Soda Mountain Wilderness Council v. Bureau of Land Management

534 F. App'x 680
CourtCourt of Appeals for the Ninth Circuit
DecidedJuly 30, 2013
Docket12-35844
StatusUnpublished

This text of 534 F. App'x 680 (Soda Mountain Wilderness Council v. Bureau of Land Management) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Soda Mountain Wilderness Council v. Bureau of Land Management, 534 F. App'x 680 (9th Cir. 2013).

Opinion

MEMORANDUM *

Soda Mountain Wilderness Council, Oregon Wild, Klamath Siskiyou Wildlands Center, Center for Biological Diversity, and Cascadia Wildlands (Soda Mountain) appeal the district court’s denial of their motion for preliminary injunction seeking to enjoin a timber sale approved by the Bureau of Land Management (BLM). Soda Mountain argues that it raised serious questions on the merits of three claims relating to: (1) whether BLM’s timber sale will contribute to the need to list the Pacific fisher under the Endangered Species Act in violation of the Federal Land Policy and Management Act; (2) whether BLM violated the National Environmental Protection Act (NEPA) by failing to take a “hard look” at logging trees infected with mistletoe; and, (3) whether BLM violated NEPA by failing to consider an alternative that avoids construction of new roads. We have jurisdiction under 28 U.S.C. § 1292(a)(1). We affirm the district court’s order denying Soda Mountain’s motion for a preliminary injunction, in part, and reverse in part.

We review the district court’s denial of a preliminary injunction under an abuse of *683 discretion standard. Am. Trucking Ass’ns, Inc. v. City of Los Angeles, 559 F.3d 1046, 1052 (9th Cir.2009). “We will not reverse the district court where it got the law right, even if we would have arrived at a different result, so long as the district court did not clearly err in its factual determinations.” Alliance for the Wild Rockies v. Cottrell, 632 F.3d 1127, 1131 (9th Cir.2011) (internal quotation marks omitted). To prevail on its motion for a preliminary injunction in the district court, Soda Mountain had to establish that it is likely to succeed on the merits; that the balance of hardships tips in its favor; that it is likely to suffer irreparable harm in the absence of preliminary relief; and that an injunction is in the public interest. Winter v. Natural Res. Def. Council, Inc., 555 U.S. 7, 20, 129 S.Ct. 365, 172 L.Ed.2d 249 (2008). As an alternative to satisfying the first two Winter elements, Soda Mountain could have shown that its complaint raised “serious questions going to the merits” and that the balance of hardships “tips sharpljf’ in its favor. Cottrell, 632 F.3d at 1131-32.

The district court did not abuse its discretion by ruling that Soda Mountain did not raise serious questions on the merits of its claim that the timber sale would contribute to the need to list the Pacific fisher as a threatened or endangered species. 1 The BLM evaluated the impact of the proposed project on the Pacific fisher and determined that it would not contribute to the need to list the fisher as a threatened or endangered species. The BLM’s determination is owed deference. City of Sausalito v. O’Neill, 386 F.3d 1186, 1206 (9th Cir.2004) (“Where a court reviews an agency action involving primarily issues of fact, and where analysis of the relevant documents requires a high level of technical expertise, we must defer to the informed discretion of the responsible federal agencies.” (internal quotation marks omitted)).

Nor did the district court err by ruling that Soda Mountain failed to raise serious questions as to the merits of its argument that the BLM failed to take the required “hard look” at logging trees infected with mistletoe. The district court found that the agency undertook a reasonably thorough discussion of the significant aspects of the probable environmental consequences of its proposed action, such that the environmental assessment “foster[s] both informed decision-making and informed public participation.” Ctr. for Biological Diversity v. Nat’l Highway Traffic Safety Admin., 538 F.3d 1172, 1194 (9th Cir.2008) (alteration in original). Here, mistletoe infected trees appear to present both environmental benefits (because the fisher uses mistletoe for resting), as well as environmental costs (because mistletoe harms the trees it infects). Removal of all mistletoe-infected trees was not advocated by either party. The record demonstrates that the BLM did not ignore the impact of the project on mistletoe, even if it did not precisely quantify the amount of mistletoe to be removed. The district court correctly ruled that this is sufficient under our case law. See Native Ecosystems Council v. U.S. Forest Serv., 428 F.3d 1233, 1242 (9th Cir.2005) (failure to specify percentages of canopy closure resulting from project not fatal where agency assessed impact of changes to canopy).

Soda Mountain’s argument that the BLM arbitrarily and capriciously re *684 moved from further consideration the proposed “no-new-roads alternative” has merit, however. The environmental assessment prepared by the BLM rejected Soda Mountain’s request to examine in detail a project alternative that would not have required the building of new roads to access three units in the project area. The BLM explained that helicopter yard-ing of the three units would be necessary if roads were not built, that helicopter yarding would be cost prohibitive, and that removing the three units from the project “would not have been consistent with [the regional management plan] direction for managing units for sustained timber production.” 2 However, the final Decision Record for the project did remove one of the three road-requiring units as well as several other units that were part of the original proposal. Because the BLM never explained why eliminating two of the three new-road-requiring units from the project would have been inconsistent with the project objectives, but eliminating several other units from the proposal was not inconsistent with project objectives, we “are left in doubt as to the reason for the change in direction.” Lands Council v. Martin, 529 F.3d 1219, 1225 (9th Cir.2008) (quoting Morales-Izquierdo v. Gonzales, 486 F.3d 484, 493 (9th Cir.2007) (en banc) (as amended)). Our review is deferential, but “the agency must nonetheless articulate a rational connection between the facts found and the conclusion made.” Id. (internal quotation marks omitted). Because we do not find in the record any explanation that allows us to reconcile the decision to reject the “no-new-roads” alternative with the decision to reduce the size of the project by more than three units, we conclude the district court erred by failing to find a likelihood of success on the merits of this part of Soda Mountain’s NEPA claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amoco Production Co. v. Village of Gambell
480 U.S. 531 (Supreme Court, 1987)
Pit River Tribe v. United States Forest Service
615 F.3d 1069 (Ninth Circuit, 2010)
Baccei v. United States
632 F.3d 1140 (Ninth Circuit, 2011)
High Sierra Hikers Association v. Blackwell
390 F.3d 630 (Ninth Circuit, 2004)
Lands Council v. Martin
529 F.3d 1219 (Ninth Circuit, 2008)
Alliance for Wild Rockies v. Cottrell
632 F.3d 1127 (Ninth Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
534 F. App'x 680, Counsel Stack Legal Research, https://law.counselstack.com/opinion/soda-mountain-wilderness-council-v-bureau-of-land-management-ca9-2013.