Snohomish County Public Utility District No. 1 v. Pacificorp

745 F. Supp. 1581, 1990 U.S. Dist. LEXIS 12912, 1990 WL 139466
CourtDistrict Court, D. Oregon
DecidedApril 10, 1990
DocketCiv. No. 89-1295-MA
StatusPublished
Cited by3 cases

This text of 745 F. Supp. 1581 (Snohomish County Public Utility District No. 1 v. Pacificorp) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snohomish County Public Utility District No. 1 v. Pacificorp, 745 F. Supp. 1581, 1990 U.S. Dist. LEXIS 12912, 1990 WL 139466 (D. Or. 1990).

Opinion

OPINION

MARSH, District Judge.

Plaintiff, Snohomish PUD, filed this action seeking declaratory relief in a contract dispute between defendants Paeificorp, et al. and the Washington Public Power Supply System (“Supply System”). In addition, plaintiff filed motions to intervene and consolidate the present action with Pacificorp, et al. v. Washington Public Power Supply System, Civ. No. 89-1282-MA (filed Nov. 22, 1989). Paeificorp and other investor owned utilities (“IOUs”), the Supply System and the Bonneville Power Administration (“BPA”) move to dismiss plaintiffs complaint. On March 5, 1990, a hearing was held on the limited issue of whether plaintiff has standing to sue under the project exchange contract in federal court. Although defendants raised several grounds for dismissal, I indicated to the parties at oral argument that I would decide the threshold issue of standing before allowing the case to proceed any further.

In my original opinion filed March 21, 1990, I found that plaintiff did not have standing to maintain this action and thus, defendants’ motions to dismiss were granted and the remaining motions to strike, intervene, and to consolidate were moot. Upon receipt of a letter from counsel for the BPA and the Supply System, my previous opinion is amended solely to correct certain undisputed background information found on pages three and four of this opinion.

BACKGROUND

Defendant Supply System, an association of nineteen Washington public utility districts and four Washington cities formed to finance, construct, own and operate electrical generating facilities. It is a municipal corporation and joint operating agency under Washington State law.

Each of the IOUs executed Project Exchange Agreements (PEAs) with the Supply System and the BPA. The PEAs provide for the purchase and assignment of shares of project capability. Pursuant to the PEAs, each IOU agreed to purchase, from the Supply System, 6.494% of the “project capability” of a nuclear power plant at Hanford, Washington, to be known as WPPSS No. 1. Under these agreements, each IOU assigned its share of project capability to the BPA in exchange for electrical power and energy during the period of June 30, 1980 through June 30, 1996.

Each IOU agreed to pay the Supply System for its share of project capability on an annual basis and in accordance with a formula set forth in the agreement. From June 1980, through June 1990, each IOU’s payments are based on certain BPA wholesale rate schedules. Beginning on June 30, 1990, and continuing through June 30, 1996, each IOU is obligated to pay a proportionate share of the Supply System’s costs related to the acquisition, construction and operation of the Project.

This action arises out of litigation originally filed by the IOUs against the Supply System in Multnomah County Circuit Court for breach of their identical Project Exchange contracts. The IOUs alleged that the Supply System was in breach of the PEAs due to termination of the construction project. The IOUs sought a declaration that they were excused from further performance under the PEAs, in addition to claims for damages. The Supply System removed the action to this court and the IOUs moved to remand the action back to Multnomah County on the basis that this [1583]*1583court lacked subject matter jurisdiction over the contracts. The matter was originally set for oral argument on January 29, 1990, but was struck upon notification of the parties that a settlement agreement was in progress. On February 28, 1990, the parties to that action entered a stipulated order of dismissal which was signed by me on that date.1

Snohomish provides electricity to approximately 200,000 customers in the State of Washington and is one of the 105 “preference customers” under the Bonneville Power Act of 1937 and pursuant to a Net Billing Agreement. The Net Billing Agreements, entered into by over 100 municipal utility companies, provide for the distribution of electricity to the project participants through the BPA. In its own Net Billing Agreement with the Supply System and the BPA, Snohomish has agreed to purchase a 19% share of WPPSS Project 1 capability.

After the Supply System removed the Pacificorp action to this court, Snohomish filed this case for declaratory relief based upon the anticipated breach of the PEAs. In addition, plaintiff sought to intervene in the pending action between Pacificorp and the Supply System and consolidate the two matters on the basis that the two cases involved the same contractual dispute.2 In its complaint, Snohomish seeks a judicial declaration of the rights and responsibilities of the parties to the project exchange agreements, money damages for anticipatory breach by the IOUs on behalf of the Supply System or BPA, and in the alternative, rescission and restitution on behalf of the Supply System or BPA.

STANDARDS

Dismissal for failure to state a claim is proper only when it appears to a certainty the plaintiff can prove no set of facts in support of his claim that would entitle him to relief. Gibson v. United States, 781 F.2d 1334, 1337 (9th Cir.1986), cert. denied, 479 U.S. 1054, 107 S.Ct. 928, 93 L.Ed.2d 979 (1987). For the purpose of the motion to dismiss, the complaint is liberally construed in favor of the plaintiff, and its allegations are taken as true. Schowengerdt v. General Dynamics Corp., 823 F.2d 1328, 1332 (9th Cir.1987).

DISCUSSION

In order to establish federal standing, plaintiff must first meet the requirements of Article III of the Constitution by alleging a “present or immediate injury in fact, where the party requesting standing has alleged such a personal stake in the outcome of the controversy as to assure that concrete adverseness which sharpens the preservation of issues.” Phillips Petroleum Co. v. Skutts, 472 U.S. 797, 804, 105 S.Ct. 2965, 2970, 86 L.Ed.2d 628 (1985). Thus, because plaintiff seeks declaratory relief relating to a contract to which it is not a party, it must demonstrate that the alleged injury poses more than a remote or speculative threat to its interests as well as demonstrating a personal stake in the outcome. See id. at 804, 105 S.Ct. at 2970 (litigant must normally assert his own legal interests rather than those of third parties).

a. Injury

Plaintiff contends that if the IOUs are allowed to breach the terms of the PEAs with the Supply System and BPA, this breach will ultimately result in higher overall operating costs which will necessarily be passed on to Snohomish and the other 104 utility districts who are parties to net billing contracts. Because the parties to the PEAs have entered into a settlement agreement and have entered a stipulated dismissal of their contract dispute, plaintiffs claims of a potential injury due to the prior anticipated breach of contract are moot. In such a situation where the parties to the PEAs are no longer at odds and where the [1584]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
745 F. Supp. 1581, 1990 U.S. Dist. LEXIS 12912, 1990 WL 139466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snohomish-county-public-utility-district-no-1-v-pacificorp-ord-1990.