Sossong v. Shaler Area School District

945 A.2d 788, 2008 Pa. Commw. LEXIS 98, 2008 WL 596766
CourtCommonwealth Court of Pennsylvania
DecidedMarch 6, 2008
Docket979 C.D. 2007
StatusPublished
Cited by4 cases

This text of 945 A.2d 788 (Sossong v. Shaler Area School District) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sossong v. Shaler Area School District, 945 A.2d 788, 2008 Pa. Commw. LEXIS 98, 2008 WL 596766 (Pa. Ct. App. 2008).

Opinion

OPINION BY

Judge FRIEDMAN.

Roger Sossong (Sossong) appeals from the April 25, 2007, and May 14, 2007, orders of the Court of Common Pleas of Allegheny County (trial court). The April 25, 2007, order, which was issued by The Honorable Timothy Patrick O’Reilly, denied Sossong’s first motion for a preliminary injunction (First Motion) against the Shaler Area School District (School District). The May 14, 2007, order, which was issued by The Honorable Michael A. Della Vecchia, denied Sossong’s request for a hearing on his second motion for a preliminary injunction (Second Motion) against the School District. We affirm.

On April 25, 2007, Sossong appeared before Judge O’Reilly with the First Motion against the School District. In the First Motion, Sossong alleged that: (1) in March, the School District sought bids for work on two school construction projects, (First Motion, ¶¶ 1-2, R.R. at 31a); (2) in the bid documents, the School District required all bidders, union or non-union, to enter into a Project Labor Agreement (PLA), (First Motion, ¶ 5, R.R. at 32a); (3) the terms of the PLA prevent non-union contractors from effectively bidding on the projects, such that the provision violates lowest responsible bidder laws, (First Motion, ¶¶ 6-8, R.R. at 32a); and (4) the School District would be awarding the contracts at a school board meeting later that same day, (First Motion, ¶ 11, R.R. at 32a). Sossong sought to preliminarily enjoin the School District from awarding the contracts. (R.R. at 33a-34a.)

Sossong attached to his First Motion a copy of a Complaint in Equity (Complaint) that he had filed with the trial court on April 24, 2007. The Complaint alleged that: (1) the School District decided to include the PLA requirement in its bid documents after the Pittsburgh Regional Building and Construction Trades Council (Trades Council) informed the School District that a PLA would ensure that the projects were completed on schedule and on budget, (Complaint, ¶¶ 19-20, R.R. at 41a); (2). the School District received only one or two bids from non-union contractors, (Complaint, ¶ 35, R.R. at 44a); (3) the PLA requirement deterred other non-union contractors from submitting bids, (Complaint, ¶ 37, R.R. at 44a); and (4) because competition for the contracts was significantly reduced, the cost of the pro *791 jects will likely be greater, 1 (Complaint, ¶ 38, R.R. at 44a).

Sossong attached the PLA provision from the School District’s bid documents to his Complaint as Exhibit A. The provision provides, in pertinent part, as follows:

1.1 The [School District] and the [Trades Council] have entered into a[PLA] in connection with all work to be performed on the District’s anticipated construction contracts.... The [PLA] ... is designed to maintain labor/management harmony and, therefore, the expeditious completion of the project on-time and on-budget.
1.2 The [PLA] precludes strikes, lockouts, work stoppages and any other disruptions of the work for the duration of the project. All contractors, both union and non-union, must sign and be bound by the terms of the [PLA], This mandatory requirement does not preclude any contractors, union or non-union, from bidding on and being awarded a contract.

(R.R. at 48a) (emphasis added).

Sossong attached the PLA, itself, to his Complaint as Exhibit B. (R.R. at 49a-63a.) Section 1.3(A)(1) of the PLA states that its intent is to “foster the achievement of a timely and on-budget completion” of the projects. (R.R. at 50a.) Section 1.2(B)(2) of the PLA states that the parties understand that “time is of the essence,” and that it is “essential that construction work ... be done in an efficient, economical manner with optimum productivity and no delays.” (R.R. at 50a) (emphasis in original).

At the same time Sossong appeared with his First Motion before the trial court, the Trades Council appeared with a motion to intervene, which was granted. (R.R. at 69a.) Sossong, the School District and the Trades Council presented argument, after which Judge O’Reilly denied Sossong’s First Motion. Judge O’Reilly explained his ruling in a subsequent opinion.

At argument, I denied the [First] Motion, and I deemed a hearing thereon to be unnecessary in view of the circumstances then existing. In particular, the award of the contract was to be made that night by [the School District]. Obviously, this would have an adverse impact on the public interest. Further ... the relief sought was an Order voiding the [PLA], which would necessitate rebidding of the entire project, which would create further delay, and adversely impact the public interest. Finally, I said from the bench that I did not see that an equitable issue lay in the case, inasmuch as citizen [Sossong’s] remedy was a surcharge action against [the School District’s] Board Members, if the award under existing circumstances proved to be a waste of [the School District’s] money.[ 2 ]

(Judge O’Reilly’s op. at 4). Judge O’Reilly further stated that his decision is supported by A Pickett Construction, Inc. v. Luzerne County Convention Center Authority, 738 A.2d 20 (Pa.Cmwlth.1999) (upholding the inclusion of a PLA require *792 ment in bidding documents), 3 and the fact that Sossong had notice of the PLA requirement at least from the time that the School District published the bid solicitation in March 2007. (Judge O’Reilly’s op. at 5-6.) Finally, Judge O’Reilly noted that the School District’s projects are subject to the Pennsylvania Prevailing Wage Act (Prevailing Wage Act); 4 thus, the likelihood that union workers would be paid more than non-union workers, resulting in a monetary loss to taxpayers, is extremely remote. (Judge O’Reilly’s op. at 6.)

On May 9, 2007, Sossong filed an Amended Complaint and Second Motion at the same docket number and without leave of court. In the Amended Complaint, Sos-song added averments that: (1) recognized the Trades Council as intervener; (2) challenged Judge O’Reilly’s April 25, 2007, order; (3) questioned the applicability of Pickett; (4) recognized that the School District awarded the contracts on April 25, 2007; and (5) stated that the projects are scheduled to begin in June 2007. (Amended Complaint, ¶¶4, 9-11, 40-47, 65, 70.) In the Second Motion, Sossong argued that, unlike the government entity in Pickett, the School District included the PLA requirement in its bid documents without conducting a study. (Second Motion, ¶ 14, R.R. at 106a.) Sossong sought in his Second Motion to enjoin the beginning of work in June 2007.

The School District filed a response to Sossong’s Second Motion, alleging that it did conduct a study, which included a review of a report entitled “Labor Analysis and Report on Feasibility for a Project Labor Agreement on the Construction Phases for the Baldwin High School” (Hill Report), prepared in September 2005 by Hill International for the Baldwin-Whitehall School District.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.D. Eckman, Inc. v. Dep't of Transp.
202 A.3d 832 (Commonwealth Court of Pennsylvania, 2019)
Allan Myers, L.P. v. Dep't of Transp.
202 A.3d 205 (Commonwealth Court of Pennsylvania, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
945 A.2d 788, 2008 Pa. Commw. LEXIS 98, 2008 WL 596766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sossong-v-shaler-area-school-district-pacommwct-2008.