This text of 232 F. Supp. 204 (Smither & Co. v. Calvin-Humphrey Corp.) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smither & Co. v. Calvin-Humphrey Corp., 232 F. Supp. 204, 1964 U.S. Dist. LEXIS 6522 (D.D.C. 1964).

Opinion

YOUNGDAHL, District Judge.

Plaintiff’s claim and defendants’ counter-claim came on for trial before this Court sitting without a jury, on April 22, 23, 24, 25, and 28, 1964. Subsequent thereto, both plaintiff and defendants filed memoranda at the request of the Court, and on May 28, 1964, plaintiff filed a reply memorandum with the permission of the Court after defendants had sought and received additional time for the filing of their memorandum.

The Court has carefully considered the testimony adduced before it (both as it was adduced and in the form of a full transcript), exhibits admitted into evidence, as well as all of the above memoranda, and has reached the following conclusions, which shall be considered as findings of fact and conclusions of law pursuant to Rule 52(a), Federal Rules of Civil Procedure:

[206]*2061. On June 29, 1962, plaintiff filed suit to enforce a mechanic’s lien for labor allegedly performed and materials allegedly furnished on a building at 1800 K Street, N.W. in the District of Columbia. The owner of the building, Calvin-Humphrey Corporation, one of the defendants herein (and referred to hereinafter as defendant), released said mechanic’s lien by filing a corporate surety bond, and plaintiff brought suit to enforce the mechanic’s lien and named as defendants the Calvin-Humphrey Corporation, the debtor, and the New Amsterdam Casualty Company, as the surety on the bond. No question arises as to the validity of the lien or its release by the filing of a surety bond. Defendant filed an answer and a counter-claim, claiming damages caused by the alleged negligence and incompetence of plaintiff’s employees and by the alleged loss^ of rental income to the defendant as a result of the failure of plaintiff to complete the work by August 15, 1961.

2. The intended agreement between the parties is embodied in plaintiff’s exhibit 4, a letter from Paul Burgoldt for Smither & Company (and approved by James M. Smither, president of Smither & Co.) to the Calvin-Humphrey Corporation, attention Mr. William T. Han-nan, President. The letter is dated June 2, 1961, and was accepted on June 8, 1961 by Mr. Hannan, who signed the letter in a blank labeled “accepted.”

3. Mr. Hannan added to the document, at the bottom of the last page below the above three signatures, the following typewritten words: “WORK TO BE COMPLETED BY AUGUST 15, 1961.” This was followed by his signed initials, “WTH.” This date of completion was never agreed to by Mr. Burgoldt or Mr. Smither, but they never protested this date. Plaintiff had begun work on the project before June 2, and continued to perform the work with knowledge that defendant had added an August 15 date. The date of August 15 was passed with the work not completed and without an official notification by defendant that it considered the contract breached by plaintiff, and after August 15, defendant made certain change-orders and instructions for additional work to be performed by plaintiff. (Tr. 18; 113-117; 142-145.) Substantial portions of the work set forth in the letter of June 2, as well as certain additional demolition work, were being performed throughout September, 1961. (Tr. 18; 113; 143-144; 347-353; 358; 369; defendant’s exhibits 2 and 4.) The Court therefore finds that time was not of the essence of this contract, and to the extent that plaintiff waived its objection to the target date of August 15 by performing work under a document to which this date had been added by Mr. Hannan, to the same extent the defendant waived its right to insist upon completion by August 15 by permitting plaintiff to continue working in September. On October 19, 1961, defendant notified plaintiff “to discontinue any further work * * * for the reason that you have unreasonably delayed the completion of this job.” (Plaintiff’s exhibit 8.) Plaintiff did no further work, and defendant hired another contractor, E. L. Klavans Co., to complete the job.

4. By October 19, 1961, plaintiff had substantially completed its obligations under the contract. (Tr. 21-28; 127-155.) Delays in completing the demolition and preparation of partitions were caused primarily by delay in receiving final notification of the exact requirements of the incoming tenant, the General Services Administration. (Tr. 29; 51; 118-119; 167; 274-275; 380-381; plaintiff’s exhibit 9). Much of the work, such as plastering ceilings and painting, depended upon the final placing of these office partitions. (Tr. 118-119; 126; 167). Defendant therefore breached the contract on October 19, 1961, by dismissing plaintiff from the job. Plaintiff is entitled to all losses sustained as a result of this breach by defendant, less any damage to defendant for improper or negligent workmanship.

5. Plaintiff has proven by a fair preponderance of the evidence that it ex[207]*207pended $11,964.12 for labor. (Tr. 77; 79-80; defendant’s exhibit 2.)

6. Plaintiff has proven by a fair preponderance of the evidence that it expended $4,945.70 for materials. (Tr. 78; 80-81; defendant’s exhibit 4.) This figure includes the full cost of the fire doors installed, which is the only item disputed by defendant in its memorandum. It is true that the contract of June 2 called for “Class C” doors instead of the “Class B” doors that were installed. But defendant’s own witness testified that “the difference is nonexistent between a Class C and Class B door.” (Tr. 201.) Defendant failed to establish what, if any, difference in price existed between the two types of doors. (Tr. 201; 264-265.) The argument that any replacement of the fire doors was unnecessary under the District of Columbia Code (Tr. 198-201) is irrelevant in view of the requirement of the June 2 contract that they be provided by plaintiff. The total of $4,945.-70 includes $425.54 for plans and permits (including all charges for “prints”). (Defendant’s exhibit 4.) If the amount expended on plans and permits is subtracted (for purposes of computing profit, see paragraph 9 below), $4,520.16 remains in the category of materials.

7. Plaintiff has proven by a fair preponderance of the evidence that it expended a total of $25,829.91 for subcontracts. (Tr. 78-79; defendant’s exhibit 3; plaintiff’s exhibits 2, 7, 14, 15, 16, 18a and b, 21a and b, 22, 23.) Plaintiff submitted to defendant all of its subcontracts and cancelled checks in payment thereof. (Tr. 79-84.) This figure includes payment for all of the subcontracts listed in defendant’s exhibit 3 except item (a) below, and specifically includes items (b), (c), and (d) below. These latter three items are the subcontracts which defendant disputes in its memorandum, except for item (a) below and except for the subcontract dealing with air-conditioners, which will be treated separately in paragraph 11 below.

(a) Plaintiff concedes (Tr. 137-139) that the claim of William R. Lone for “supervision” (in the amount of $1,171.10) “could” be a duplication of the charge (in the amount of $562.50) which was paid to Lone on an hourly basis as “superintendent” and which is included in the amount spent for labor (defendant’s exhibit 2.) In this state of the evidence, the Court concludes that plaintiff has failed to prove by a fair preponderance of the evidence that it owes Lone the additional $1,171.10, and the Court will disallow this amount in its entirety. Plaintiff does not claim that it is entitled to the $1,200 for “supervision” set forth in the contract of June 2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
232 F. Supp. 204, 1964 U.S. Dist. LEXIS 6522, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smither-co-v-calvin-humphrey-corp-dcd-1964.