Snyder Taft Corners Act 250

CourtVermont Superior Court
DecidedJanuary 27, 2016
Docket15-2-15 Vtec
StatusPublished

This text of Snyder Taft Corners Act 250 (Snyder Taft Corners Act 250) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snyder Taft Corners Act 250, (Vt. Ct. App. 2016).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Environmental Division Unit Docket No. 15-2-15 Vtec

The Snyder Taft Corners LLC JO DECISION ON MOTION

This matter is an appeal from the Natural Resource Board’s determination that The Snyder Taft Corner, LLC was not entitled to a refund for a portion of the fee it paid in connection with an Act 250 permit amendment it submitted to the District #4 Environmental Commission because the issue was moot. Snyder Taft Corner, LLC (Applicant) raises one question on appeal: “Was it wrong to require Snyder to pay an application fee in excess of the statutory cap set by 10 V.S.A. § 6083a(a)(6).” Pending before the Court are the parties’ cross-motions for summary judgment. Applicant argues that the statutory cap on application fees in 10 V.S.A. § 6083a(a)(6) applies to the sum of all fees paid in a master plan application and successive amendment applications. Because the fee for its most recent amendment application would make Applicant’s total fees paid exceed the statutory cap, Applicant asserts that it should not have been required to pay the excess, and that it is entitled to a judgment in the amount of the excess it eventually paid (under protest). The Natural Resources Board (Board) argues that this appeal is “moot” because Applicant did eventually pay the excess and the sole remedy for obtaining an application fee refund is to first request a refund from the District Commission, and Applicant failed to do so. In the alternative, the Board argues that the statutory cap applies to each individual permit amendment, not to the sum of all fees paid for a given permit series.

Factual Background

The parties in this case have submitted a stipulated statement of undisputed facts. The record also includes exhibits filed by Applicant, which are publicly available documents from its various permit applications in the master plan permit series at issue. As the Board has not 1 challenged the exhibits, we also rely on the exhibits to provide undisputed facts. See V.R.C.P. 56(c)(3) and 56(e)(2). For the sole purpose of deciding the pending motions, the Court recites the following facts, which we understand to be undisputed unless otherwise noted.

1. The Snyder Taft Corners, LLC is the developer of a mixed-use planned united development project in Williston, Vermont known as Finney Crossing (the Project). 2. The Project consists of a mix of office, service, and retail uses and a variety of housing types. 3. The Project is subject to Land Permit series 4C0887. 4. The Project is subject to the Town of Williston’s residential growth management process and must be constructed in phases over a period of at least nine years. 5. Applicant applied for a land use permit amendment for the Project on March 29, 2007. 6. The District #4 Environmental Commission (District Commission) issued Land Use Permit Amendment 4C0887-1R on December 16, 2009, approving the master plan for the Project’s 356 residential units and 186,000 square feet of commercial space, and authorizing Applicant to begin construction of phase one of the Project. 7. The District Commission issued positive findings under all Act 250 criteria for the first phase of residential construction as well as positive findings on a majority of criteria for the entire Project. 8. The District Commission directed that “[c]onstruction of the remaining residential units and any commercial buildings are [sic] not authorized until a permit amendment is issued for that purpose.” The District Commission further directed that subsequent permit amendments should specifically address those criteria for which positive findings had not yet been made. 9. When the Applicant applied for its permit in 2007, it paid an application fee based on the cost of construction for the entire Project—i.e., for 356 residential units and 186,000 square feet of commercial space. At that time, the statutory cap for application fees under 10 V.S.A. § 6083a(a)(6) was $135,000.00. 1998, No. 155, § 26. Because a fee based on the actual cost of construction for the entire Project would exceed the cap, Applicant paid $135,000.00. 10. Over the next seven years, through the course of various permit amendments, the District Commission approved construction of a total of 361 units.

2 11. In 2010, the Legislature increased the statutory cap to $150,000. See 2010 No. 134, § 33. 12. On September 17, 2014, Applicant submitted Land Use Permit Application 4C0887-1R-H (H Amendment Application) for the construction of twenty additional residential units. If approved, this would bring the total number of permitted units to 381. 13. Applicant noted that an application fee based on the construction costs for the twenty additional units would be $19,170.00 under 10 V.S.A. § 6083a(a). 14. Applicant provided payment of $11,962.50, which represented its calculation of the difference between the sum of all fees paid to that point and the then-existing statutory cap of $150,000 under Section 6083a(a)(6) (2010). 15. Applicant claimed that the $11,962.50 payment amounted to the maximum allowed fee for the Project according to 10 V.S.A. § 6083a(a)(6). 16. On September 18, 2014, the District Coordinator issued a jurisdictional opinion (JO 4- 240) to Applicant that determined that Applicant’s application was incomplete because it did not include the required fee of $19,170.00 (the full fee based on construction costs for the H Amendment Application). 17. As of September 26, 2014, Applicant had paid the remaining application fee amount for a total of $19,170.00 so that its application could go forward. Applicant noted in correspondence to the District Coordinator that it was paying the fee “under protest.” 18. On September 26, 2014, the H Amendment Application was deemed complete. 19. On October 1, 2014, the District Commission published a notice of minor application for the H Amendment Application. The District Commission issued the permit on December 16, 2014 without a hearing, pursuant to the minor amendment procedures in Act 250 Rule 51. 20. On October 20, 2014, Applicant filed a notice of appeal of JO 4-240 with the Environmental Division of the Superior Court. The District Coordinator’s JO 4-240 erroneously advised Applicant that an appeal of the JO was to be filed with the Environmental Division when the correct challenge was by a request for reconsideration to the Board. Pursuant to a stipulation between the parties, the Court dismissed the appeal without prejudice because it was filed in the incorrect forum.

3 21. Applicant filed a request for reconsideration of JO 4-240 with the Board on November 11, 2014. Applicant argued for a refund in the amount of $8,220.00, claiming that the balance was an overpayment. 22. On November 25, 2014, the Board distributed a Notice of Reconsideration, and during the fifteen-day notice period, the Board received no request for a hearing or any replies. 23. Applicant did not submit a request for a refund of the fee paid with the District Commission. 24. In its reconsideration decision, the Board found that the incompleteness issue considered under JO 4-240 was moot because Applicant had not submitted a refund request to the District Commission.

Discussion

The pending cross motions for summary judgment raise two issues. The first is whether Applicant’s appeal is moot because Applicant failed to follow proper procedure in requesting a refund. The second is whether Applicant’s application fee for the minor amendment to its already-approved master plan should be subject to the statutory cap, 10 V.S.A. § 6083a(a)(6), that was applied to the master plan, or instead should be considered an distinct application subject to a new cap.

I. Summary Judgment Standard

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Burlington v. Fairpoint Communications, Inc.
2009 VT 59 (Supreme Court of Vermont, 2009)
Appeal of Weeks
712 A.2d 907 (Supreme Court of Vermont, 1998)
Tarrant v. Department of Taxes
733 A.2d 733 (Supreme Court of Vermont, 1999)
In Re Grievance of Danforth
812 A.2d 845 (Supreme Court of Vermont, 2002)
Argast v. State Environmental Board
463 A.2d 214 (Supreme Court of Vermont, 1983)
Pollak v. City of Burlington
608 A.2d 659 (Supreme Court of Vermont, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Snyder Taft Corners Act 250, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snyder-taft-corners-act-250-vtsuperct-2016.