Sonepar Distribution New England, Inc. v. T & T Electrical Contractor's, Inc.

37 A.3d 789, 133 Conn. App. 752, 2012 Conn. App. LEXIS 87
CourtConnecticut Appellate Court
DecidedFebruary 28, 2012
DocketAC 32662
StatusPublished
Cited by3 cases

This text of 37 A.3d 789 (Sonepar Distribution New England, Inc. v. T & T Electrical Contractor's, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sonepar Distribution New England, Inc. v. T & T Electrical Contractor's, Inc., 37 A.3d 789, 133 Conn. App. 752, 2012 Conn. App. LEXIS 87 (Colo. Ct. App. 2012).

Opinion

Opinion

LAVINE, J.

This appeal arises from a breach of contract action for failure to pay for materials allegedly delivered by the plaintiff, Sonepar Distribution New England, Inc., doing business as Northeast Electrical Distributors, to the defendants, T & T Electrical Contractor’s, Inc., and Gerard T. Beaudoin III. 1 The plaintiff appeals from the judgment rendered by the trial court *754 granting the defendant’s oral motion to dismiss made at the conclusion of the plaintiffs case-in-chief. On appeal, the plaintiff claims that the court improperly (1) applied the preponderance of the evidence standard when ruling on the defendant’s motion to dismiss made pursuant to Practice Book § 15-8, 2 (2) concluded that it had failed to present sufficient evidence that the subject goods were delivered, (3) denied its motion to open the judgment and (4) found that it had failed to comply with the court’s order to submit new evidence that reasonably was likely to change the outcome of the case. We agree that the court improperly applied the preponderance of the evidence standard when ruling on the motion to dismiss, but conclude that the error was harmless and thus affirm the judgment of the trial court.

The following facts and procedural history are relevant to our resolution of the plaintiffs claims. The plaintiff commenced this action in May, 2009, seeking payment for certain goods that the plaintiff alleged it had delivered to the defendant’s storage facility at 330 Ledyard Street in Hartford. The plaintiff claimed that, although it had delivered the goods to the defendant’s satisfaction, the defendant refused to pay pursuant to a certain credit agreement between the parties. The plaintiff claimed that the defendant owed $59,114.67 plus interest. 3 The case was tried to the court in April and May, 2010. At the conclusion of the plaintiffs casein-chief, the defendant moved for a judgment of dismissal. On May 4, 2010, the court granted the motion to dismiss, but also granted the plaintiff thirty days to *755 discover and present new evidence, if any, to prove its claim. On June 4, 2010, the plaintiff filed a motion to open the judgment and present newly discovered evidence. On August 3, 2010, the court denied the motion to open following the plaintiffs offer of proof. After the court denied the plaintiffs motion to reargue, the plaintiff appealed.

I

The plaintiffs first claim is that it was improper for the court to apply the preponderance of the evidence standard when ruling on the defendant’s motion to dismiss for failure to make out a prima facie case pursuant to Practice Book § 15-8. We agree that the preponderance of the evidence standard is inapplicable to a motion to dismiss for failure to make out a prima facie case, but conclude that the court’s error in applying the preponderance standard was harmless, as ultimately the court was the trier of fact. See Berchtold v. Maggi, 191 Conn. 266, 272, 464 A.2d 1 (1983); Friends of Animals, Inc. v. United Illuminating Co., 124 Conn. App. 823, 842 n.12, 6 A.3d 1180 (2010).

“If, on the trial of any issue of fact in a civil action tried to the court, the plaintiff has produced evidence and rested his or her cause, the defendant may move for judgment of dismissal, and the judicial authority may grant such motion, if in its opinion the plaintiff has failed to make out a prima facie case. ... A prima facie case ... is one sufficient to raise an issue to go to the trier of fact. ... In order to establish a prima facie case, the proponent must submit evidence which, if credited, is sufficient to establish the fact or facts which it is adduced to prove. ... In evaluating [the trial court’s decision on] a motion to dismiss, [t]he evidence offered by the plaintiff is to be taken as true and interpreted in the light most favorable to [the plaintiff], and every reasonable inference is to be drawn in [the *756 plaintiffs] favor. . . . Whether the plaintiff has established a prima facie case entitling the plaintiff to submit a claim to a trier of fact is a question of law over which our review is plenary.” (Citations omitted; internal quotation marks omitted.) Sullivan v. Thorndike, 104 Conn. App. 297, 302, 934 A.2d 827 (2007), cert. denied, 285 Conn. 907, 908, 942 A.2d 415, 416 (2008).

In order to prevail on a breach of contract action, a plaintiff must prove “the formation of an agreement, performance by one party, breach of the agreement by the other party and damages.” (Internal quotation marks omitted.) Chiulli v. Zola, 97 Conn. App. 699, 706-707, 905 A.2d 1236 (2006).

The following facts, as gleaned from our review of the transcript and on which the parties generally agree, provide the context for the plaintiffs claim. On or about June 6, 2006, the defendant placed an order for 100 Quazite boxes, 4 lids and bolts (collectively boxes) with the plaintiff. According to Tim Sullivan, manager of the plaintiffs Hartford branch office, the plaintiff placed an order with the manufacturer requesting that the boxes be delivered directly to the defendant’s storage facility (drop shipped order). The manufacturer, Strong-well, indicated that it could not “drop ship” the order, but would deliver the order to the plaintiffs central distribution center in Canton, Massachusetts. The plaintiff was then responsible for delivering the boxes to its Hartford branch office and then to the defendant. Despite this indication, the manufacturer drop shipped 100 boxes to the defendant’s storage facility in Hartford. The defendant took delivery of the drop shipped order *757 from the manufacturer 5 6 and paid the plaintiff. Apparently, the manufacturer also delivered 100 boxes to the plaintiffs Hartford branch office. The plaintiff claims that it delivered 100 boxes, in two truckloads, to the defendant’s storage facility (stock order shipment) on August 10, 2006. 6 The defendant denies having received the stock order shipment and refuses to pay the plaintiffs invoices for the same. This action, the court reasoned, turns on whether the stock order shipment was delivered to the defendant. 7

At trial, the plaintiff produced a receipt signed by one of the defendant’s agents for the drop shipped order and an internal document noting délivery prepared by one of its employees for the stock order shipment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moutinho v. 500 North Avenue, LLC
Connecticut Appellate Court, 2019
State v. Porfil
Connecticut Appellate Court, 2019
Fort Trumbull Conservancy, LLC v. City of New London
43 A.3d 679 (Connecticut Appellate Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
37 A.3d 789, 133 Conn. App. 752, 2012 Conn. App. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sonepar-distribution-new-england-inc-v-t-t-electrical-contractors-connappct-2012.