Sonken-Galamba Corp. v. Butler Iron & Steel Co.

119 F.2d 283, 1941 U.S. App. LEXIS 3693
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 30, 1941
DocketNo. 11878
StatusPublished
Cited by3 cases

This text of 119 F.2d 283 (Sonken-Galamba Corp. v. Butler Iron & Steel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sonken-Galamba Corp. v. Butler Iron & Steel Co., 119 F.2d 283, 1941 U.S. App. LEXIS 3693 (8th Cir. 1941).

Opinion

GARDNER, Circuit Judge.

This is an appeal from a judgment entered in an action brought by appellee against appellants to recover damages for the breach of a contract of sale by the buyer. A jury was waived and the action was tried to the court, resulting in findings of fact and conclusions of law in favor of plaintiff on all the issues. The parties will be referred to as they appeared below.

The contract was for the purchase and sale of certain scrap iron and by its terms plaintiff agreed to sell and defendant Berry agreed to purchase the scrap iron coming from 113 condemned oil tanks at Romana, Oklahoma, 'and Neodesha, Kansas, at $16 per ton f.o.b. cars, with privilege to the buyer of hauling such tonnage at price of $15.50 per ton at present location. $15,000 was deposited on the purchase price, and deliveries were to be made at the rate of 750 tons per month commencing in June, 1937. While the contract was made in the name of W. C. Berry as party of the second part, it is conceded that he executed the same on behalf of the Sonken-Galamba Corporation as purchaser, and the court found that defendants were jointly and severally interested. Defendants elected to haul the scrap iron in their own trucks at $15.50 per ton. Performance of the contract continued until March, 1938, when a controversy developed and the contract was modified by reducing the price in the amount of $1 per ton and the further agreement that, “It is understood that nothing herein shall vary any other terms of the original contract dated April 23, 1937; however W. C. Berry agrees to either move all materials, except angles whose rivets have not been backed out, on or before May 1st or pay for same under the terms of said contract subject only to the stipulation herein of his receiving $1.00 per ton reduction, which is in lieu of cleaning sketch plates, bottoms and ring sheets, it being understood that the May 1st date is, of course, subject to strikes and embargo as provided in the original agreement.”

Defendants did not remove all of the material before May 1, 1938, the last material taken and paid for being on May 13, 1938. The total materials taken and paid for amounted to 7,500.337 net tons. The deposit totaling $15,000 made by defendants was received by plaintiff, and the materials taken and accepted were sufficient to exhaust this deposit and no more. There were no strikes nor embargoes to interfere with the performance of the contract. On July 7, 1938, plaintiff made demand for payment under the contract as modified and gave notice that unless the terms of the contract were performed on or before July 15, 1938, it would take legal action against defendants. Defendants neither removed any more of the scrap iron before July 15, 1938, nor made payment for what they had not already received. They gave no shipping instructions to plaintiff for shipping or removing any of the material, and the total balance of the material on hand for which defendants had contracted amounted to 2,450.663 net tons. By the terms of the contract plaintiff would have received $14.50 per ton, or a total of $34,-500.57 for the balance of this material. The best available market price on or about July 15, 1938, was $6 per ton, so that [285]*285the difference between the contract price and the market price of the material not accepted, on or about July 15, 1938, was $22,055.94.

It was claimed by defendants that weather conditions prevented the performance of the contract by them within the time limited by the contract, but that on August 12, 1938, they sent a truck for part of this material but were denied delivery by the plaintiff. On this issue the court found that the truck was sent without previous notice of any kind to plaintiff of defendants’ intention so to do, and that it was not sent in good faith but was done by the defendants with the hope and expectation that it might be of some aid to them in the defense of any litigation instituted by plaintiff against them on account of their breach of the agreements; that the acts of the watchman in charge of certain of the material in refusing to permit defendants to take any part of it was not an act of refusal by plaintiff, and that defendants were not on July 15, 1938, or at any other time thereafter, ready and willing to perform or carry out any agreement binding on them under the terms thereof. The court found that while there had been unusual rains, such condition had not been continuous and that defendants might have hauled the material had they attempted in good faith so to do between May 1, 1938, and July 15, 1938. The court also found that the written notice sent by plaintiff to defendants demanding performance allowed a reasonable time as a matter of fact and that they could have paid plaintiff the balance due on the contract on or before July 15, 1938, had they desired in good faith so to do.

On this appeal defendants contend (1) that the court erred in holding that they breached the contract on July 15, 1938, because plaintiff waived the time for performance up to July 7 and its demand for performance within seven days thereafter was not a reasonable time; (2) that the court erred in not holding that plaintiff breached the contract on August 12, 1938, by refusing to permit defendants to remove and pay for the remaining scrap iron which was the subject of the contract because the demand of July 7 was unreasonable, and hence, the defendants had a right under the contract to remove and pay for the scrap iron; (3) that the court erred in holding that the measure of damages was the difference between the contract price and the market price and in holding that the resale alleged to have taken place was immaterial.

The contention that the court erred in holding the contract to have been breached on July 15, 1937, is bottomed on the assertion that the demand for performance made on July 7, 1938, did not allow a reasonable time for defendants to perform. The final performance date fixed by the written contract was May 1, 1938. The court found the plaintiff had waived time of performance up to July 7, 1938. On that date, plaintiff’s attorney wrote defendants a letter demanding payment under the agreement. The letter, among other things, contained the following: “By your own conduct you leave us no alternative but to advise you that unless the terms of the contract are carried out on or before July 15, 1938, we will be forced to take such legal action as we deem necessary to protect our client’s interest.” It is claimed by defendants that having waived performance, it was incumbent upon plaintiff to grant a reasonable time for defendants to remove the scrap iron and pay for it. The supplemental agreement of March 11, 1938, contained provision that, “W. C. Berry agrees to either move all materials, except angles whose rivets have not been backed out, on or before May 1st or pay for same under the terms of said contract.” Confessedly, he had not removed and paid for the material. After that date his obligation was to pay for the material. The demand made upon defendants did not purport to require defendant to remove the material. It required only the payment of the purchase price. The court found that the time 'specified in the written notice sent by plaintiff to defendants was a reasonable time as a matter of fact and that defendants could have paid the plaintiffs the balance due under the contract on or before July 15, 1938, if they had desired in good faith so to do. Defendants were obligated to pay under the contract whether or not the materials were removed. It was the manifest intent of the parties, as the trial court concluded, that payment for the materials was to be made regardless of whether the removal of the materials was made by May 1st.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vincent W. Kosuga v. Jack H. Kelly
257 F.2d 48 (Seventh Circuit, 1958)
Landau v. St. Louis Public Service Company
273 S.W.2d 255 (Supreme Court of Missouri, 1954)
Davis v. Hauschild
243 S.W.2d 956 (Supreme Court of Missouri, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
119 F.2d 283, 1941 U.S. App. LEXIS 3693, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sonken-galamba-corp-v-butler-iron-steel-co-ca8-1941.