Mr. Justice Wolverton,

after stating the facts, delivered the opinion of the court.

1. Two questions are presented by the record: First, whether the mechanics’ liens, or any of them, should have priority over the mortgages upon the land upon which the hotel building is constructed; and, second, whether the defendant Beach should be required to prorate his demand with the other mechanics’ lien claimants. The appellant maintains the affirmative of the first and the negative of the latter proposition. It has become settled law in this state that a mechanic’s lien for materials used in the construction of a building upon land previously mortgaged will take precedence of the mortgage as to the building: Cooper Mfg. Co. v. Delahunt, 36 Or. 402 (51 Pac. 649). The appellant insists, however, that the mortgages in question were taken subsequent to the commencement of the hotel building, with notice thereof to the holders of the legal title, and are postponed to his mechanic’s lien. This is a question of fact to be determined from the evidence.

2. The defendant Wilkins, the mortgagor in both mortgages, acquired his deed from Mrs. Gerhard to the north half of lot 8, block 5, October 15, 1891, and the one from Phile to the north half of lot 7, December 9 following. The mortgage was given at the time he acquired title to the property. He testifies that Mrs. Gerhard gave him a contract to convey some ten days or two weeks before he obtained the deed; that he paid her $200 down, and informed her at the time of obtaining the contract that he intended to construct the building upon the lot; that subsequently, to- wit, on October 5, he had a quantity of lumber delivered in the vicinity with the intention and purpose of constructing the same. As it respects the Phile purchase, he states that he had been talking to him for some time previous to the acquirement of the deed about building a hotel, that Phile was aware of his intention [586]*586to build, and that they arrived at a verbal understanding about a week before the deed was made. Among other things, he says: “I told him (Phile) that I didn’t want to sell that piece of property that I owned across the street, unless I could purchase the half lot of his to complete my plans for the hotel.” There was evidence tending to show that neither Gerhard nor Phile posted any notices on the premises warning persons that they would not stand responsible for any expenditure of labor or materials employed or used in the structure.

Mr. Wilkins is not borne out in detail by the subsequent proofs. Mrs. Gerhard and her son both testify that there was no agreement entered into between her and him for the sale of the lot, except on the day before the deed was executed ; that the $200 was paid at that time, and the deed and mortgage executed the next day; that he approached her some two weeks prior thereto regarding a purchase of the lots in the interest of some Portland party, and spoke of the likelihood of a hotel being constructed thereon, if she would sell, but that no terms were agreed upon until the day before the date of the deed. Phile says that there was some talk of constructing the hotel prior to1 the time he conveyed, but that he came to no agreement with Wilkins touching the lot until about the time the deed was executed. It is shown by other testimony that 6,169 feet of lumber was deposited in the alley back of the east half of lot 8, which adjoins the Phile lot then owned by Wilkins; that the lumber was delivered under an arrangement with Wilkins to furnish it for the construction of a store building on his lot; that some time prior to the thirteenth of 'November Wilkins changed his plans and made arrangements for the delivery of other lumber suitable for the hotel building, and on the thirteenth another consignment was delivered, perhaps in the street opposite the Wilkins lot, or it may have been opposite the Phile lot. Two other consignments were delivered prior to De[587]*587cember g, — one on November 20, and one on December 3. These were unloaded in the street opposite the lot upon which the hotel was subsequently constructed. Considered .in its entirety, the evidence proves quite conclusively that, when the first consignment of lumber was delivered, Wilkins had no intention of building a hotel, and that it was not delivered for that purpose. Just when the change in his plans was determined upon by him is not apparent. Certainly not before the purchase from Mrs. Gerhard, and very likely not until shortly prior to November 13. Even at this date he had no intention of extending the building upon the Phile lot, as he had then entered into no arrangement for it of any kind. Whatever ideas he may have had for making such extension were merely speculative, and by no means settled or determined upon. In any event, whether it pertains to the Gerhard or Phile lot, Wilkins certainly had no intention of building upon either until he should acquire legal title,— that is, he did not purpose trespassing upon or invading the property of others, and without their consent erect the building thereon, — and it is undoubtedly true that he did not have such consent while these individuals held the title. There was no time between the execution of the deeds and mortgages when it could be said that he was engaged in the construction of the building; those instruments having been executed concurrently, so that there was no occasion at any time which required these mortgagees to post notices to protect any interest that they may have had against incumbrances thereon by reason of the construction of the hotel, and hence whatever liens may have been acquired against the building could not extend to the lots in preference to the mortgages: Mo. Val. Lumber Co. v. Reid, 4 Kan. App. 4 (45 Pac. 722).

3. The second question must be determined by the effect of the former appeal and the decree of this court with reference thereto. It is insisted that, as the other mechanics’ lien [588]*588claimants did not appear in this court, the reversal did not affect their status, and that the decree of the lower court, whereby it was determined that the mortgagé liens were superior to the mechanics’ liens on the building, must yet be considered as standing intact as to them, but reversed as to the defendant Beach. The contention is based somewhat upon the decree entered .in this court, which remands the cause, “with permission to the appellant (Beach) to apply for leave to amend his answer so as to present the real issues in the case for a trial on the merits so' far as his interests are involved.” Stress is placed upon the latter clause. The trial had been concluded, so far as it pertained to. the rights of the other lien claimants, and their priorities fixed and established, while Beach was not permitted to establish his status, because it was thought he was not in a position to establish his demand, owing to the state of the pleadings. No one appeared in this court to dispute Beach’s appeal except Gerhard and Phile, although all lien claimants were served with notice thereof. It will be borne in mind that the mechanics’ lien claimants other than Beach were postponed by the original decree of the lower court to the lien of the mortgages, both as it respects the land and the building. By their omission to prosecute their suit here for better conditions, we are obliged to assume that they were satisfied with the decree as it then stood, and this left the controversy to proceed as between the mortgage lien claimants and Beach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roach's Estate
92 P. 118 (Oregon Supreme Court, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
64 P. 760, 38 Or. 583, 1901 Ore. LEXIS 36, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-wilkins-or-1901.