Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc.

CourtCourt of Appeals of Texas
DecidedOctober 15, 2008
Docket04-08-00051-CV
StatusPublished

This text of Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc. (Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc., (Tex. Ct. App. 2008).

Opinion

i i i i i i

MEMORANDUM OPINION

No. 04-08-00051-CV

SOMERSET INDEPENDENT SCHOOL DISTRICT and Somerset Independent School District Public Facility Corp., Appellants

v.

NICHOLSON PROFESSIONAL CONSULTING, INC., Appellee

From the 341st Judicial District Court, Webb County, Texas Trial Court No. 2003-CVQ-001551-D3 Honorable Elma Salinas Ender, Judge Presiding

Opinion by: Alma L. López, Chief Justice

Sitting: Alma L. López, Chief Justice Catherine Stone, Justice Sandee Bryan Marion, Justice

Delivered and Filed: October 15, 2008

REVERSED AND REMANDED

Somerset Independent School District and Somerset Independent School District Public

Facility Corp. (“Somerset) appeal the trial court’s order granting the Second Amended Motion for

Summary Judgment and No-Evidence Motion for Summary Judgment filed by Nicholson

Professional Consulting, Inc. (“NPCI”). Somerset contends that the trial court erred in granting

NPCI’s traditional motion for summary judgment because genuine issues of material fact exist as 04-08-00051-CV

to: (1) the elements of “legal duty” and “proximate cause” in regard to Somerset’s negligence claim;

and (2) NPCI’s role as project manager in regard to Somerset’s claim for breach of implied warranty.

Somerset also contends that the trial court erred in granting NPCI’s no-evidence motion for summary

judgment because: (1) the motion did not challenge specific elements of Somerset’s causes of action;

and (2) Somerset presented more than a scintilla of evidence raising genuine issues of material fact

with regard to the elements of “legal duty” and “proximate cause.” We reverse the trial court’s order

and remand the cause to the trial court for further proceedings.

BACKGROUND

Somerset entered into a contract with Unico Construction Co. for the construction of an early

childhood center. Mid-Continent Casualty Company was Unico’s surety for the project. Unico

began construction in 1998, and Mid-Continent began receiving payment bond claims in December

of 1998. Unico ultimately defaulted on the contract in February of 2000 when the project was 98%

complete. Mid-Continent took over the project and completed it. In March of 2004, Somerset sued

multiple defendants for negligence in the construction and design of the early childhood center,

including NPCI, alleging faulty construction and design resulted in extensive water damage. NPCI

filed its original motion seeking summary judgment in April of 2007, and the trial court granted

NPCI’s second amended motion on December 20, 2007. In January of 2008, the trial court granted

a motion to sever NPCI from the action that remained pending against the other defendants, making

the trial court’s judgment final for purposes of appeal.

STANDARD OF REVIEW

We review both traditional and no evidence summary judgments de novo. Joe v. Two Thirty

Nine Joint Venture, 145 S.W.3d 150, 156 (Tex. 2004). We consider the evidence in the light most

-2- 04-08-00051-CV

favorable to the non-movant and indulge all reasonable inferences and resolve any doubts in the

non-movant’s favor. Id. at 157. We will affirm a traditional summary judgment only if the movant

established there are no genuine issues of material fact and it is entitled to judgment as a matter of

law on a ground expressly set forth in the motion. Id. We will affirm a no-evidence summary

judgment only if the non-movant failed to produce more than a scintilla of probative evidence raising

a genuine issue of material fact on a challenged element of the cause of action. Ford Motor Co. v.

Ridgway, 135 S.W.3d 598, 600 (Tex. 2004).

DISCUSSION

Somerset contends that the documentary evidence attached to its response raised a genuine

issue of material fact with regard to NPCI’s role as project manager. NPCI responds that the

evidence conclusively established that it was a contract administrator not an on-site manager.

Paul LaForge, a surety claims manager for Mid-Continent, was in charge of ensuring that the

construction on the early childhood center was completed after Unico defaulted. LaForge stated that

he hired Scott Melton as the project manager of construction operations, and he hired William

McComas, an employee of NPCI, as the contract administrator. LaForge testified in his deposition

that Melton was in charge of all on-site activities. Melton was responsible for the quality of work

on site during the completion of the project and for ensuring that the work was completed in a good

and workmanlike manner. LaForge was responsible for overseeing Melton’s decisions in that regard.

LaForge testified that NPCI was not involved in the construction or the design work but was only

in charge of “paper-type stuff.” LaForge testified that McComas “didn’t have building experience,

and I wasn’t about to turn him lose [sic].” McComas’s job was a paperwork job that LaForge would

call the project manager of contract administration.

-3- 04-08-00051-CV

In response to NPCI’s motion and to counter LaForge’s testimony, Somerset relied on

NPCI’s invoices for its work on the project and several letters and documents signed by McComas

as project manager. NPCI contends that this evidence is insufficient to raise a genuine issue of

material fact because the use of the term “project management” and the title “project manager” in

the invoices and letters is speculative in terms of the actual activities in which NPCI engaged.

If the invoices only used the term “project management” and the letters signed as “project

manager” related exclusively to contract administration issues, we might agree with NPCI. The

invoices, however, provide greater detail than merely referring to “project management,” and the

letters signed by McComas as project manager relate to actual details involving construction activity.

Most critical, in our opinion, are the invoice entries for “On site construction management - dealing

with issues as they arose.” and “Onsite to deal with construction management issues as they arose.”

Additional entries that give rise to an inference that NPCI was not exclusively engaged in paperwork

include:

• 08/01/2000 On site. ... Meet with Pete Gonzalez to review activities in general and specifically address column base plate grouting.

• 08/03/2000 On site. ... Meet with Pete Gonzalez to update him on activities and discuss column base grouting options. Discuss testing of columng [sic] base grouting with testing lab and Bill.

• 08/29/2000 On site all day coordinating efforts of subs and suppliers, meeting with owner’s rep, and researching questions by subcontractors.

• 03/23/2000 Somerset- jobsited [sic] visit and review of drawings and files with regard to possible building movement

• 03/24/2000 Somerset - outlining outstanding issues needing resolution

The letters signed by McComas as project manager also appear to extend beyond paperwork issues,

including a letter written to John Casanova, the superintendent of Somerset schools, regarding a

-4- 04-08-00051-CV

water intrusion issue. The letter stated that an investigation had been undertaken to discover the

source of the water intrusion and that McComas “personally looked into the matter with Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Joe v. Two Thirty Nine Joint Venture
145 S.W.3d 150 (Texas Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
Somerset Independent School District and Somerset Independent School District Public Facility Corp. v. Nicholson Professional Consulting, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/somerset-independent-school-district-and-somerset--texapp-2008.