Smizel v. Odanah Iron Co.

74 N.W. 488, 116 Mich. 149, 1898 Mich. LEXIS 659
CourtMichigan Supreme Court
DecidedMarch 15, 1898
StatusPublished
Cited by2 cases

This text of 74 N.W. 488 (Smizel v. Odanah Iron Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smizel v. Odanah Iron Co., 74 N.W. 488, 116 Mich. 149, 1898 Mich. LEXIS 659 (Mich. 1898).

Opinion

Montgomery, J.

This is an action for negligent injury. On the 26th of February, 1890, the defendant was the owner of the Cary Mine. At this mine was a [151]*151shaft known as “No. 1 Shaft,” which shaft was about 148 feet deep. The first level of said shaft was about 35 feet from the surface, the second level about 50 feet below the first level, and the third level 63 feet below the second level. Shortly before the day in question, the defendant company caused a platform to be built at the second level above mentioned. • The shaft at that point was about 8 by 10 feet across, and the platform was about 10 by 12 feet; the planks of the platform projecting onto the rock at each edge of the shaft. This platform was built of timber 8 by 10 inches in diameter, and three timbers running crosswise of the shaft. On these timbers were laid 2-inch planks. Through this platform was a hole used for the skip-road, which hole was about 4 feet 6 inches square, and near that hole was what was known as the “manhole” or “ladder-way;” being a hole through which men passing up and down the ladder-way might pass, which'was sufficiently large to admit of the passage of a human body of ordinary size. The platform in question extended over the entire shaft, except for the holes above mentioned. As to whether the planks were spiked down is a matter of controversy. Defendant’s counsel contend that the undisputed testimony shows that they were, while plaintiff’s counsel contend that it was a question for the jury.

On the day in question, the plaintiff, together with another workman at the Cary Mine, named Prelomski, were engaged, together with the shift-boss, whose name was Matthews, in building what is known as a “skip-rest,” just beneath the surface of the platform. This skip-rest was built of timbers, and was located about six feet below the level of the platform, and was used for the purpose of allowing the skip to rest thereon while the same was being loaded. At the third level, 63 feet below, the miners were engaged in mining ore by blasting and drilling and picking, and the testimony shows that at the third level a drift had been mined out to the east and to the west of the shaft in question, to the east about 25 feet and to the west about 15 feet, and blasting was going on at the end of one [152]*152of these drifts, but whether in the east or west drift is not shown by the evidence in this case. While the plaintiff and shift-boss and Prelomski were thus engaged in building the skip-rest, warning was given by the miners below that they were about to fire a blast, and the shift-boss ordered the two men who were working with him to leave the place where they were working, under the platform, and all three went up onto the platform, thence east across the platform into a drift, and through a door into what is known as the “ open pit.” After these three persons had arrived at the open pit, the blast was fired, and the shift-boss stepped out to the shaft, and found it filled with smoke. He then noticed that some of the planking of the platform at the second level had been disturbed by the blast, and he and some miners who were on the west side of the shaft took hold of the planks which had been disturbed, and laid them down fiat upon the platform as they had been originally. The planks which the shift-boss thus rearranged were the long planks, being about 12 feet long. Between the hole made by the skip-road and the edge of the shaft the planks were short, being approximately 6 feet long. The shift-boss testified that he did not notice that any of the short planks were disturbed or overthrown.

After the shift-boss had thus rearranged the platform, he called to the men who were in the open pit to come up the ladder, and go over into another shaft to work; and the shift-boss walked across the platform to the ladder-way, followed by Smizel, the plaintiff, who was in turn followed by Prelomski. As the shift-boss started up the ladder-way, Smizel fell, and it is claimed by him that he stepped upon a plank which had been blown loose by the explosion, which slipped with him, and that he then fell through the hole made in the platform, falling to the bottom of the shaft, by which he was seriously injured. None of the timbers in the platform were disturbed, nor were any of the planks composing the platform broken. The platform in question was built under the supervision of [153]*153one Thomas Bolitho, who, so far as appears in this case, was entirely competent to do that work. This platform in question was used simply for men to stand upon and to pass over. It is claimed by the defendant that the undisputed testimony shows that a platform such as this was the usual and customary platform used in the mines in this locality for the purpose for which this platform was intended. It is further claimed by the defendant that the probability of the platform’s being disturbed by blasting below, under circumstances such as were shown in this case, was very remote, and that it was not such an occurrence as would be taken into consideration or as would be apprehended by reasonably prudent mining men.

As the plaintiff’s counsel concede the importance of the question of fact as to whether the planks were spiked, it is necessary, to look into the record to ascertain whether defendant’s contention that the evidence was conclusive of the fact should be sustained. Two witnesses for the defendant testify that the planks were spiked, viz., Matthews and Bolitho. Matthews was the shift-boss, who testified that, after the explosion, boards were torn up, and he replaced them. He was asked, “Do you know whether those planks were spiked3?” and answered, “Yes, sir; they were spiked.” He further testified as follows:

l‘Q. What did you do with the spikes when you put them down?
“A. The spikes went right down.
“Q. You mean the spikes fit the same holes they had been drawn out of ?
“A. They might have. The boards went right down just as even as they are there [pointing to the model],
“Q. What I want to find out is, when you jumped onto the plank you jumped on so that the spikes went right down into the timbers again?
“A. Perhaps so. They went down even.”

He also testified that he used no hammer, and that it took him but a very short time to replace the planks. Bolitho, who built the platform, testified that he spiked the plank down. On the part of the plaintiff, Prelomski, who was working with plaintiff, testified:

[154]*154“I didn’t see any nails in the loose plank after Smizel went through. If there were spikes in it, sure I must have seen it; I would have seen it. ”

On cross-examination he testified as follows:

‘ ‘ Q. Do you know whether there were any spikes in it at that time or not ?
“A. I didn’t see any spikes in the plank.
‘ ‘ Q. Did you look to see whether there were any in it or not ?
“A. If there were spikes there I would have seen it; everybody would have seen it.
“Q. Did you look to see whether there were any spikes in it or not ?
“A. No.
“Q. Did you see any spikes in the other planks ?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hewitt v. East Jordan Lumber Co.
98 N.W. 992 (Michigan Supreme Court, 1904)
McQueeny v. Chicago, Milwaukee & St. Paul Railway Co.
94 N.W. 1124 (Supreme Court of Iowa, 1903)

Cite This Page — Counsel Stack

Bluebook (online)
74 N.W. 488, 116 Mich. 149, 1898 Mich. LEXIS 659, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smizel-v-odanah-iron-co-mich-1898.