Smith v. Wilson

1958 OK 31, 325 P.2d 421, 1958 Okla. LEXIS 389
CourtSupreme Court of Oklahoma
DecidedFebruary 4, 1958
Docket37209
StatusPublished
Cited by3 cases

This text of 1958 OK 31 (Smith v. Wilson) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Wilson, 1958 OK 31, 325 P.2d 421, 1958 Okla. LEXIS 389 (Okla. 1958).

Opinion

CORN, Vice Chief Justice.

On January 11, 1954, plaintiff suffered accidental personal injuries of a serious and permanent nature. The accident occurred when an automobile in which she was riding, operated by her husband, skidded, rolled down an earthen fill and pinned plaintiff underneath the vehicle. The fill had been built to permit vehicular traffic on Highway 270 to cross the intersection of the road with a new road being constructed as a highway improvement project. The factual background of this appeal may he delineated in the following manner.

During 1953 the State Highway Department was improving Highway 270 in Lati-mer County, Oklahoma. The project involved raising the road level in certain places, relocation or straightening of the existing road, installation of new bridges and laying of rock bed, asphalt surface over the entire area. The improvements covered two contiguous sections, one within the city of Wilburton, the other approximately 41/2 miles in an easterly direction. About 2.2 miles east of the city limits the old road curved in a northerly direction and intersected the new road, which was of greater elevation, in a south-west direction. To accommodate traffic on the old road it was necessary to construct a fill about 10 feet high leading up to the new roadbed. After crossing the intersection a dirt fill approximately 18 feet high led down to the old highway. Completion of the improvements was to be accomplished by different contractors, who undertook performance of separate phases of the construction under contracts with the State Highway Department.

On July 16, 1953, the State Highway Department, hereinafter referred to as the Department, contracted with defendant for the paving of 0.465 miles of highway within the city limits of Wilburton, under a contract designated SAP-1005(4), and also for paving of 4.484 miles of road east of the city under contract SAP-1005 (5). These contracts, identical except for consideration expressed, in part provided:

“ * * * furnish all tools, equipment, materials, and labor, and * * * build and complete Oklahoma State Aid Project No. SAP-1005(4) and SAP-1005 (5) surfacing * * * in accordance with the Oklahoma plans on file with the Department of Highways at *423 Oklahoma City, Oklahoma * * * and with the Oklahoma Standard Specifications for Highway Construction * * * made a part hereof as fully as though copied in full herein *

The Contracts also provided for defendant

“ * * * to begin work on the date designated by the Engineer, and to complete work within One Hundred * * * working days thereafter * * * »

Time was made the essence of the contracts, and failure to complete thereunder entailed payment of $20.00 per day as liquidated damages for delay in completion of the contracts.

The Oklahoma Standard Specifications for Highway Construction, which were made a part of these contracts by reference, in part provide:

“Barricades and Warning Signs. The contractor shall, before closing or in any way tearing up an existing road, furnish and erect approved barricades to protect the traveling public and the work. The barricades shall be placed across the road at such locations that they may be seen for at least three hundred (300) feet. They shall be painted white or whitewash shall be renewed as often as necessary to keep the barricades thoroughly covered.
“From sunset to sunrise the Contractor shall furnish and maintain at least one light at each barricade.
“The Contractor shall also furnish and maintain one red light as a warn'ing sign to be furnished and placed a prescribed distance ahead of each barricade.”

And, a further provision of the Specifications, and which is a part of all Department contracts, placed a seasonal limitation upon laying asphalt paving within the period from October 31st to May 1st.

In October, 1953, and while the grading contractor was engaged in performance, it was ascertained that a water line within the Wilburton city .limits would have to be lowered to enable the grading contractor to install a concrete drain above the water line. After consultation with the Department’s resident engineer it was agreed that lowering the waterline was within defendant’s contract, and defendant’s superintendent made plans to do this work, although defendant had not contemplated performance of any work under the contracts at that time.

Before work could be commenced under any contract an authorization, commonly referred to as a work order, had to be issued by the Department. ‘ On October 22, 1953 the Department’s Construction Engineer addressed a letter to defendant which stated, in part:

“You are hereby authorized to commence construction not later than November 5, 1953 for the improvement of State Aid Project SAP-1005(4) Surf. Consisting of 0.465 Mi. Stab. Aggr. Base and Bid. Rock Asph. Crse. in Wilburton.”

This letter also mentioned conditions under which such authorization was issued, including the contract requirement that the work be completed within 100 days, and advised defendant the project was under the direct supervision of the resident engineer. An identical letter relating to the 4.-484 miles of road extending east of Wilbur-ton, covered by contract SAP-1005 (5) was sent defendant at the same time. On the same date the following letter, a copy of which was sent defendant, was written to the resident engineer.

“Mr. T. R. Livesay October 22, 1953 Mr. Jno J. Stobaugh, Jr. SAP-1005(4) and (5), surfacing Latimer County
“The work order on the above captioned project is being issued this date in order that the utilities in the vicinity of Wilburton can be moved to their permanent locations and the Grading Contractor can complete his work.
“Upon completion of this work in the vicinity of Wilburton, you will
*424 suspend all operations until completion
of the Grading Contract.
“/s/ Jno J. Stobaugh, Jr.
Construction Engineer.”

Defendant commenced work on November 5th and completed moving of the water line on November 16th. The resident engineer's diary, or work report, disclosed completion of the work on November 16th, and a notation “Time suspended, due to seasonal conditions within the contract.” Upon completion of this job defendant was released, moved out all equipment, and thereafter did not return to either of the areas under contract until after the date of the accident. The work on the water lines was done to accommodate the grading contractor, who was enabled to complete the grading, secure final inspection and be released from further responsibility on November 29, 1953. Defendant never entered upon the area east of Wilburton, where the accident occurred until March, 1954. After the grading contractor was released from responsibility the Department maintained the old highway and the crossings and erected signs and barricades until March, 1954.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Price v. United States
530 F. Supp. 1010 (S.D. Mississippi, 1981)
Transcon Lines Corporation v. CORNELL CONST. COMPANY
1975 OK 85 (Supreme Court of Oklahoma, 1975)
Ferguson v. Ben M. Hogan Company
307 F. Supp. 658 (W.D. Arkansas, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
1958 OK 31, 325 P.2d 421, 1958 Okla. LEXIS 389, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-wilson-okla-1958.