Smith v. Gray

147 N.E. 459, 316 Ill. 488
CourtIllinois Supreme Court
DecidedApril 24, 1925
DocketNo. 15991. Reversed and remanded.
StatusPublished
Cited by18 cases

This text of 147 N.E. 459 (Smith v. Gray) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Gray, 147 N.E. 459, 316 Ill. 488 (Ill. 1925).

Opinion

Mr. Chipf Justice Duncan

delivered the opinion of the court:

E. P. Smith, trading as the F. P. Smith Wire and Iron Works, obtained a judgment in the municipal court of Chicago against William H. Gray for $3911.01 for labor and materials furnished under a written contract, including extras. The judgment was affirmed by the Appellate Court on appeal, and this court awarded a writ of certiorari to review the judgment.

The contract sued on in this case is in two parts, in the form of letters addressed to Gray, plaintiff in error, (herein called defendant,) by defendant in error, F. P. Smith, (herein called plaintiff,) and signed by both parties, the first or original contract being dated May 2, 1916, and the second or supplemental contract September 27, 1916. By the original contract plaintiff agreed to furnish materials for, and to change according to requirements shown by the architect’s drawing, the stairs on seven floors of the building known as the Board of Trade Hotel, the stairs from the second to the third floor to be new and the one from the basement to the second floor to be also new and constructed of plate and angle stringers, checkered steel treads and no risers, with pipe hand-rails where necessary. The work on the stairs was to be done on the basis of cost, plus ten per cent, and not to exceed $200 per floor, or a total of $1400 for the seven floors. Plaintiff was also to furnish three new Bally columns for the basement and put in eighteen elevator doors as specified, using present sills but furnishing all new materials for tracks, hangers, locks, etc.; also seven stair hall doors and one door on first floor corridor and one to alley, all made of materials as specified and to be three feet wide and seven high. Plaintiff was to have the option of furnishing pressed steel frames in place of the specified channel iron frames, furnish steel tops for two elevator cabs, four cast-iron thresholds for entrance doors, and include one three-foot stairway fire-escape but no stand-pipe, — all for the sum of $4600, erected. Payment was to be made by defendant on the 10th day of each month for eighty-five per cent of the work erected during the preceding month, from estimates furnished by plaintiff, the amount of each estimate to be mutually agreed on.

The second or supplemental contract, omitting date and signatures, is in this language: “In making the bid for putting in the fire-escape on the northeast corner of the building, it was figured at $1235, which figure Mr. W. H. Gray agrees, in order not to delay the work further, to pay $2000 for, which will make a difference of $765 additional. F. P. Smith agrees to get proper permits from the city for building the same and furnish final inspection from the city.” The work was to begin at once after the signing of the contract but no time was fixed for its completion.

The contention of plaintiff is that he has performed the entire contract covered by the original and supplemental contracts; that he is entitled to recover the $4600 named in the original contract plus the $765 mentioned in the supplemental contract, and in addition thereto $568.81 for ten other items of extras agreed on and furnished from July 1, 1916, to November 23, 1916, making a total of $5933.81, less a cash payment of $2000 made by the defendant July 15, 1916. He also makes a further claim of $704.80 for interest up to July 28, 1920, the date of his affidavit of claim, together with all further interest that may accrue up to the rendering of final judgment.

The defendant filed an affidavit of merits, stating, in substance, that being about to remodel the Board of Trade building he engaged a reputable architect to prepare the necessary plans, drawings and specifications; that it was contemplated to open the hotel for business in July or August, 1916; that the plans, specifications and drawings were prepared and delivered to plaintiff in May, 1916, and contained the provision that the work upon the building was to begin on the date of the contract; that the plans and specifications and contracts included the erection and installation of a suitable three-foot stairway fire-escape upon the outside of the building to meet the approval and pass the inspection of the building department of Chicago; that prior to entering into the contract plaintiff made a careful examination of the plans and specifications and contracts and of the building to which the fire-escape was to be attached; that but for the unreasonable delay of plaintiff in erecting the fire-escape the hotel could and would have been open for business at least two and a half months before it actually was, and that the delay was solely chargeable to plaintiff; that under the conditions then existing among contractors in Chicago, defendant- was unable to secure the work to be done by any other contractors engaged in structural iron work, which plaintiff well knew; that plaintiff sought to compel defendant to pay for the fire-escape the additional sum of $765 named in the supplemental contract for its erection and charged it to defendant in his affidavit of claim as “extra steel for bracing walls;” that the extra steel for such purpose was never furnished and there is no consideration for the supplemental contract; that defendant frequently urged plaintiff to complete the erection of the fire-escape but he unreasonably delayed so doing and the same was not completed until November 27, 1916, to the damage of defendant in the sum of $9409.50, including $900 damage by delay to other work.

