Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc.
This text of Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc. (Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
i i i i i i
MEMORANDUM OPINION
No. 04-08-00051-CV
SOMERSET INDEPENDENT SCHOOL DISTRICT and Somerset Independent School District Public Facility Corp., Appellants
v.
NICHOLSON PROFESSIONAL CONSULTING, INC., Appellee
From the 341st Judicial District Court, Webb County, Texas Trial Court No. 2003-CVQ-001551-D3 Honorable Elma Salinas Ender, Judge Presiding
Opinion by: Alma L. López, Chief Justice
Sitting: Alma L. López, Chief Justice Catherine Stone, Justice Sandee Bryan Marion, Justice
Delivered and Filed: October 15, 2008
REVERSED AND REMANDED
Somerset Independent School District and Somerset Independent School District Public
Facility Corp. (“Somerset) appeal the trial court’s order granting the Second Amended Motion for
Summary Judgment and No-Evidence Motion for Summary Judgment filed by Nicholson
Professional Consulting, Inc. (“NPCI”). Somerset contends that the trial court erred in granting
NPCI’s traditional motion for summary judgment because genuine issues of material fact exist as 04-08-00051-CV
to: (1) the elements of “legal duty” and “proximate cause” in regard to Somerset’s negligence claim;
and (2) NPCI’s role as project manager in regard to Somerset’s claim for breach of implied warranty.
Somerset also contends that the trial court erred in granting NPCI’s no-evidence motion for summary
judgment because: (1) the motion did not challenge specific elements of Somerset’s causes of action;
and (2) Somerset presented more than a scintilla of evidence raising genuine issues of material fact
with regard to the elements of “legal duty” and “proximate cause.” We reverse the trial court’s order
and remand the cause to the trial court for further proceedings.
BACKGROUND
Somerset entered into a contract with Unico Construction Co. for the construction of an early
childhood center. Mid-Continent Casualty Company was Unico’s surety for the project. Unico
began construction in 1998, and Mid-Continent began receiving payment bond claims in December
of 1998. Unico ultimately defaulted on the contract in February of 2000 when the project was 98%
complete. Mid-Continent took over the project and completed it. In March of 2004, Somerset sued
multiple defendants for negligence in the construction and design of the early childhood center,
including NPCI, alleging faulty construction and design resulted in extensive water damage. NPCI
filed its original motion seeking summary judgment in April of 2007, and the trial court granted
NPCI’s second amended motion on December 20, 2007. In January of 2008, the trial court granted
a motion to sever NPCI from the action that remained pending against the other defendants, making
the trial court’s judgment final for purposes of appeal.
STANDARD OF REVIEW
We review both traditional and no evidence summary judgments de novo. Joe v. Two Thirty
Nine Joint Venture, 145 S.W.3d 150, 156 (Tex. 2004). We consider the evidence in the light most
-2- 04-08-00051-CV
favorable to the non-movant and indulge all reasonable inferences and resolve any doubts in the
non-movant’s favor. Id. at 157. We will affirm a traditional summary judgment only if the movant
established there are no genuine issues of material fact and it is entitled to judgment as a matter of
law on a ground expressly set forth in the motion. Id. We will affirm a no-evidence summary
judgment only if the non-movant failed to produce more than a scintilla of probative evidence raising
a genuine issue of material fact on a challenged element of the cause of action. Ford Motor Co. v.
Ridgway, 135 S.W.3d 598, 600 (Tex. 2004).
DISCUSSION
Somerset contends that the documentary evidence attached to its response raised a genuine
issue of material fact with regard to NPCI’s role as project manager. NPCI responds that the
evidence conclusively established that it was a contract administrator not an on-site manager.
Paul LaForge, a surety claims manager for Mid-Continent, was in charge of ensuring that the
construction on the early childhood center was completed after Unico defaulted. LaForge stated that
he hired Scott Melton as the project manager of construction operations, and he hired William
McComas, an employee of NPCI, as the contract administrator. LaForge testified in his deposition
that Melton was in charge of all on-site activities. Melton was responsible for the quality of work
on site during the completion of the project and for ensuring that the work was completed in a good
and workmanlike manner. LaForge was responsible for overseeing Melton’s decisions in that regard.
LaForge testified that NPCI was not involved in the construction or the design work but was only
in charge of “paper-type stuff.” LaForge testified that McComas “didn’t have building experience,
and I wasn’t about to turn him lose [sic].” McComas’s job was a paperwork job that LaForge would
call the project manager of contract administration.
-3- 04-08-00051-CV
In response to NPCI’s motion and to counter LaForge’s testimony, Somerset relied on
NPCI’s invoices for its work on the project and several letters and documents signed by McComas
as project manager. NPCI contends that this evidence is insufficient to raise a genuine issue of
material fact because the use of the term “project management” and the title “project manager” in
the invoices and letters is speculative in terms of the actual activities in which NPCI engaged.
If the invoices only used the term “project management” and the letters signed as “project
manager” related exclusively to contract administration issues, we might agree with NPCI. The
invoices, however, provide greater detail than merely referring to “project management,” and the
letters signed by McComas as project manager relate to actual details involving construction activity.
Most critical, in our opinion, are the invoice entries for “On site construction management - dealing
with issues as they arose.” and “Onsite to deal with construction management issues as they arose.”
Additional entries that give rise to an inference that NPCI was not exclusively engaged in paperwork
include:
• 08/01/2000 On site. ... Meet with Pete Gonzalez to review activities in general and specifically address column base plate grouting.
• 08/03/2000 On site. ... Meet with Pete Gonzalez to update him on activities and discuss column base grouting options. Discuss testing of columng [sic] base grouting with testing lab and Bill.
• 08/29/2000 On site all day coordinating efforts of subs and suppliers, meeting with owner’s rep, and researching questions by subcontractors.
• 03/23/2000 Somerset- jobsited [sic] visit and review of drawings and files with regard to possible building movement
• 03/24/2000 Somerset - outlining outstanding issues needing resolution
The letters signed by McComas as project manager also appear to extend beyond paperwork issues,
including a letter written to John Casanova, the superintendent of Somerset schools, regarding a
-4- 04-08-00051-CV
water intrusion issue. The letter stated that an investigation had been undertaken to discover the
source of the water intrusion and that McComas “personally looked into the matter with Mr.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/somerset-independent-school-district-and-somerset--texapp-2008.