Smith v. Tampa Electric Co.

46 Fla. Supp. 185
CourtCircuit Court of the 13th Judicial Circuit of Florida, Hillsborough County
DecidedDecember 8, 1977
DocketNo. 75-468
StatusPublished

This text of 46 Fla. Supp. 185 (Smith v. Tampa Electric Co.) is published on Counsel Stack Legal Research, covering Circuit Court of the 13th Judicial Circuit of Florida, Hillsborough County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Tampa Electric Co., 46 Fla. Supp. 185 (Fla. Super. Ct. 1977).

Opinion

ROBERT W. PATTON, Circuit Judge.

This cause came on to be heard before the court on June 30th, 1977 upon the following motions filed by the defendants Tampa Electric Company and Globe Indemnity Company — motion for new trial, motion for judgment notwithstanding verdict and motion for remittitur. There were present at the hearing Timothy F. Prugh, Esq., of Shackleford, Farrior, Stallings & Evans, attorneys for the defendants, and I. W. Williams, Esq., and Morris Milton, Esq., attorneys for the plaintiffs, John A. Smith and Mary Smith, his wife.

The court has considered the motions and the arguments of counsel with respect thereto and also the memorandums which they have filed in the cause subsequent to the hearing at the request of the court.

This was an action for personal injuries suffered by the co-plaintiff John A. Smith (hereafter referred to as “the plaintiff” or “Smith”) while he was employed by Cone Brothers Contracting Company, which was a subcontractor on a highway construction project in Hillsborough County. Mary Smith, the other plaintiff in the action, claimed derivative damages as the result of the injuries to her husband, John A. Smith. The injuries suffered by Smith resulted from an electrical charge passing through a mobile crane, or some part thereof, which was being operated by another employee of Cone Brothers Contracting Company at the time. There was sufficient evidence, in the opinion of this court, from which the jury in this case could determine that the electrical charge above mentioned came from uninsulated power lines of the defendant Tampa Electric Company located in the immediate vicinity of the crane. The evidence further reveals that approximately 7,600 volt current was being transmitted over the power lines at the time of the accident.

The power lines in question were of a temporary nature and had been erected by Tampa Electric Company over an area in which that company knew, or had reason to know, that construction work on a bridge immediately adjacent to the power line was either then taking place or about to take place. It is the opinion of the court that there was ample evidence from which the jury could determine that Tampa Electric Company knew, or had reason to know, that construction equipment such as cranes would be in use in the area adjacent to the power line.

[187]*187The accident happened in an area lying between the bridge on the east and a temporary road on the west. The land between the road and bridge was approximately 90 feet wide. The bridge and the temporary road both ran in a generally north and south direction. The power line also ran along the east side of the road and in the same general direction.

On the morning of the accident a mobile crane had been brought onto the strip of land between the temporary road and the bridge under construction. Previous to that time Cone Brothers Conracting Company had caused a number of bundles of steel to be placed on the aforesaid strip of land, same having been located either underneath the east edge of the electric line or very close thereto. The purpose of bringing the crane into that location on the morning in question was so that it would be used to move the bundles of steel from the positions in which they were then located a distance of some 20 to 25 feet to the east. The steel was to be used in the construction of the bridge.

On the morning in question the plaintiff, whose usual job was cement finishing, was directed by his foreman to select a fellow employee in order that the two of them could work in conjunction with the crane operator, also an employee of Cone Brothers Contracting Company, in moving the bundles of steel. The first task to which the plaintiff was assigned was to assist the crane operator in moving the crane to a position from which it could be used to move the steel. The crane was a self-propelled vehicle having two separate cabs. One of the cabs was used for the purpose of driving the vehicular part of the crane, and it was into this cab that the plaintiff was directed to go in order to drive said vehicle to the proper position. The plaintiff did so drive said vehicle under the direction of the crane operator to the location which the latter had selected for the crane to be placed for the purpose of moving the steel. There was testimony that after the crane had been so placed the boom thereof was 4 to 7 feet east of the electric line.

The crane had a boom 35 to 45 feet or more in length and the boom could be moved both from side to side and up and down. There was evidence that the top of the boom was higher than the electric wires. The crane was operated from the cab above mentioned and the operator testified that in moving the boom from side to side he was able to lock same when he stopped this operation, thus rendering it impossible to move the boom until such brake was released.

As part of his duties on the morning in question, the plaintiff was assigned the responsibility of signalling the crane operator when the boom of the crane should be stopped as it was moved [188]*188toward the west for the purpose of picking up a load of steel. This was done by means of hand signals, and Smith and the crane operator had agreed on a point where the boom was 4 to 6 feet distant from the closest wire as the place to stop the westward movement of the boom.

It was completely clear from the evidence that all three members of the crane operation, including the plaintiff, had been warned of the presence of the electric wires before they commenced the movement of the steel, and that they had also been warned of the fact that the electric lines carried a high voltage of electricity and were very dangerous. They had also been told not to cause the boom of the crane to be moved closer than six feet from the electric wires.

It was under these circumstances that this crew of three men commenced the movement of the steel. A steel cable ran up over the top end of the boom and down to a steel object characterized in the evidence as a “headache ball” or a “mammy headache ball.” Two cables were attached to the lower part of this “headache ball” and extended downward so that they could be attached to the bundles of steel by the use of shackles and bolts at the ends of the cables. The plaintiff and his co-worker had the responsibility of fastening these shackles to the steel, one cable being fastened to each end. After the steel was so fastened, the crane operator would tighten the cable, thus causing the steel to be lifted from the ground. Then by turning the boom of the crane, the operator would move the steel to the east and place it on the ground where the plaintiff and his co-worker would unfasten the shackles. After this was done the operator would cause the boom of the crane to swing back to the west and when it reached the designated position the plaintiff would give the operator a hand signal to stop.

The crane operator testified that he was not entirely dependent upon the hand signals from the plaintiff to stop moving the boom when the designated position at the west end of the turn was reached, but that he could also fix this position by sighting objects in the area.

On the morning in question four or five bundles of steel were moved from the original location to the new position without mishap. On the last of these successful moves, after the steel was placed on the ground in the new location, the crane operator moved the boom back to the west and stopped it on a hand signal from the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ahearn v. Florida Power and Light Company
129 So. 2d 457 (District Court of Appeal of Florida, 1961)
C. W. Zaring & Co. v. Dennis
19 So. 2d 701 (Supreme Court of Florida, 1944)
Schwartz v. Priest
14 So. 2d 845 (Supreme Court of Florida, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
46 Fla. Supp. 185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-tampa-electric-co-flacirct13hil-1977.