would not be able to complete its Navy obligations without substantial financial assistance. The Bureau suggested that the plaintiff apply for extra-contractual help under Title II of the First War Powers Act which permitted the defense agencies to amend contracts so as to increase the prices, without consideration from the contractor, where that was necessary to aid the defense effort. Programs and procedures had been developed by the agencies during World War II for considering requests for relief under Title II,2 and in modified form these continued after the close of the war. In the Navy, in 1954, definitive action on such requests was taken by the Contract Adjustment Board, but the operating bureau concerned with the contract first reviewed the request and made recommendations to the Board.

On May 31, 1954, plaintiff filed an elaborate request for First War Powers Act relief on both of its contracts, “in a sum not to exceed $506,657.13.” This request dealt with the possibilities of other sources of further financing and specifically referred to anticipated increases in contract prices, through change orders, of “perhaps $85,000.00.” See findings 18,25. Thereafter, plaintiff’s vice-president, Starr, had a conversation with a representative of the Bureau of Ships (Lucisano) directed to the contractor’s statement that official [4]*4change orders still to be finally adjudicated, along with requested change orders not yet acted upon, totaled “perhaps $85,000.00.” The Navy desired to know more about this sum because any monies which could be expected to be due under the contract would reduce (or perhaps obviate) the need for financial relief as a matter of grace. In explaining the makeup of the $85,000, Starr did not mention most of the items now in suit but he did say that the contractor would continue to press certain unspecified requests for change orders which the Bureau had refused to approve; that other requests were still pending at various stages; and that the contractor intended to file in the future further requests for change orders. On this basis Starr expressed the belief that plaintiff was entitled to at least $85,000. See finding 19.

The Bureau did not rest on the plaintiff’s own estimates of costs, losses, and amounts probably payable on outstanding claims for changes, but made its own investigations and exercised its own judgment. On the basis of the information submitted by the plaintiff and obtained through its own inquiries, the Bureau proposed and forwarded to the Contract Adjustment Board, on August 18, 1954, its detailed analysis of the plaintiff’s request for First War Powers Act relief, together with the recommendation that a total (on both Navy contracts) of only $125,000 be granted. Supplementary statements of facts and recommendations were transmitted by the Bureau to the Board early in September 1954. The Bureau’s presentation did not at any time say that plaintiff had no further claim for additional costs or would have no further claims.

The application for relief was then reviewed by the Technical Assistant to the Contract Adjustment Board who suggested that a total of only $65,000 (apparently thereafter reduced to $58,000) be allowed.3 The Board considered the request at a meeting on September 2, 1954, which was not attended by any representative of the plaintiff (although it had been advised that one could be present).

The Adjustment Board, on September 8,1954, authorized an increase (without consideration) of the total price of both [5]*5contracts by $74,000, the amount the Board considered sufficient to enable the plaintiff to complete its two Navy contracts. The Board’s opinion discussed various pertinent considerations but did not refer to any representation by plaintiff as to the extent of possible legal claims for contract changes. About ten days later, the plaintiff, insisting that the amount awarded was inadequate and based on erroneous assumptions and calculations, requested an additional increase of $82,473.14. On October 5,1954, the Board authorized a further increase of not to exceed $45,000. Again, the written explanation of the Board’s decision did not rely on any representations by plaintiff as to amounts recoverable under possible change orders.

With the aid of this relief under the First War Powers Act plaintiff completed its work on the patrol boat contract on December 24,1954. It continued to present and the Navy to process — before, during, and after the period in which its request for extra-contractual relief was being considered— various requests for extras and changes under the two contracts it was performing. Some of these requests were granted and some denied, but all were considered on their merits. With respect to such claims presented or urged in the years 1954 through 1957, the Bureau did not at any time take the position that plaintiff had estopped itself by representations made when it applied in 1954 for a First War Powers Act adjustment.

In the early part of 1956, over a year after completion of the patrol boat contract, plaintiff submitted to the contracting officer, under the disputes clause, consolidated claims covering the items for which compensation is now sought.4 In March 1958, the contracting officer found that plaintiff had performed all except one of these items of extra work at Bureau direction and at an increased cost of $52,009.30. He rejected one item, the “as-constructed” drawings, as not extra work. He refused, however, to issue change orders compensating plaintiff for any of the extra work because, in his view, [6]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
158 Ct. Cl. 1, 1962 U.S. Ct. Cl. LEXIS 177, 1962 WL 9268, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sound-ship-building-corp-v-united-states-cc-1962.