Sorrentino v. State

22 Misc. 2d 330, 201 N.Y.S.2d 429, 1960 N.Y. Misc. LEXIS 2866
CourtNew York Court of Claims
DecidedJune 6, 1960
DocketClaim No. 34905
StatusPublished
Cited by1 cases

This text of 22 Misc. 2d 330 (Sorrentino v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sorrentino v. State, 22 Misc. 2d 330, 201 N.Y.S.2d 429, 1960 N.Y. Misc. LEXIS 2866 (N.Y. Super. Ct. 1960).

Opinion

Alexander Del Giorno, J.

Floyd F. iSorrenti.no, who was a funeral director and emibalmer for 20 years, and who, since 1951, had ibid for and performed six other contracts with the State for the removal of bodies from cemeteries affected by highway construction, entered into the present contract with the State of New York on the 25th day of January, 1956 for the: Removal of all human remains from the burial ground on [331]*331Map 21, Parcel 24, City of Amsterdam, Route 5-S, Arterial Connection, City of Amsterdam, County of Montgomery.”

Prior to the contract, but after receiving copy of notice of bids, claimant stated that he went to the site to examine the cemetery and gather information concerning the number of bodies to be removed and the manner of best accomplishing the same. At the cemetery proper he saw many broken headstones and the outlines of a road already cut through by the general highway contractor. At and around this cut he saw bones and caskets sticking out of the ground. He inquired of the church and neighbors and was told that this cemetery, which was a Catholic cemetery, belonged to St. Mary’s Parish in Amsterdam, and had not been used for 50 years or more. He further testified that the area of the cemetery was some 3% acres. The claimant asserted that from his investigation he had formed an opinion that there were some 4,000 bodies buried in that cemetery. He gave this opinion to Mr. John S. Hadala, the State engineer in charge of that highway construction, who told claimant that, in his opinion, and from what he had been able to ascertain, there were no such number of bodies.

Claimant testified further that he started the work of removing bodies on April 11,1956, in the presence of George C. Gifford, a State engineer, who had been placed in charge of the removal process, and Father Edward H. Gilmour, the assistant to Monsignor Walsh, who was the pastor of St. Mary’s Church. They had a conference at the site, and all agreed that, as the digging went on, where an outline of a casket was indicated, that was to be considered as a grave whether there were any visible remains of the content or not. The parties agreed that, where there had been a casket, although it was now entirely decomposed, the deteriorated lumber of the casket left a discoloration in the ground that clearly marked its previous existence and shape.

Father Gilmour testified that where only such outline was indicated, nevertheless it represented a moral grave ” which contained the remains of a person originally buried therein. The priest insisted that from this moral grave ” the claimant should pick any bits of bones, metal, screws, nails or wood, and if none of these were present, the claimant was to pick therefrom what were the decomposed ashes of a human body and place them in the new and smaller box and count that as a body. Father Gilmour testified also that he had been placed in charge of the removal operations by his pastor and that his judgment was to determine what constituted a grave pursuant to the tenets of the Catholic Church. He stated that as a matter of [332]*332morals and conscience, he had to ascribe this singular identity to a grave even where it was only a “ moral grave Father Grilmour asserted that Mr. Hadala agreed with him as to what was a “ moral grave ”.

For himself, Mr. Hadala testified that while he accepted the priest’s definition of a “ moral grave ” he disputed with the priest that a moral grave ” should be considered as a separate entity. Mr. Hadala conceded, however, that he did not contradict the priest any more than above stated, nor did he prevent the claimant from placing the remains of each “ moral grave ” in a separate box.

Father Grilmour and the State representatives strictly supervised the removals. Thus, Sorrentino was in no position to dispute, even if he wanted to, the position taken by the priest who was, as stated, accepted by all concerned as the arbiter of what was to be considered a grave.

But the dispute basically was not limited to what was or was not a grave. It also involved the question of whether the claimant was restricted to payments on the basis of the contract as drawn or on a unit basis of each removal as bid by Mm. The contract of January 25,1956 specified that it was for “ removal of ,all human remains from the burial ground ’ ’ and stipulated that the State would pay to claimant the sum of $6,000. However, this contract cannot be considered at its own face value because it is based upon the proposal and specifications (bid) which were submitted by the claimant and is attached to the contract. The court considers the bid the basic portion of the contract. In this bid the claimant bid $44.98 per body transferred, which sum included al-1 phases of work, labor, materials and equipment required for each disinterment and reinterment in the new St. Mary’s Cemetery. The contract, as drawn, was inclusive of the estimated number of bodies and was also inclusive of $1,300 for each common burial plot required in the new cemetery as well as $600 for a suitable monument.

The $6,000 set out in the contract was based on a guess as to the estimated number of bodies thought to be buried there. The fact that the State also considered the contract as one of payment to the claimant on a unit basis is indicated most affirmatively by the letter marked as claimant’s Exhibit 22, dated January 4, 1956 (or 21 days before the awarding of the contract to claimant) written by Mr. P. (Paul) GL Baldwin, Director of the Bureau of Rights of Way and Claims, to H. A. Cohen, Director, Bureau of Contracts & Accounts, which is quoted: ‘‘ Inasmuch as the number of bodies located on the above parcel cannot be ascertained, it is believed that an arbi[333]*333trary figure of $6,000 be made to cover all of the conditions of the specifications herein, and it is further recommended that the performance bond be in a sum of not less than $6,000.00. ’ ’

The fact is that this cemetery was over 100 years old and no interment had taken place therein for over 50 years. The records of burials, if there had been any, were not available. The priests had hardly more knowledge of the number of interments therein than did the State or the claimant.

The claimant described how the work was done. He had a small bulldozer with a blade in front. This removed the earth a little at a time until the casket or outline thereof was reached, whereupon the rest of the digging was done manually.

The boxes used for the transfer of the remains were in dimension 18 inches long by 12 inches wide by 10 inches high and were made of one-inch white pine boards. As the remains from each grave were placed therein, each box was nailed shut and then numbered by the State agent. Then the claimant would remove it to a building which was on the grounds and which was kept locked. During April and May, 1956, the claimant removed 133 bodies, of which 30 were “ moral graves ”. In May, 1956 also, the claimant received from the State an estimate of work done to May 20, which set forth that there was due to the claimant payment for the 133 bodies in the sum of $5,682.34. The State also estimated that, as of then, the job was 50% completed. This sum paid to the claimant was based upon the unit payment of $44.98 less $300 retained by the State.

The claimant continued his work. However, feeling confused by this equivocal situation, he requested through Mr. Hadala that the State give him a supplemental contract which would clarify their respective rights and obligations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hueber Hares Glavin Partnership v. State
75 A.D.2d 464 (Appellate Division of the Supreme Court of New York, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
22 Misc. 2d 330, 201 N.Y.S.2d 429, 1960 N.Y. Misc. LEXIS 2866, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sorrentino-v-state-nyclaimsct-1960.