Snelling v. Dine

170 N.E. 403, 270 Mass. 501, 1930 Mass. LEXIS 1043
CourtMassachusetts Supreme Judicial Court
DecidedMarch 3, 1930
StatusPublished
Cited by18 cases

This text of 170 N.E. 403 (Snelling v. Dine) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snelling v. Dine, 170 N.E. 403, 270 Mass. 501, 1930 Mass. LEXIS 1043 (Mass. 1930).

Opinion

Crosby, J.

This action, brought by the plaintiff as trustee in bankruptcy of the Socold Refrigerating Corporation, is to recover for the alleged breach of a contract under which the defendant, in July, 1928, ordered of the plaintiff fifty “Socold Refrigerators” of specified sizes, the price being $100 “each f.o.b. factory ... to be delivered and paid for as soon as ready.” This order . was accepted by the plaintiff. The case is before this court on exceptions of both parties. The plaintiff excepted to that part of the charge to the jury which dealt with the question of damages, and to the refusal to give certain rulings in connection therewith. The defendant excepted to the exclusion of evidence and to the disposition of certain requests for rulings.

When the plaintiff was appointed trustee in bankruptcy, the refrigerating corporation had been engaged in the manufacture of refrigerators. At the time the contract between the parties was entered into, there were no refrigerators, of the sizes therein specified, assembled and ready for delivery in the possession of the plaintiff, but he did have [505]*505the component parts necessary for their manufacture. The completed product consisted of the following parts: a cabinet, motor, freezer, condenser, frost unit, thermostat, expansion valves and tubing. The plaintiff proceeded to assemble and complete ten refrigerators of the sizes called for by the contract, and shortly thereafter notified the defendant that they were ready for delivery. The defendant at that time refused to take them and subsequently continued to do so, although at various times he accepted and paid for seven of them. The three remaining which had been assembled were finally disposed of for $185. The additional forty refrigerators which the defendant had agreed to purchase were never assembled, and the parts which would have been used to make them were sold separately as parts.

The only testimony relating to damages was that of one McIntosh, who was in general charge of the business of the plaintiff in the manufacture and sale of refrigerators. On the question of damages, the plaintiff requested the trial judge to give the following instructions: “ (18). If the jury finds that the defendant broke the contract, the plaintiff’s damages as to refrigerators not manufactured is the difference between the contract price and the cost of manufacture after making due allowance for the value of materials the plaintiff had on hand”; and “(19). If the jury finds that the plaintiff had in his possession all the parts necessary to manufacture forty refrigerators then the cost of manufacture to the plaintiff is the fair market value of such parts at the time when the defendant should have taken the refrigerators plus the reasonable labor cost of assembling the same.” These instructions were refused, and the trial judge instructed the jury in substance that if they should find for the plaintiff, the measure of damages would be the difference, if any, between the contract price and the fair market value of completed Socold refrigerators at the time the goods ought to have been accepted, or if no time was fixed for acceptance then at the time of refusal to accept. The plaintiff excepted to the instructions so given, and to the refusal to give the rulings above set forth.

[506]*506It is an elementary principle in the law of damages that, where a contract is broken, the promisee is entitled to be placed in as good position as he would be in had the promisor fulfilled his contract. Garfield & Proctor Coal Co. v. New York, New Haven & Hartford Railroad, 248 Mass. 502, 507. It was said in John Hetherington & Sons, Ltd. v. William Firth Co. 210 Mass. 8, at page 21: “The fundamental principle of law upon which damages for breach of contract are assessed is that the injured party shall be placed in the same position he would have been in, if the contract had been performed, so far as loss can be ascertained to have followed as a natural consequence and to have been within the contemplation of the parties as reasonable men as a probable result of the breach, and so far as compensation therefor in money can be computed by rational methods upon a firm basis of facts.” Having this principle in mind, we consider first the measure of damages applicable to the forty refrigerators that were never completed.

