Sneeden v. United States

31 Fed. Cl. 671, 1994 U.S. Claims LEXIS 155, 1994 WL 443729
CourtUnited States Court of Federal Claims
DecidedAugust 11, 1994
DocketCong. Ref. No. 92-865 X
StatusPublished
Cited by3 cases

This text of 31 Fed. Cl. 671 (Sneeden v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sneeden v. United States, 31 Fed. Cl. 671, 1994 U.S. Claims LEXIS 155, 1994 WL 443729 (uscfc 1994).

Opinion

REPORT OF THE HEARING OFFICER

HODGES, Judge.

This congressional reference arises from a private relief bill to compensate Donald W. Sneeden, Mary S. Sneeden, and Henry Best, stockholders and officers of Lincoln Construction Company, Inc. (Lincoln).1 Under 28 U.S.C. § 2509, either House of Congress may refer such a bill to the Chief Judge of this Court for a report. The Chief Judge designates a hearing officer to conduct findings of fact in accordance with our rules and practice. A three-judge panel of this court reviews the hearing officer’s findings.

In accordance with 28 U.S.C. § 2509 this court must determine the facts bearing upon the question presented by Congress. We inform Congress whether the demand is a legal or equitable claim, or a gratuity, and the amount due the claimant, if any.2 Then Congress acts on the bill referred or passes a substitute bill.

The substance of the hearing officer’s report is advisory and conclusions whether the claim is legal or equitable, and compensation due, are recommendations only. The facts of each case are sui generis; congressional reference cases have no binding value as precedent.

The bill referring this case to the Court of Federal Claims asked only one question related to the merits: Did the United States act in bad faith in settling plaintiffs’ claim before the Board of Contract Appeals. A careful review of the record of this trial does not support a finding of bad faith by the Government, as that term is generally accepted by the legal community. For that reason alone, we find that an award to Lincoln would be a gratuity.

I

On February 14, 1978 the United States Army Corps of Engineers awarded Contract No. DAWC 54-78-C-0020 to J. Lawson Jones Construction Company, Inc. (Jones) as the prime contractor on the Wilkerson Creek Bridge Replacement Project in Hyde County, North Carolina. The contract contemplated replacing an existing bridge over the Atlantic Intracoastal Waterway with a new bridge. Construction for the roadways form[673]*673ing the approaches to the bridge required over 325,000 cubic yards of earth embankments. The contract completion date was February 27, 1980. Lincoln began work in March 1978 as a subcontractor.

Lincoln’s responsibility was to construct the earthen embankment approach to the bridge. The government’s project was based upon a design by the North Carolina Department of Transportation. The original design had provided for embankments no higher than 30 feet. The Government altered this design in response to a value engineering proposal.3 The value engineering program changes raised the embankment to 45 feet, shortened the concrete portion of the bridge, and increased the earthwork to a 52-foot fill. Lincoln learned of the changes only after filing a Freedom of Information Act request.

Lincoln experienced difficulty performing under the changed specifications because of moisture conditions of the soil. Following several unsuccessful attempts to resolve the moisture problems caused by the changed specifications, the Corps blamed plaintiffs and directed that Lincoln remove its quality control officer.

Lincoln hired Dr. Ralph Fadum, Dean of Engineering at North Carolina State University, a recognized soils expert. He concluded that the contract could not be performed because of defective specifications and composition of the soil.

Following meetings with Senator Robert Morgan’s staff and Corps personnel, Lincoln requested a final decision from the Contracts ing Officer on its claim. The Contracting Officer denied Lincoln’s claim on November 5, 1979.

In January 1980, Congressman Charlie Rose offered his assistance and arranged a meeting among Corps personnel, Mr. Snee-den, and two presidential assistants. At this meeting, the Corps’ Deputy Director for Civil Works recommended that Lincoln appeal the CO’s decision to the division engineer in Atlanta. That meeting did not resolve the dispute, and Lincoln took its case to the Corps of Engineers Board of Contract Appeals in December 1980. The Board did not issue an opinion for five years. The trial lasted seven weeks. Lead counsel for the Corps was Mr. Alva Hall.

The Wilkerson Bridge project was completed in September 1981, eight months after the trial and three and one-half years after Lincoln commenced performance. After months of no decision from the Board, Lincoln’s financial situation deteriorated to the point that Lincoln’s surety no longer would support Lincoln. Lincoln was unable to secure other contracts because it could not be bonded. Lincoln filed for bankruptcy in 1982; its principal asset was its claim against the Government.

Two years after trial, still with no Board opinion, Lincoln’s counsel requested a pre-deeisional audit, and the Corps agreed. The 1983 audit concluded that Lincoln’s claim totaled $2,572,028. However, the parties were unable to agree on the audit and the Corps would not negotiate cost figures. The audit was used to furnish information to the Contracting Officer concerning the claims. The accountant in charge of the 1983 audit noted in his memo on the audit report that the results were intended for evaluation of the claimed costs, and not for any other use. This audit was revised during the quantum negotiations three years later. In January 1986, five years after trial, the Board ruled for Lincoln on all counts and directed the parties to settle the quantum by negotiation. The Corps sought reconsideration of the Board’s decision, and this motion was denied in June 1986. Five and a half years after trial began, the Board closed the liability phase of plaintiffs’ claim.

The Corps designated Mr. Hall to negotiate the quantum issue. Mr. Hall considered the Board’s decision to have been wrongly decided, and he wanted to try the quantum portion of Lincoln’s claim before the Board. He believed that the Government had defenses to the quantum issue, and this belief determined his beginning point for the quantum negotiations.

[674]*674II

The first issue for negotiation was the amount of interest applicable to Lincoln’s claim. The Government’s internal documents supported an interest rate of 79.98%, but the rate negotiated at the first meeting in February 1986 was 70%. Plaintiffs contend that this was evidence of the government’s bad faith.

The Contracting Officer was required to act impartially in negotiating quantum, but the rights of both parties must be considered. The 79.98% interest rate was based on a standard index rate from November 1979 to February 1986. Some claimed costs were incurred after November 30, and the Corps was not permitted to pay interest on claims not yet incurred. The original calculation of 79.98% did not reflect the amount to which plaintiffs were entitled, as the government argued in their negotiations. Plaintiffs now state that they did not agree to the 70% interest rate.

Plaintiffs were represented by well-informed attorneys who were experienced negotiators. Plaintiffs could not show that they accepted a 70% interest rate involuntarily. They argue that the Government had authority to settle at an 80% rate, and thus the 70% rate was an act of bad faith, but plaintiffs were not under duress to accept the 70% interest rate.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Banfi Products Corp. v. United States
40 Fed. Cl. 107 (Federal Claims, 1997)
Kanehl v. United States
41 Cont. Cas. Fed. 77,160 (Federal Claims, 1997)
Sneeden v. United States
33 Fed. Cl. 303 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
31 Fed. Cl. 671, 1994 U.S. Claims LEXIS 155, 1994 WL 443729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sneeden-v-united-states-uscfc-1994.