Smith v. D.R. Horton, Inc

Procedural entryThis page is a short order in Smith v. D.R. Horton, Inc. Read the opinion of the Court — 417 S.C. 42
Supreme Court of South Carolina·Decided July 6, 2016·No. 27645·Published

Opinion

THE STATE OF SOUTH CAROLINA

In The Supreme Court

Gregory W. Smith and Stephanie Smith, Respondents,

v.

D.R. Horton, Inc., Tom's Vinyl Siding, LLC, Lutzen

Construction, Inc., Boozer Lumber Company, All

American Roofing, Inc., Myers Landscaping, Inc.,

Defendants,

of whom D.R. Horton, Inc. is the Petitioner.

Appellate Case No. 2013-001345

ON WRIT OF CERTIORARI TO THE COURT OF APPEALS

Appeal From Dorchester County

Edgar W. Dickson, Circuit Court Judge

Opinion No. 27645

Heard March 3, 2015 – Filed July 6, 2016

AFFIRMED

Matthew Kinard Johnson and W. Kyle Dillard, both of Ogletree Deakins Nash Smoak & Stewart, PC, of Greenville, for Petitioner.

Phillip Ward Segui, Jr., of Segui Law Firm, of Mt. Pleasant, John T. Chakeris, of Chakeris Law Firm, and Michael A. Timbes, of Thurmond Kirchner Timbes & Yelverton, PA, both of Charleston, for Respondents.

ACTING JUSTICE TOAL: D.R. Horton, Inc., asks this Court to reverse the court of appeals' decision in Smith v. D.R. Horton, Inc., 403 S.C. 10, 742 S.E.2d 37 (Ct. App. 2013), affirming the circuit court's refusal to compel arbitration between Gregory and Stephanie Smith (collectively, the Smiths) and D.R. Horton. We affirm.

FACTS/PROCEDURAL BACKGROUND D.R. Horton is a corporation specializing in residential construction. In March 2005, the Smiths entered into a home purchase agreement (the Agreement) with D.R. Horton for the design and construction of a new home in Summerville, South Carolina.

The Agreement is organized into numbered paragraphs and lettered subparagraphs, and sets forth the various responsibilities of the parties prior to and immediately following closing.1 Paragraph 14 of the Agreement is titled "Warranties and Dispute Resolution," and consists of subparagraphs 14(a) through 14(j). Subparagraphs 14(c) and 14(g) contain provisions stating that the parties agree to arbitrate any claim arising out of D.R. Horton's construction of the home, as well as any disputes related to the warranties contained in the Agreement. However, in the majority of the remaining subparagraphs of paragraph 14, D.R. Horton expressly disclaims all warranties for the home—including the implied warranty of habitability—except for a ten-year structural warranty. Moreover, subparagraph 14(i) stipulates that D.R. Horton "shall not be liable for monetary damages of any kind, including secondary, consequential, punitive, general, special or indirect damages." (Emphasis in original).

In August 2005, D.R. Horton completed construction of the Smiths' home, and the Smiths closed on the property and received the deed. Thereafter, the Smiths experienced a myriad of problems with the home that resulted in severe

1 For example, the Agreement requires the Smiths to obtain suitable financing to purchase the home prior to the start of construction and to deposit a specified amount of earnest money, and requires D.R. Horton to convey marketable title to the Smiths at the closing. water damage to the property. D.R. Horton attempted to repair the alleged construction defects on "numerous occasions" during the next five years, but was ultimately unsuccessful.

In 2010, the Smiths filed a construction defect case against D.R. Horton and seven subcontractors. In response, D.R. Horton filed a motion to compel arbitration. The Smiths opposed the motion, arguing, inter alia, that the arbitration agreement was unconscionable and therefore unenforceable.

The circuit court denied D.R. Horton's motion to compel arbitration, finding that the arbitration agreement was unconscionable. The court based its ruling on "a number of oppressive and one-sided provisions," including D.R. Horton's attempted waiver of the implied warranty of habitability, as well as subparagraph 14(i)'s prohibition on awarding money damages of any kind against D.R. Horton. D.R. Horton made a motion to reconsider pursuant to Rule 59(e), SCACR, but the circuit court again denied the motion to compel.2

D.R. Horton appealed, and the court of appeals affirmed the circuit court's order. See Smith, 403 S.C. at 10, 742 S.E.2d at 37. The court of appeals found the arbitration agreement was unconscionable, citing subparagraph 14(i) and its prohibition on awarding money damages against D.R. Horton. Id. at 15, 742 S.E.2d at 40–41. Further, the court of appeals sua sponte conducted a severability analysis to determine whether subparagraph 14(i) could be severed from the remaining provisions of the arbitration agreement. Id. at 17, 742 S.E.2d at 41. The court of appeals ultimately concluded that severing the subparagraph would be inappropriate. Id.