If the defendant had performed his agreement to accept and pay for the refrigerators, the plaintiff would have realized a profit amounting to the difference between the contract price and the cost of the component parts, plus the cost of assembling them into the completed refrigerators. Because of the defendant’s breach, these refrigerators were not assembled, and the plaintiff never received for them the market price of completed Socold refrigerators. The plaintiff was under no obligation to continue, for the benefit of the defendant, to manufacture the refrigerators, expend money in their assembling, and take the risk attendant on finding a market for them. Besides, the plaintiff could not enhance damages by assembling parts and completing the refrigerators after notice that the defendant refused to receive them. Cumberland Glass Manuf. Co. v. Wheaton, 208 Mass. 425. Roehm v. Horst, 178 U. S. 1. Meyer Brothers Drug Co. v. McKinney, 137 App. Div. (N. Y.) 541, affirmed 203 N. Y. 533. The rule stated in Daniels v. Newton, 114 Mass. 530, is not applicable to the facts in the present case. If the difference between the contract price and the market price is taken as the measure of damages, it must be on the [507]*507assumption that the plaintiff at the time of the breach, or subsequently, had in his possession the goods contracted for and that these goods could be sold in the open market. Garfield & Proctor Coal Co. v. New York, New Haven & Hartford Railroad, supra. Williston on Sales (2d ed.) § 582. To apply the rule of damages as stated by the trial judge in respect to the forty uncompleted refrigerators, is to ignore the fact that they never came into existence and that the plaintiff never received their market value. The application of this rule would not place the plaintiff in the position he would be in had the defendant fully performed his obligations under the contract.

Under the provisions of G. L. c. 106, the same result follows. Section 53 (3) is applicable only when the goods agreed to be sold are in existence at the time of the defendant’s breach, or, as in Garfield & Proctor Coal Co. v. New York, New Haven & Hartford Railroad, supra, when they subsequently came into existence. Williston on Sales (2d ed.) §§ 582, 583a. G. L. c. 106, § 53 (4) reads: “If, while labor or expense of material amount are necessary on the part of the seller to enable him to fulfil his obligations under the contract to sell or the sale, the buyer repudiates the contract or the sale, or notifies the seller to proceed no further therewith, the buyer shall be liable to the seller for no greater damages than the seller would have suffered if he did nothing toward carrying out the contract or the sale after receiving notice of the buyer’s repudiation or countermand. The profit which the seller would have made if the contract or the sale had been fully performed shall be considered in estimating such damages.” Upon the facts disclosed by the record, this clause is applicable to the uncompleted refrigerators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commercial Wharf East Condominium Ass'n v. Waterfront Parking Corp.
588 N.E.2d 675 (Massachusetts Supreme Judicial Court, 1992)
Louise Caroline Nursing Home, Inc. v. Dix Construction Corp.
285 N.E.2d 904 (Massachusetts Supreme Judicial Court, 1972)
Charlotte Theatres, Inc. v. Gateway Co.
191 F. Supp. 834 (D. Massachusetts, 1961)
Good v. Howlett
16 Mass. App. Dec. 120 (Mass. Dist. Ct., App. Div., 1959)
Ficara v. Belleau
117 N.E.2d 287 (Massachusetts Supreme Judicial Court, 1954)
Kelsey v. Hampden Court Hotel Co.
15 Mass. App. Div. 125 (Mass. Dist. Ct., App. Div., 1950)
Associated Perfumers, Inc. v. Andelman
55 N.E.2d 209 (Massachusetts Supreme Judicial Court, 1944)
Carrig v. Gilbert-Varker Corp.
50 N.E.2d 59 (Massachusetts Supreme Judicial Court, 1943)
Britt v. Schertzer
8 Mass. App. Div. 149 (Mass. Dist. Ct., App. Div., 1943)
Charles Street Garage Co. v. Kaplan
45 N.E.2d 928 (Massachusetts Supreme Judicial Court, 1942)
Stern v. Potter
1 Mass. App. Dec. 120 (U.S. District Court, 1941)
Botti v. Venice Grocery Co.
35 N.E.2d 491 (Massachusetts Supreme Judicial Court, 1941)
Cragin v. Jones
186 N.E. 578 (Massachusetts Supreme Judicial Court, 1933)
Package Confectionery Co. v. Perkit
184 N.E. 166 (Massachusetts Supreme Judicial Court, 1933)
Outhwaite v. A. B. Knowlson Co.
242 N.W. 895 (Michigan Supreme Court, 1932)
Country Club Soda Co. v. Arbuckle
181 N.E. 256 (Massachusetts Supreme Judicial Court, 1932)
Whitty Manufacturing Co. v. Clark
180 N.E. 315 (Massachusetts Supreme Judicial Court, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
170 N.E. 403, 270 Mass. 501, 1930 Mass. LEXIS 1043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snelling-v-dine-mass-1930.