Smith v. Vail

65 N.Y.S. 834, 53 A.D. 628
Appellate Division of the Supreme Court of the State of New York·Decided July 17, 1900·Published·Cited by 2 cases

Opinion

O’BRIEN, J.

The suit was brought to enforce a mechanic’s lien for $8,285.06, a balance claimed to be due for work performed by plaintiff on defendant’s premises 773 Broadway, between May 10 and December 12, 1898, under a contract entered into between the parties in April, 1898. By the contract the plaintiff agreed “to furnish all the material, and do * * all the mason work, carpentry, iron work, and electric work required in the erection, completion, and finishing” of defendant’s building, in a good and workmanlike manner, in accordance with the specifications, to be' wholly and fully completed and finished by the 1st of August, 1898, in consideration of $27,630, of which $10,000 was to be paid when the roof was on, $10,000 when floors were laid and rough plastering finished, and $7,630 when the contract was entirely completed. The contract also provided that the architects were to be sole arbiters; that time was “of essence”; and that unless failure on the part of the plaintiff to complete by August 1, 1898, “shall result from the act of God or the public enemy,” the plaintiff should forfeit the sum of $50 a day as liquidated damages for failure to complete the building within the time specified. The plaintiff alleges in his complaint that he “duly fulfilled and performed all the conditions of said contract on his part to be performed within the time therein specified except wherein he was delayed by changes ordered by the architect and by other contractors for whom he was obliged to wait, and over whom he had no control, their work not being included in his contract; that he was entitled to receive, in addition to the contract price, $655.06 for extra work performed by him, and that but $20,000 had been paid him, leaving $8,285.06, the amount of Ms lien, which sum he has demanded, but has not been paid, although on January 9, 1899, the architect gave him a certificate stating that he was “entitled to the final payment * * * in accordance with the terms of the contract, and in addition the sum of five hundred and seventy-one and 68/ioo dollars ($571.63) for extra materials furnished and labor performed.” The answer, though admitting that the building was finally completed in accordance with specifications, and stating that the sum of $571.63 was agreed upon for extra work, and that the time to complete the work was verbally extended from August 1st to August 15th, alleges that the building was not completed till December 12th, and that such delay was not due to the act of God or the public enemy, but to the plaintiff, so that the defendant is entitled to a counterclaim against the plaintiff under the contract of $50 a day for the delay, or $5,950; and also a further sum of $4,500, [836] which was incurred by the defendant in procuring other premises between August 15th and December 12th. The plaintiff’s reply asserts that no part of the delay was justly attributable to him.

There was, of course, no merit in the second counterclaim, as the parties had already stipulated for liquidated damages, if any. As to the first counterclaim, and the question of the plaintiff’s right to recover, there were presented questions of fact which were resolved by the special term in plaintiff’s favor, and it is necessary, in stating our conclusions on this appeal, to review briefly the evidence. ■

Free access — add to your briefcase to read the full text and ask questions with AI

Smith v. Vail, 65 N.Y.S. 834, 53 A.D. 628 (N.Y. Ct. App. 1900).

65 N.Y.S. 834 (Smith v. Vail) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mason Tire & Rubber Co. v. Cummins-Blair Co.
157 N.E. 367 (Ohio Supreme Court, 1927)
Reading Hardware Co. v. City of New York
129 A.D. 292 (Appellate Division of the Supreme Court of New York, 1908)