SOREN-HODGES v. Blazer Homes, Inc.

129 P.3d 196, 204 Or. App. 86, 2006 Ore. App. LEXIS 107
CourtCourt of Appeals of Oregon
DecidedFebruary 1, 2006
DocketCCV 00-11-272; A116294
StatusPublished
Cited by6 cases

This text of 129 P.3d 196 (SOREN-HODGES v. Blazer Homes, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SOREN-HODGES v. Blazer Homes, Inc., 129 P.3d 196, 204 Or. App. 86, 2006 Ore. App. LEXIS 107 (Or. Ct. App. 2006).

Opinion

*89 SCHUMAN, J.

In this negligence action, the trial court granted summary judgment to defendant Blazer Homes, Inc. (Blazer), 1 concluding that plaintiffs’ action seeking damages for Blazer’s allegedly substandard construction of their home was barred by claim preclusion because plaintiffs had already brought an earlier action against Blazer for breach of contract stemming from the same construction project. Plaintiffs contend that claim preclusion cannot operate as a bar to the present action because it is based on alleged defects that, at the time of the first action, they neither knew of nor could reasonably have discovered. Because we conclude that there is a factual dispute on that issue, we agree with plaintiffs that the court erred in granting summary judgment.

Blazer contracted to build a home for plaintiffs. The project was completed in 1992, although plaintiffs did not believe that Blazer had fully or competently performed on the contract. In 1994, Blazer sued plaintiffs for $8,488.07 allegedly still due under the contract. Plaintiffs filed a counterclaim alleging breach of contract, breach of warranty, misrepresentation, and violations of Oregon’s Unlawful Trade Practices Act, ORS 646.605 to 646.638. The case went before an arbitrator. The arbitration agreement recorded plaintiffs’ assertions that Blazer

“(1) failed to complete the home as promised;
“(2) manipulated the accounting and documentation of costs in an attempt to charge [plaintiffs] more than they agreed to pay for the home;
“(3) refused to correct its defective work or to undertake warranty work;
“(4) attempted to charge [plaintiffs] for correcting [Blazer’s] defective work;
*90 “(5) attempted to charge [plaintiffs] for goods and services not incorporated into their home;
“(6) failed to supply an adequate heating system for their home; and
“(7) failed to adequately supervise the construction of their home resulting in deviations from the plans and specifications.”

Several of these general assertions contained more detailed specifications of what, according to plaintiffs, defendant had failed adequately to accomplish, including flaws in the roof, windows, and siding. After a hearing, the arbitrator awarded plaintiffs $11,650.03 plus half of the costs of arbitration, designated plaintiffs as the prevailing parties, and awarded them attorney fees. The award was filed in Washington County Circuit Court.

In 2000, plaintiffs filed the present negligence action against Blazer and others to redress damage that plaintiffs allege they did not discover until that year. That damage, plaintiffs contend, resulted from water intrusion, previously unknown construction defects, and use of improper construction materials. Plaintiffs further assert that once that damage became manifest, plaintiffs discovered “additional hidden damage, including water damage and hidden sheathing and framing damage [.]” The complaint alleges that defendants performed their work negligently in the following particulars:

“The water leakage and damage is the result of the following non-exhaustive list of items of faulty workmanship and construction, and improper defective materials:
“(a) Roof flashings[ 2 ] were not properly installed or sealed to protect the home from wet weather;
“(b) Roof scuppers[ 3 ] were not properly installed or sealed to protect the home from wet weather;
“(c) Windows and doors were not properly installed or sealed to protect the home from wet weather;
*91 “(d) Penetrations through the synthetic stucco on the exterior of the home (known as exterior insulated finish system or ‘EIFS’) were not properly sealed to protect the home from wet weather;
“(e) The foam board for the EIFS was not properly installed on the exterior walls of the home;
“(f) The EIFS on the exterior walls of the home was not installed with proper slopes for drainage;
“(g) The EIFS on the exterior walls of the home was improperly terminated below ground level;
“(h) The EIFS on the exterior walls of the home has cracked and failed;
“(i) The EIFS was not installed on the exterior walls of the home in accordance with published manufacturer’s recommendation and industry standards;
“(j) The building was not weatherproofed according to the building code.”

The complaint further alleges that defendants negligently-failed to warn plaintiffs about certain EIFS maintenance requirements and that defendants’ failure to comply with building codes constituted negligence per se. Plaintiffs averred, in the form of an ORCP 47 E 4 affidavit, that an expert would testify that the newly discovered defects could not reasonably have been discovered at the time of the 1994 action.

Blazer raised claim preclusion as an affirmative defense and moved for summary judgment on that basis. After hearing arguments, the trial court granted Blazer’s motion for summary judgment and explained its decision as follows:

*92 “[THE COURT]: Well, counsel, I don’t know who represented these folks on their first go around. But any time you allege that there is a defect in the roof and a defect, there’s leaks and defects in caulking and all those things, and you grow up in Oregon, you certainly have got to know that those kind of defects are going to cause some damage within the walls of the structure. I guess it’s just common sense.
“I think these claims should have been raised in the original proceeding. And for that reason, based upon the law that has been presented in the briefs, I am going to grant the motion for summary judgment.”

Plaintiffs assign error to that ruling.

The doctrine of claim preclusion may be invoked to prevent a party from bringing a second claim after a final judgment in a prior action if the prior judgment is binding on both parties, the claim in the second action is based on the same factual transaction or series of connected transactions that was at issue in the first claim, the second claim seeks a remedy additional or alternative to the one sought in the first claim, and the second claim could have been brought along with the first claim. Rennie v. Freeway Transport, 294 Or 319, 323, 656 P2d 919 (1982); Troutman v. Erlandson, 287 Or 187, 202, 598 P2d 1211 (1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ramirez v. Kornegay
336 Or. App. 125 (Court of Appeals of Oregon, 2024)
Burns v. Thuney
D. Oregon, 2023
Loveland Essential Group, LLC v. Grommon Farms, Inc.
2012 COA 22 (Colorado Court of Appeals, 2012)
Jakobitz v. Iron Horse Business Services, LLC
145 P.3d 277 (Court of Appeals of Oregon, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
129 P.3d 196, 204 Or. App. 86, 2006 Ore. App. LEXIS 107, Counsel Stack Legal Research, https://law.counselstack.com/opinion/soren-hodges-v-blazer-homes-inc-orctapp-2006.