Somers Construction Co. v. United States

106 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 27, 1946 WL 4422
CourtUnited States Court of Claims
DecidedMarch 4, 1946
DocketNo. 45054
StatusPublished
Cited by1 cases

This text of 106 Ct. Cl. 1 (Somers Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Somers Construction Co. v. United States, 106 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 27, 1946 WL 4422 (cc 1946).

Opinion

Whaley, Chief Justice,

delivered the opinion of the court:

On January 12, 1938, the plaintiff entered into a contract with the War Department for a change in the Augusta Levee, near Augusta, Georgia. The work included enlargement of a portion of the levee both to the landside and to the riverside, a false berm on the landside, certain road crossings and a steel sheet pile retaining wall.

The specific work involved in suit is the handling of earth. There is no controversy over the retaining wall.

Earth or dirt for the enlargement was to be obtained from two sources. The existing levee was to contribute its designated share; the remainder was to be obtained from borrow pits in South Carolina. The material for the false berm was to come from landside borrow pits to the extent shown on the drawings, the remainder to come from the borrow pits in South Carolina.

The specifications and drawings gave engineering details. Dirt from the borrow pits in South Carolina is designated as “haul”; that from a location close enough to the new work to be cast thereon by dragline and bucket is known as “cast.”

The specifications estimated the yardage of enlargement, false berm, and road crossings to be 216,000 cubic yards, which was approximate only, and might be increased or diminished by not more than 20 percent.

The contract drawings indicated also a total yardage of 216,000 cubic yards, of which approximately 114,000 was to be haul and 102,000 was cast, a ratio of 52.78 (haul) to 47.22 (cast).

These estimated quantities were what is known as “net” yardages. The plaintiff had actually to haul and cast dirt of greater volume to take care of shrinkage. This factor of shrinkage was stated in percentages which were affected by the manner of handling the dirt, such as by heavy or light tractor, by dragline and the nature of the dirt. The embankment had to be constructed up to a so-called gross grade, to [27]*27take care of subsequent shrinkage, and traction of equipment over the levee as it mounted higher might necessitate more dirt in order to achieve the required gross grade. Shrinkage factors were specified, and the plaintiff and the defendant could make their calculations accordingly.

The plan of work was to haul dirt from the South Carolina pits, deposit it on the levee up to a certain point or elevation, and then bring the levee up to gross grade by casting thereon dirt from certain nearby sections of the old levee or borrow pits.

Casting was cheaper than hauling, and, in order to use all the dirt permitted to be taken from the old levee, this called for some nice calculation of the amount that should first be hauled. If the hauling was underestimated, hauling would have to be resumed after casting, because only certain amounts could be taken from the old levee, and the trucks hauling on the second operation from the South Carolina pits would have a higher ascent to climb, manifestly increasing the cost of operations. It was important, for reasons of economy, to use the distant borrow pits for low-level embankment.

With this situation in view the plaintiff made its bid of 22 cents per cubic yard, regardless of whether the material was haul or cast.

The 22 cents per cubic yard is explained as follows: The plaintiff estimated the cost of handling 114,000 cubic yards of haul at 24 cents per cubic yard, and the cost of handling 102,000 cubic yards of cast at a figure which amounted to 6.7 cents per cubic yard. The total cost, thus calculated, would be $34,194.00. The bid price was $47,520.00, and the difference of $13,326.00 was the contractor’s anticipated profit.

It will thus be seen that if the estimated cost per cubic yard for each class and the bid price per cubic yard for both classes be taken as constants, a variation in the ratio between haul and cast would upset the anticipated profit.

And the burden of plaintiff’s complaint, as we understand it, is that the ratio of 52.78 (haul) to 47.22 (cast), deduced from the contract drawings, so greatly varied from conditions as they developed in the actual work, as to constitute a misrepresentation amounting to breach of contract. This, in substance, is the conclusion of plaintiff’s brief.

[28]*28But there are other questions to be disposed of. Plaintiff contends that the defendant’s calculation of quantities for pay purposes is inaccurate and unreliable, and the defendant, denying plaintiff’s contention, maintains that the plaintiff’s proposed method of arriving at pay quantities embraces certain false premises and is not trustworthy.

The burden of proof that must be borne by the plaintiff goes beyond that of showing that the defendant’s basis of settlement is erroneous. Without proof of a more exact settlement there would be no foundation for a money judgment such as this court is empowered to award.

The contract did not provide the specific method of measuring the earthwork, but the defendant, in making its concluding settlement on the contract, applied cross-sections made from surveys. Such surveys are of course made before and after the work has been done, are compared with each other, and the necessary engineering calculations made. Surveys are not always accurate, but with a reasonable degree of accuracy the results are deemed sufficient for pay purposes. We understand that plaintiff’s position is not that the cross-section method is of itself unreasonably inaccurate, but that in this case the preconstruction cross-sections were so grossly inaccurate as to form no reasonable basis for payment; that, the final survey made, the final cross-sections taken could not in fairness be superimposed upon the original cross-sections, the original cross-sections being so grossly inaccurate.

Early in the work the plaintiff found that the Government was paying it less than it was currently expending on the work. Daily estimates of the work done did not agree with the estimates upon which payments were being made, although this discrepancy was not conclusive of inaccuracy, for the reason, in part, that the daily estimates of earthwork were of gross yardage, while the estimates for pay purposes were of net yardage, and the difference between gross and net was determined by contract percentages based on the nature of the particular operation and the nature of the material.

The plaintiff, being skeptical, tried another method of measuring quantities. It began to count the truck-loads of earth hauled. This method of measurement did not of course [29]*29apply to dragline and bucket, but the hauling was apparently what the plaintiff was more concerned about.

The capacity of the trucks varied, and the loading was not uniform. Since payments were being made on net yardage the difficulty was presented of ascertaining an appropriate shrinkage factor to be applied. If a truck was carrying three cubic yards, how many net cubic yards did that represent in place in the levee enlargement?

In order to ascertain the average load per truck, two given factors are needed. One is the number of trucks, the other is the total load of all of them. But the total load is here not a given factor, it is a result which is to be ascertained. We conclude that plaintiff’s estimate of four cubic yards gross as the average is without proper foundation in the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dubois Const. Corp. v. United States
98 F. Supp. 590 (Court of Claims, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
106 Ct. Cl. 1, 1946 U.S. Ct. Cl. LEXIS 27, 1946 WL 4422, Counsel Stack Legal Research, https://law.counselstack.com/opinion/somers-construction-co-v-united-states-cc-1946.