Solondz Bros. Lumber v. Piperato

101 A.2d 33, 28 N.J. Super. 414, 1953 N.J. Super. LEXIS 651
CourtNew Jersey Superior Court Appellate Division
DecidedNovember 30, 1953
StatusPublished

This text of 101 A.2d 33 (Solondz Bros. Lumber v. Piperato) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Solondz Bros. Lumber v. Piperato, 101 A.2d 33, 28 N.J. Super. 414, 1953 N.J. Super. LEXIS 651 (N.J. Ct. App. 1953).

Opinion

The opinion of the court was delivered by

Eastwood, S. J. A. D.

This appeal concerns itself with the construction of sections N. J. S. 2A :44-75, 77, 81 and 85, of the Mechanics’ Lien Law.

Among the questions posed there are only three that require our determination, to wit: (1) Did the plaintiff’s stop notice set forth and specify the amount due and demanded as nearly as possible?; (2) Did the two payments aggregating $1,100 made by the owners to the contractor constitute advance payments for which the owners were not entitled to any credit in ascertaining the amount of money in their hands at the time of the filing of the stop notice?; and (3) Were the owners allowed a sufficient credit for the cost of completing the construction, consequent upon the abandonment of the work by the contractor ?

The trial court, sitting without a jury by consent of the parties, held that the challenged payments aggregating $1,100 were not, under its construction of the statute, advance payments; that the owners were entitled to credit therefor in ascertaining the amount of money in their hands at the time of the filing of the stop notice and that the owners were entitled to a further credit of $750 for the reasonable cost of completing the construction of the dwelling house under the terms of the contract, thus leaving a balance of $150 in the hands of the owners subject to the plaintiff’s claim. The plaintiff appealed from the ensuing judgment in its favor for $150 and the defendants-owners filed a cross-appeal from that part of the judgment which allowed them the sum of $750 for the completion of the construction.

The following factual recital will more clearly portray the resulting issues.

The defendants William Yarotsky and Catherine Yarotsky entered into a contract on September 29, 1950 with one Joseph Piperato, whereby the latter agreed to erect a dwelling house for the sum of $15,500, which was to be paid in [417]*417installments, the final payment of $2,000 to be made upon the full completion as certified by the architect. The building contract and accompanying specifications were filed in the Union County Clerk’s office on October 3, 1950.

The building materials used in the Yarotsky house were purchased by the contractor from the plaintiff, and totalled the sum of $5,109.58, against which Piperato had a credit for payments on account and materials not used in the amount of $2,647.09, leaving a balance due of $2,462.49. In the instant action, Piperato was made a defendant and judgment by default was entered against him in the sum claimed plus interest and costs of suit.

The plaintiff finding itself unable to collect the amount due from the contractor, filed a “stop notice” on March 6, 1952 in the Union County Clerk’s Office, directed to the Yarotskys, wherein it was stated that there was due to the plaintiff the sum of $2,462.49 for materials furnished and demanding that the same be retained out of any money due or to become due from the defendants-owners. A copy of the stop notice was, on March 7, 1952, sent by registered mail to the Yarotskys and was received by them on March 15, 1952.

It is clear that the contractor never completed the house. At the time the plaintiff filed its stop notice, the owners had remaining in their hands the sum of only $900 out of the final payment of $2,000.

When it became apparent that the contractor would not complete the house — in fact, that he had actually abandoned the job — the owners vacated their other place of residence in November, 1951, and moved into the new house in its unfinished condition. The Yarotskys assert that out of the final $2,000 installment they made payments to the plumber, painter and for other work and materials necessary for a completion of the construction, totalling $1,370.59, which payments they contend were expended in good faith about five months before the plaintiff filed its stop notice; that on April 10, 1952 and April 18, 1952 they paid out $100 and $225, totalling $325, for landscaping and walks, and also [418]*418$270.59 for linoleum, electrical fixtures and hardware, which the builder failed to provide, thus leaving in the hands of the Yarotskys the sum of $304.41. There was testimony proff erred by the defendants’ expert, Walter Ernst, that it would cost approximately $825 to repair some of the work done faultily by the contractor and that the job was still not according to the plans, and that to re-do the necessary work in accordance with the plans it would cost more than $2,000.

When a construction contract is filed, N. J. S. 2A :44-75 of the Mechanics’ Lien Law imposes a lien for materialmen and laborers on any funds in the hands of the owner representing money due or to grow due to the contractor.

In the case of James Falcone Plumbing & Heating Co., Inc., v. Pasquale, 26 N. J. Super. 285 (App. Div. 1953), Judge Erancis discusses quite exhaustively all of the legal questions that arise in a consideration of the present appeal. Rather than needlessly reiterate the legal rules enunciated therein, we suggest that the reader of this opinion will find it profitable, indeed, if he examine that decision.

The contention of the Yarotskys that the amount due and demanded in the stop notice was not in conformity with the statute (N. J. S. 2A:44-77), in that it did not “set forth the amount due and demanded, specifying the amount as nearly as possible” is not supported by the proofs. The owners argue that the differences in the price of the material as charged when compared with the amount of credits for materials not used and returned, show a definite design or carelessness on the part of the materialman which is fatal, citing the Falcone ease, supra, and other cases in support of their contention. The language of section 77 is not a mandate to set forth the amount due with absolute accuracy. But as much accuracy as is reasonably possible is required. Tuttle v. Cadwell, 92 N. J. L. 26 (Sup. Ct. 1918); Harry Pinsky & Son Co. v. Wike, 101 N. J. Eq. 45 (Ch. 1927), affirmed 103 N. J. Eq. 18 (E. & A. 1928); Intili v. Bonnet, 6 N. J. Misc. 1043 (Sup. Ct. 1928); Hasson v. Bruzel, 104 N. J. Eq. 95 (Ch. 1929); James [419]*419Falcone Plumbing t& Healing Co., Inc., v. Pasquale, supra. It is apparent, however, that in the instant case, under the proofs and the holding of the trial judge, who sat as court and jury, there was no variance between the amount stated in the stop notice and the amount due the plaintiff as established at the trial. The default judgment entered in favor of the plaintiff against the contractor Piperato in this action was for the amount stated in the stop notice. In his findings of fact and conclusions of law the trial judge stated:

‘‘The plaintiff, Solondz Brothers Lumber Company, furnished material to Piperato to be used in the construction of the house. There was a balance due for material supplied in the amount of §2,462.49. The plaintiff proceeded to seenre a default judgment against Pij>erato in the amount of §2,498.49, damages, costs, and interest on the principal sum due.”

Therefore, under the proofs, we conclude that there was a sufficient compliance with the statute. James Falcone Plumbing & Heating Co., Inc., v. Pasquale, supra; Harry Pinsky & Son Co. v. Wike, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
101 A.2d 33, 28 N.J. Super. 414, 1953 N.J. Super. LEXIS 651, Counsel Stack Legal Research, https://law.counselstack.com/opinion/solondz-bros-lumber-v-piperato-njsuperctappdiv-1953.