Smith v. Vail

65 N.Y.S. 834, 53 A.D. 628
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJuly 17, 1900
StatusPublished
Cited by2 cases

This text of 65 N.Y.S. 834 (Smith v. Vail) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Vail, 65 N.Y.S. 834, 53 A.D. 628 (N.Y. Ct. App. 1900).

Opinion

O’BRIEN, J.

The suit was brought to enforce a mechanic’s lien for $8,285.06, a balance claimed to be due for work performed by plaintiff on defendant’s premises 773 Broadway, between May 10 and December 12, 1898, under a contract entered into between the parties in April, 1898. By the contract the plaintiff agreed “to furnish all the material, and do * * all the mason work, carpentry, iron work, and electric work required in the erection, completion, and finishing” of defendant’s building, in a good and workmanlike manner, in accordance with the specifications, to be' wholly and fully completed and finished by the 1st of August, 1898, in consideration of $27,630, of which $10,000 was to be paid when the roof was on, $10,000 when floors were laid and rough plastering finished, and $7,630 when the contract was entirely completed. The contract also provided that the architects were to be sole arbiters; that time was “of essence”; and that unless failure on the part of the plaintiff to complete by August 1, 1898, “shall result from the act of God or the public enemy,” the plaintiff should forfeit the sum of $50 a day as liquidated damages for failure to complete the building within the time specified. The plaintiff alleges in his complaint that he “duly fulfilled and performed all the conditions of said contract on his part to be performed within the time therein specified except wherein he was delayed by changes ordered by the architect and by other contractors for whom he was obliged to wait, and over whom he had no control, their work not being included in his contract; that he was entitled to receive, in addition to the contract price, $655.06 for extra work performed by him, and that but $20,000 had been paid him, leaving $8,285.06, the amount of Ms lien, which sum he has demanded, but has not been paid, although on January 9, 1899, the architect gave him a certificate stating that he was “entitled to the final payment * * * in accordance with the terms of the contract, and in addition the sum of five hundred and seventy-one and 68/ioo dollars ($571.63) for extra materials furnished and labor performed.” The answer, though admitting that the building was finally completed in accordance with specifications, and stating that the sum of $571.63 was agreed upon for extra work, and that the time to complete the work was verbally extended from August 1st to August 15th, alleges that the building was not completed till December 12th, and that such delay was not due to the act of God or the public enemy, but to the plaintiff, so that the defendant is entitled to a counterclaim against the plaintiff under the contract of $50 a day for the delay, or $5,950; and also a further sum of $4,500, [836]*836which was incurred by the defendant in procuring other premises between August 15th and December 12th. The plaintiff’s reply asserts that no part of the delay was justly attributable to him.

There was, of course, no merit in the second counterclaim, as the parties had already stipulated for liquidated damages, if any. As to the first counterclaim, and the question of the plaintiff’s right to recover, there were presented questions of fact which were resolved by the special term in plaintiff’s favor, and it is necessary, in stating our conclusions on this appeal, to review briefly the evidence. ■

The plaintiff testified that in the prosecution of the work he had contracted to do there was a delay soon after the work began on account of a beam in a party wall over which there was a dispute with the adjoining owner, which lasted for more than a month, and the architect directed him not to take down the wall or beam; that he was again delayed three or four days by not receiving the boiler flues from the steam-heating company employed by the defendant; that there was at least two days’ delay because the plumbers, over whom he had no control, did not make connection with the sewer in Broadway; that the boilers occasioned a delay of nearly a month, as they came two weeks late, and then were left in the way before being set, until which time the mason work could not be done; that the architect ordered cornices different from those contemplated, and the details of carpenter work were not received in time; that other new work as to metal ceilings was decided upon, which hindered him; that on July 2d he wrote the architects that “all the sidewalk and store-entrance work * * * is delayed because the engines have not been delivered. These engines must be lowered to the basement at the area, which is covered with patent lights. The patent lights are now fitted in place, but cannot be set, because that would shut out the engines. The patent lights not being set prevents laying the sidewalk, and also finishing up the doorway. Can you not hurry the engines to the building at once?” The plaintiff further said: That, when the engines finally arrived, the men broke the patent-light frame by rolling the engines over it. That changes were made in the elevator doors, and the elevator men punched out the plastering. That time was lost because the hardware did not arrive promptly, and because the architects interfered with his men, so that he wrote them on August 26th: “I have left nothing undone * * * to hurry the completion of the building. But my efforts are in many instances made useless by having the subcontractors countermanded by yourself. O’Connor wishes all the hardware furniture delivered at once to him at the building.” That the Electric Equipment Company retarded him, because they were awaiting defendant’s instructions as to a switchboard. That he had as many men at work every day as he could usefully employ. The plaintiff’s testimony was corroborated by that of his associate, Mr. Atkins, who made the estimate on the plans; by Mr. Garrigan, his bricklayer and foreman mason; by the carpenter, Mr. O’Connor, who said the hardware did not come till August 31st, and his work was dependent upon receiving it; by Mr. Patterson, whom he employed as a superintendent; and also by the letters which áre in evidence, sent to [837]*837the architects by the plaintiff, requesting them to hurry along the other work, so that his own might proceed. In behalf of the defendant, Mr. Mowbray, the architect, testified that he was on the premises nearly every day; that there was a dispute as to the party wall, but he did not think that delayed the work; that the masonry could not be "done till the boilers were set, which took about two weeks, but that this did not materially impede the progress of the plaintiff, who, as soon as possible, began his work; that, as to the flue pipes, there might have been one or two days’ delay by the steam-fitting company, and that by putting the pipes in the cellar there was some portion of the carpenters’ work as well as the plasterers’ work kept back; that, as soon as the contract was given, Mr. O’Connor came to him for details, and others were furnished later, but practically all by the middle of July; that he did give Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mason Tire & Rubber Co. v. Cummins-Blair Co.
157 N.E. 367 (Ohio Supreme Court, 1927)
Reading Hardware Co. v. City of New York
129 A.D. 292 (Appellate Division of the Supreme Court of New York, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
65 N.Y.S. 834, 53 A.D. 628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-vail-nyappdiv-1900.