D.R. Horton petitioned the court of appeals for rehearing, asserting that the court of appeals made two fundamental errors. First, D.R. Horton argued that the court of appeals' unconscionability analysis was flawed because it did not discuss whether the Smiths lacked a meaningful choice in entering the arbitration agreement. See Simpson v. MSA of Myrtle Beach, Inc., 373 S.C. 14, 24–25, 644 S.E.2d 663, 668 (2007) (stating that an unconscionability analysis has two prongs, one of which is whether one of the parties to the contract lacked a meaningful

2 In the second order denying D.R. Horton's motion to compel arbitration, the court elaborated on its previous finding of unconscionability, finding that the Agreement was a contract of adhesion, and that the Smiths had significantly less bargaining power than D.R. Horton. choice in agreeing to arbitrate (citing Carolina Care Plan, Inc. v. United HealthCare Servs., Inc., 361 S.C. 544, 554, 606 S.E.2d 752, 757 (2004); S.C. Code Ann. § 36-2-302(1) (1976))).

Second, D.R. Horton asserted that the court of appeals' decision violated the United States Supreme Court's holding in Prima Paint Corp. v. Flood & Conklin Manufacturing Co. See 388 U.S. 395, 406 (1967) (holding that courts may only consider the threshold question of whether the arbitration agreement is fraudulently induced and thus invalid, not whether the contract as a whole is invalid); see also S.C. Pub. Serv. Auth. v. Great W. Coal (Ky.), Inc., 312 S.C. 559, 562–63, 437 S.E.2d 22, 24 (1993) (adopting a broad interpretation of Prima Paint in South Carolina, and holding that "a party cannot avoid arbitration through rescission of the entire contract when there is no independent challenge to the arbitration clause" (the Prima Paint doctrine)). In D.R. Horton's view, the arbitration agreement was contained exclusively in subparagraph 14(g), and therefore, the court of appeals' consideration of the allegedly one-sided terms in subparagraph 14(i) was inappropriate.3

Ultimately, the court of appeals denied the petition for rehearing, and we granted D.R. Horton's petition for a writ of certiorari to review the court of appeals' decision.

ISSUE Whether the arbitration agreement is unconscionable?

STANDARD OF REVIEW Arbitrability determinations are subject to de novo review. Bradley v. Brentwood Homes, Inc., 398 S.C. 447, 453, 730 S.E.2d 312, 315 (2012). However, a circuit court's factual findings will not be reversed on appeal if any evidence reasonably supports the findings. Id. at 453, 730 S.E.2d at 315.

ANALYSIS

3 In conjunction with this argument, D.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Smith v. D.R. Horton, Inc, (S.C. 2016).

Smith v. D.R. Horton, Inc (Smith v. D.R. Horton, Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Prima Paint Corp. v. Flood & Conklin Mfg. Co.
388 U.S. 395 (Supreme Court, 1967)
Allied-Bruce Terminix Cos., Inc. v. Dobson
513 U.S. 265 (Supreme Court, 1995)
Buckeye Check Cashing, Inc. v. Cardegna
546 U.S. 440 (Supreme Court, 2006)
Preston v. Ferrer
552 U.S. 346 (Supreme Court, 2008)
Nitro-Lift Technologies, L. L. C. v. Howard
133 S. Ct. 500 (Supreme Court, 2012)
Jaffe v. Gibbons
351 S.E.2d 343 (Court of Appeals of South Carolina, 1986)
Kennedy v. Columbia Lumber & Manufacturing Co.
384 S.E.2d 730 (Supreme Court of South Carolina, 1989)
Columbia Architectural Group, Inc. v. Barker
266 S.E.2d 428 (Supreme Court of South Carolina, 1980)
Sapp v. Ford Motor Co.
687 S.E.2d 47 (Supreme Court of South Carolina, 2009)
Simpson v. MSA of Myrtle Beach, Inc.
644 S.E.2d 663 (Supreme Court of South Carolina, 2007)
South Carolina Public Service Authority v. Great Western Coal (Kentucky) Inc.
437 S.E.2d 22 (Supreme Court of South Carolina, 1993)
Zabinski v. Bright Acres Associates
553 S.E.2d 110 (Supreme Court of South Carolina, 2001)
Schulmeyer v. State Farm Fire & Casualty Co.
579 S.E.2d 132 (Supreme Court of South Carolina, 2003)
Carolina Care Plan, Inc. v. United Healthcare Services, Inc.
606 S.E.2d 752 (Supreme Court of South Carolina, 2004)
Munoz v. Green Tree Financial Corp.
542 S.E.2d 360 (Supreme Court of South Carolina, 2001)
Episcopal Housing Corp. v. Federal Insurance
239 S.E.2d 647 (Supreme Court of South Carolina, 1977)
Beach Co. v. Twillman, Ltd.
566 S.E.2d 863 (Court of Appeals of South Carolina, 2002)