Smith v. Molleson

26 N.Y.S. 653, 81 N.Y. Sup. Ct. 606, 57 N.Y. St. Rep. 250, 74 Hun 606
CourtNew York Supreme Court
DecidedDecember 15, 1893
StatusPublished

This text of 26 N.Y.S. 653 (Smith v. Molleson) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Molleson, 26 N.Y.S. 653, 81 N.Y. Sup. Ct. 606, 57 N.Y. St. Rep. 250, 74 Hun 606 (N.Y. Super. Ct. 1893).

Opinion

PARKER, J.

In October 1888, the plaintiff entered into a contract with the city of New York to enlarge the American Museum of Natural History, in Manhattan square. The contract provided that certain portions of the building exposed to view on the exterior should be faced with granite. Shortly thereafter, plaintiff made a contract with Pratt & Molleson to furnish, cut, set, and clean all the new granite work which plaintiff had contracted to furnish. Pratt & Molleson gave to plaintiff a bond in the penal sum of $6,000, conditioned that they would faithfully perform their contract. This they did not do. Hence this action against their surety, who assigns two grounds of defense: (1) That the bond is without consideration to support it; (2) that the plaintiff and Pratt & Molleson varied the terms of the contract.

Touching the question of the want of consideration, it appears that before the contract was made between the plaintiff and Pratt & Molleson it was agreed that, if the contract should be awarded to the latter, security for faithful performance on their part should be furnished by them. Plaintiff so testifies, and the senior member of the firm, who were the principals in the bond, conceded it. In accordance with their promise, the making of which was a condition precedent to the awarding of the contract, they presented to the plaintiff the bond in suit, which recited the making of the contract between Smith and Pratt & Molleson, and briefly described the work which Pratt & Molleson had therein covenanted to perform, and the compensation to be paid therefor; and it was conditioned that Pratt & Molleson should faithfully perform their contract, or that they should pay such sum of money as the other party to the contract should suffer by reason of a failure of performance, not exceeding $6,000. It is apparent that the parties to the contract, as well as the surety on the bond, understood that the giving of the bond was requisite in order to secure to Pratt & Molleson the contract, and that the purpose of it was to secure Smith against loss in case of a failure of performance. The letting of the contract to Pratt & Molleson on condition that they should furnish security for their faithful performance of the contract furnished a good consideration to sustain the bond given. This proposition is sufficiently supported in the reasoning of the court in Bank v. Coit, 104 N. Y. 532-536,11 N. E. 54.

The second defense is sought to be founded on that principle of the law of suretyship which gives to a substantial variation of a contract by the parties to it, without the consent of the surety, the effect of' releasing him. The contract provided that Smith should pay to Pratt & Molleson, for the work which they covenanted to perform, the sum of $30,000, “as follows: In monthly payments not to exceed eighty per cent, of the estimated value of the work performed on the building; the final payment to be made when this work is all complete, and after the expiration of thirty days, and after all [655]*655the drawings and specifications have been returned to J. 0. Cady-and Company, architects.” The variation oí which defendant mainly complains is that the plaintiff paid to Pratt & Molleson, from time to time, sums of money which aggregated more than 80 per cent, of the estimated value of the work actually performed on the building, so that, at the time when the plaintiff took the contract away from Pratt & Molleson because of their failure to perform its conditions, there had been paid to them a greater sum than was due for work and material actually in the bufiding. It is undisputed that Pratt & Molleson were not possessed of funds requisite to the carrying out of the contract in accordance with its provisions, and from the inception of the work, almost, the plaintiff from time to time made to them moderate advancements on account of the work which they had actually performed, with the purpose in view of enabling them, if possible, to fulfill their agreement. The advancements thus made never at any time exceeded 80 per cent, of the value of the stone on hand, and the work done thereon. Briefly stated, if the contract only authorized payments not to exceed 80 per cent, of the materials furnished and work done on such stone as was actually set in the building, plaintiff made an overpayment, but if it authorized a payment of 80 per cent, of the work actually performed, whether on stone set in the building, or those not set, but wholly or partially ready for setting, then the payments were not in excess. In construing this provision of the contract it should be borne in mind that while it was intended to secure to the contractors a portion of the contract price, from time to time, as the work proceeded, it was also intended as a protection to the plaintiff against the payment of so large a sum as to leave the amount remaining unpaid insufficient to insure performance on the part of the contractors. Thus the monthly payments were limited to a sum not exceeding 80 per cent, of the estimated value of the work performed. How, the granite which the contractors were to furnish had to be taken out of the quarries in Hova Scotia, thence conveyed to Hiantic, Conn., where it was cut and put in readiness to be set in the building, and then taken to Hew York, and placed in position, as the work progressed, necessarily, therefore, the larger part of the expense of the contractors in performing their work was incurred before the stone were set in the building. The fact that a provision for monthly payments to be based on estimates furnished shows that the parties to the contract appreciated that it was necessary for the contractors that payments should be made at short intervals to enable them to go on with the work. Having this purpose in view, it was but reasonable, and apparently in furtherance Of their general object, to authorize payments based on work actually performed, including stone wholly or partially ready for setting, as well as those set. This is the construction of the contract which the parties themselves, by their conduct, gave to it before any of the stone were set. After the stone had been taken from the quarries in Hova Scotia to Hiantic and cut, the contractors applied for a payment on account, and the plaintiff, accompanied by one of the architects superintending the construction of the building, visited the yard at Hiantic where the stone were [656]*656being dressed; examined them, made an estimate of their value, and on that basis an advancement to the contractors of a sum less than 80 per cent, of their estimated value was made. Defendant contends that the construction thus placed upon it by the parties, and which seems to be the one intended by them, cannot prevail, because the language employed is that monthly payments are “not to exceed eighty per cent, of the estimated value of the work performed on the building;” that th'e meaning of the phrase is that estimates shall be based solely on stone actually set; that work done in preparing them for setting, and in delivering them on the ground, is not work “performed on the building.” This construction, in the light of the circumstances surrounding the making of the contract, and the conduct of the parties thereunder, seems to us too narrow. Webster, in defining “on,” gives, as one of its meanings, “In reference or relative to.” Adopting this meaning, and the provision so reads as to authorize an 80 per cent, payment based on the estimated value of the work performed in reference or relative to the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie County Savings Bank v. . Coit
11 N.E. 54 (New York Court of Appeals, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
26 N.Y.S. 653, 81 N.Y. Sup. Ct. 606, 57 N.Y. St. Rep. 250, 74 Hun 606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-molleson-nysupct-1893.