Soegard v. Concretera Nacional, Inc.

88 P.R. 174
CourtSupreme Court of Puerto Rico
DecidedApril 25, 1963
DocketNo. 409
StatusPublished

This text of 88 P.R. 174 (Soegard v. Concretera Nacional, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Soegard v. Concretera Nacional, Inc., 88 P.R. 174 (prsupreme 1963).

Opinion

Mr. Justice Pérez Pimentel

delivered ,the opinion of the Court.

By the month of October 1957 Concretera Nacional, Inc., and Javier Soegard subscribed an agreement by which the defendant-appellant, Concretera Nacional, Inc., bound itself to serve plaintiff-appellee, Javier Soegard, 84 cubic yards of reinforced concrete with a cube strength of 3,000 lbs. Said delivery would take place in Barrio Palmer of Rio Grande, where Javier Soegard was constructing a building for the purpose of moving his mixed business of dry goods, groceries, and construction materials known as “La Tienda Grande”.

The defendant-appellant served 79 cubic yards of reinforced concrete at the place agreed upon in the morning and afternoon of October 18, 1957. In turn, plaintiff-appellee paid Concretera Nacional, Inc., by check, the sum of one thousand five hundred eighty dollars ($1,580), price of the reinforced concrete delivered. Next day plaintiff noticed that the concrete had not set in some places of the roof, for which reason he proceeded to so inform Concretera Nacional, Inc., through its Treasurer, Mr. Domenech. He observed the roofing slab a few days later and authorized that certain loading and pressure tests be made, at the expense of defendant. Meanwhile, Mr. Soegard ordered the bank to stop payment of the aforesaid check. The tests of the roof having been made, the results were deficient and Mr. Soegard proceeded to destroy the whole roof and construct it again in accordance with the norms in the field of construction. To collect the expenses incurred in this operation and the subsequent loss for not having used the premises, plaintiff-appellee Soegard filed the complaint which has given rise to this suit. Likewise, engineer Otto González Ydrach filed a complaint against Concretera Nacional, Inc., for injury to his professional reputation and for the moral and mental damages suffered by him. González [176]*176Ydrach had designed the building under construction belonging to Mr. Soegard, and he also supervised the project. The cases were consolidated.

The trial court after hearing the evidence of both parties decided, as a matter of fact, the following:

“The defendant having been notified of what had occurred through its Treasurer, Mr. Domenech, he promised to go to the project, and he went the following week and authorized that certain loading and pressure tests be made at the expense of the defendant.
“Said tests having been made the result was that of the nine sections of the roofing slab those marked 2 and 3 (Exh. 1) did not give the 3,000 pound strength but only 763 pounds.
“Because the roof in those sections did not support the load, the whole roof was then destroyed, as it was most advisable and safe, and a new one was made at a cost of $6,225.20. (Exh. 4.)
“The destruction and reconstruction of beams and roof delayed the construction that would have been finished by December 15, 1957, until the end of March, 1958, for plaintiff Javier Soegard to move his business of dry goods, groceries, and construction materials.
“Plaintiff Javier Soegard could not use the premises under construction, which were new and more ample, for the Christmas Season; he had to cancel orders for the amount of $15,000 and store the merchandise already delivered for $20,000, which would have netted 20 per cent profit.
“Plaintiff Javier Soegard paid the sum of $700 for the tests made at the request and expense of the defendant. (Exh. 2.)
“The work of unloading the reinforced concrete delivered to the construction in defendant’s trucks lasted from 7:30 a.m. to 5:30 p.m. without interruption, since lunch was served by the plaintiff at the project, and the workers, including those of the defendant, took turns to lunch.
“Plaintiff Javier Soegard has incurred in expenses and delays in the construction and finishing of the project because the reinforced concrete served by defendant had already ‘hardened’ or was set at the time of using it, because the dry mixture had been prepared more than an hour and a half in advance, and a certain amount of water in excess of the amount required had [177]*177to be added so that the mixture would yield .the strength required in that part of the project.
“Plaintiff failed to receive benefits from his business for the sum of $4,000, by reason of the delay in finishing the project.
“We cannot conclude that plaintiff Otto González Ydrach has suffered damages in his reputation as civil engineer. The evidence shows a capricious inference of liability by private persons on plaintiff Otto González Ydrach, for the demolition of the project that he had designed and was supervising. He has only been exposed to the annoyances or moral suffering caused by the knowledge that the project designed by him had to be demolished by fault of defendant.”

In its conclusions of law the trial court held that a person has the right to claim damages for mental sufferings caused by the fault or negligence of another person. To that effect it ordered Concretera Nacional, Inc., to pay plaintiff Otto Gon-zález Ydrach the sum of $500 for moral and mental damages suffered on account of the facts mentioned in the previous findings of fact. Likewise, it ordered Concretera Nacional, Inc., to pay plaintiff Javier Soegard, Inc., the following sums:

“1. Six .thousand two hundred twenty-five dollars and twenty cents ($6,225.20) for the demolition and reconstruction of the beams and roof, including materials and labor.
“2. Four thousand dollars ($4,000) for the damages caused to the plaintiff for the delay in finishing the project.
“3. Seven hundred dollars ($700) paid by plaintiff Javier Soegard for the tests ordered by defendant.
“Defendant is ordered to pay the costs, and one thousand dollars for attorney’s fees that will be divided in $800 for plaintiff’s attorney’s fees in case No. 58-131, and $200 for attorney’s fees in case No. 58-3014.”

Appellant points out the commission of eight errors and discusses the first two jointly because they are related to each other. It maintains that the trial court in concluding that “because the reinforced concrete served by the defendant had already ‘hardened’ or was set at the time of using it because the dry mixture had been prepared more than an [178]*178hour and a half in advance, and a certain amount of water in excess of the amount required had to be added so that the mixture would yield the strength required in the part of the project,” said court gave credit to defendant’s evidence and it should have, consequently, dismissed the claim. It assumes that the time that the trucks delayed in taking their turn to mix the concrete and serve it, was due to the slowness and poor organization of the employees and laborers of the project, and the interruption in the unloading of the concrete, ordered by the master builder at the lunch hour. It stands on an erroneous premise'.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
88 P.R. 174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/soegard-v-concretera-nacional-inc-prsupreme-1963.