Defendant also filed what he calls a plea of set-off, which includes the $9409.50 damages included in his plea of reóoúpment. The former plea also includes a claim of $800 for about a ton and a half of brass removed from the elevator walls and claimed and taken by plaintiff and which defendant insists he was not entitled to under the contract; álso $300 for plaintiff’s share of cost of power and elevator service during construction and remodeling. In this plea of set-off are also included other items of overcharge by plaintiff-' amounting to $1486.95, for which defendant claims he is entitled to credit.

" The work" of repairing and remodeling the -building bn the inside'was begun immediately after the signing of the original'contract by the parties, and there is no claim that this work was not done according to the contract and without delay. ; The only qúéstíon that defendant raises in the argument as to' the''charge íor'-’tM's work 'is; that as against that claim he was entitled to a credit of $40’ for door-stops not properly furnished, and which was practically conceded by plaintiff and apparently allowed by the jury; also, that he was entitled to a set-off for the value of the brass taken away from the building by plaintiff. Defendant further claimed that plaintiff was not entitled to interest.

The principal contention of defendant is that the supplemental contract of September 27, 1916, is void for want of sufficient consideration; that the additional charge of plaintiff of $765 for constructing the fire-escape cannot be recovered by plaintiff for said reason, and that by reason of the unnecessary delay in constructing the fire-escape defendant was greatly damaged and that he should be allowed the sum claimed by his pleas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Superior Structures Co. v. City of Sesser
660 N.E.2d 1362 (Appellate Court of Illinois, 1996)
Jiri Mucha v. Charles King
792 F.2d 602 (Seventh Circuit, 1986)
E. M. Melahn Construction Co. v. Village of Carpentersville
427 N.E.2d 181 (Appellate Court of Illinois, 1981)
Servbest Foods, Inc. v. Emessee Industries, Inc.
403 N.E.2d 1 (Appellate Court of Illinois, 1980)
John Kubinski & Sons, Inc. v. Dockside Development Corp.
339 N.E.2d 529 (Appellate Court of Illinois, 1975)
St. Joseph Hospital v. Corbetta Construction Co.
316 N.E.2d 51 (Appellate Court of Illinois, 1974)
Alco Standard Corp. v. F & B Manufacturing Co.
281 N.E.2d 652 (Illinois Supreme Court, 1972)
Chicago & N. W. R. Co. v. Chicago Packaged Fuel Co.
99 F. Supp. 361 (N.D. Illinois, 1951)
Standard Oil Co. of Indiana v. Daniel Burkhartsmeier Cooperage Co.
77 N.E.2d 526 (Appellate Court of Illinois, 1948)
Hamilton Watch Co. v. George W. Borg Corp.
46 N.E.2d 112 (Appellate Court of Illinois, 1942)
Wall v. Chicago Park District
37 N.E.2d 752 (Illinois Supreme Court, 1941)
Cohn v. Litwin
35 N.E.2d 410 (Appellate Court of Illinois, 1941)
Litwin v. Litwin
30 N.E.2d 619 (Illinois Supreme Court, 1940)
Cherry v. Aetna Casualty & Surety Co.
25 N.E.2d 11 (Illinois Supreme Court, 1939)
Sterling-Midland Coal Co. v. Great Lakes Coal & Coke Co.
266 Ill. App. 46 (Appellate Court of Illinois, 1932)
LeRoy State Bank v. J. Keenan's Bank
261 Ill. App. 441 (Appellate Court of Illinois, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
147 N.E. 459, 316 Ill. 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-gray-ill-1925.