Snavely Co. v. Laurel Lake Retirement, Unpublished Decision (10-28-1999)

CourtOhio Court of Appeals
DecidedOctober 28, 1999
DocketNo. 76331.
StatusUnpublished

This text of Snavely Co. v. Laurel Lake Retirement, Unpublished Decision (10-28-1999) (Snavely Co. v. Laurel Lake Retirement, Unpublished Decision (10-28-1999)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snavely Co. v. Laurel Lake Retirement, Unpublished Decision (10-28-1999), (Ohio Ct. App. 1999).

Opinion

JOURNAL ENTRY AND OPINION
This cause came on to be heard upon the accelerated calender pursuant to App.R. 11.1 and Loc.App.R. 25, the record from the Cuyahoga County Court of Common Pleas, oral argument and the briefs of counsel. Snavely Company, Inc., plaintiff-appellant, appeals from the judgment of the Cuyahoga County Court of Common Pleas, General Division, Case No. CV-377456, in which the trial court granted the motion to stay the underlying proceedings pending completion of arbitration filed by Laurel Lake Retirement Community, defendant-appellee. Plaintiff-appellant assigns a single error for this court's review.

Plaintiff-appellant's appeal is not well taken.

In January, 1986, defendant-appellee entered into a development agreement with the Mediplex Group, Inc. and its subsidiaries the purpose of which was to develop and construct the Laurel Lake Retirement Community in Hudson, Ohio. Mediplex subsequently entered into a construction contract in 1987 with plaintiff-appellant as the general contractor responsible for construction of the project sponsored by defendant-appellee. The construction contract identified defendant-appellee as the sponsor of the construction project and specifically provided that defendant-appellee would be the owner of the land upon which the retirement community was to be built upon closing of the bond financing for the project. Financing was complete in February, 1988, at which time defendant-appellee became owner of the land and the construction project itself. At this point, the construction project was approximately 30% completed.

The construction contract in question contained the following arbitration provision:

All claims, disputes and other matters in question between the Contractor and the Owner arising out of, or relating to, the Contract Documents or the breach thereof, shall be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise. No arbitration shall include by consolidation, joinder or any other manner, parties other than the Owner, the Contractor, the Architect and any other persons substantially involved in a common question of fact or law, whose presence is required if complete relief is to be accorded in the arbitration. No person other than the Owner, Contractor or Architect shall be included as an original third party or additional third party to an arbitration whose interest or responsibility is insubstantial. Any consent to arbitration involving an additional person or persons shall not constitute consent to arbitration of any dispute not described therein. The foregoing agreement to arbitrate and any other agreement to arbitrate with an additional third person or persons duly consented to by the parties to the Owner-Contractor Agreement shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof.

In addition, the general conditions of the contract contains the following provision entitled Successors and Assigns:

The Owner and the Contractor each binds himself, his partners, successors, and assigns and legal representatives to the other party hereto and to the partners, successors, assigns and legal representatives of such other party in respect to all covenants, agreements and obligations contained in the Contract Documents. Contractor shall not assign the Contract or sublet it in part or as a whole without the written consent of the Owner, nor shall the Contractor assign any moneys due or to become due to him hereunder, without the previous written consent of the owner.

Upon becoming owner of the project, defendant-appellee appointed its own construction representatives to attend on-site construction meetings with plaintiff-appellant and others involved in the project, as well as coordinate payment for work completed on the project to date. Ultimately, all payments on the project to plaintiff-appellant were approved and made by defendant-appellee. The project was completed by plaintiff-appellant in October, 1988.

In July 1998, defendant-appellee allegedly discovered for the first time that a sprinkler system at the retirement home that had been constructed and installed by plaintiff-appellant was defective in certain areas of the retirement community. Defendant-appellee maintained that the sprinkler system had not been installed by plaintiff-appellant in accordance with contract specifications thereby reducing the systems effectiveness and estimated life span. Defendant-appellee believed that the entire sprinkler system would need to be replaced due to the existing defects.

Pursuant to the construction contract, plaintiff-appellant was allegedly responsible for materials and installation of the fire protection sprinkler system at Laurel Lake Retirement Community. On July 8, 1998, a letter was sent by defendant-appellee notifying plaintiff-appellant of the alleged breach of the construction contract. In the correspondence, defendant-appellee demanded that plaintiff-appellant promptly replace the defective sprinkler system and non-conforming installation under the terms of the construction contract.

Upon receipt of defendant-appellee's correspondence, plaintiff-appellant apparently refused to replace the sprinkler system in question. Defendant-appellee was then forced to obtain the services of a separate contractor to remove and replace the defective sprinkler system installed by plaintiff-appellant.

On December 30, 1998, defendant-appellee filed a demand for arbitration against plaintiff-appellant with the American Arbitration Association, pursuant to the arbitration provision contained in the 1987 construction contract executed by the Mediplex Group, Inc. and plaintiff-appellant Defendant-appellee maintained that it was entitled to proceed under the arbitration provision as a successor in interest and an intended third-party beneficiary under the contract.

On February 19, 1999, plaintiff-appellant filed the instant declaratory judgment action in the Cuyahoga County Court of Common Pleas in which it maintained that it was not required to arbitrate any dispute with defendant-appellee since it was not a party or signatory to the 1987 construction contract. On March 3, 1999, defendant-appellee filed a motion to stay the, action pending completion of the previously instituted arbitration proceedings before the American Arbitration Association.

On March 12, 1999, the trial court conducted an oral hearing on the pending motions. At the conclusion of the hearing, the trial court issued an order providing that the arbitration proceedings were stayed as to both parties until further notice of the trial court and stated further that it would rule upon the issue of whether standing to enforce an arbitration clause in a contract was itself an issue that was subject to arbitration. The trial court requested additional briefs on that issue.

On April 7, 1999, the trial court granted defendant-appellee's motion to stay the declaratory judgment action through the following entry:

Motion of Defendant Laurel to stay this action pending completion of arbitration case number #5311000027298 before the American Arbitration Association is granted; stay of all arbitration proceedings is hereby lifted; all proceedings in the within action are stayed until further order of the court. Final.

On April 23, 1999, plaintiff-appellant filed a timely notice of appeal pursuant to R.C. 2711.02 and 2505.02

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
Didado v. Lamson & Sessions Co.
610 N.E.2d 1085 (Ohio Court of Appeals, 1992)
Sasaki v. McKinnon
707 N.E.2d 9 (Ohio Court of Appeals, 1997)
Ervin v. American Funding Corp.
625 N.E.2d 635 (Ohio Court of Appeals, 1993)
Divine Construction Co. v. Ohio-American Water Co.
599 N.E.2d 388 (Ohio Court of Appeals, 1991)
St. Vincent Charity Hospital v. URS Consultants, Inc.
677 N.E.2d 381 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Snavely Co. v. Laurel Lake Retirement, Unpublished Decision (10-28-1999), Counsel Stack Legal Research, https://law.counselstack.com/opinion/snavely-co-v-laurel-lake-retirement-unpublished-decision-10-28-1999-ohioctapp-1999.