Smith v. Adams

11 Va. Cir. 543, 1984 Va. Cir. LEXIS 64
CourtRockingham County Circuit Court
DecidedAugust 24, 1984
DocketCase No. (Chancery) 10421; Case No. (Law) 6888
StatusPublished

This text of 11 Va. Cir. 543 (Smith v. Adams) is published on Counsel Stack Legal Research, covering Rockingham County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Adams, 11 Va. Cir. 543, 1984 Va. Cir. LEXIS 64 (Va. Super. Ct. 1984).

Opinion

By JUDGE HENRY H. WHITING

This suit, filed to enforce a mechanic’s lien upon the defendant’s residence for restoration work after its damage by fire, involves a number of issues which will be dealt with in the order of their required resolution.

[544]*544(A) Was the memorandum of mechanic’s lien filed within the required ninety-day period?

The property owners say that the mechanic’s lien was filed beyond the ninety-day period. The contention is denied for the following reasons.

(1) One claim is that inserting the date interest was to accrue as beyond the ninety-day period meant that the contract was completed on that date.

While interest was claimed from June 10, 1983, and the contractor did not file the memorandum of mechanic’s lien until September 14, 1983, its president contended that interest accrued from the date the owners got the insurance check for the loss and not from the date of completion of the job. Nowhere on the memorandum does the contractor state when the job was completed, nor was it required to do so by the applicable statutes. Virginia Code Sections 43-4, 43-5. The Court does not believe an amendment is required to the memorandum; it finds as a fact that the contractor merely claimed interest from the earlier date and that did not preclude him from proving the actual completion date.

(2) Evidence has been heard upon the factual dispute as to whether work was done upon the premises within the ninety-day period of the filing of the memorandum. At the hearing the contractor introduced evidence to show James Byrd, one of its employees, hung four of the storm windows required to be supplied under the contract within that period. That employee, who testified by deposition, said he picked up those windows at a local supply source showing the delivery of four storm windows to him within the ninety-day period. (This was corroborated by the invoice. (Plaintiff’s Exhibit 3 to the deposition)) Byrd said that the defendant Joyce Schultz came out of the house as he was installing the windows and asked his identity and purpose, which he furnished (deposition April 14, 1984, page 6). His time is also corroborated by the time ticket introduced as Plaintiff’s Exhibit 2 to the deposition. The property owners contended that this ticket was for an earlier week of work, so indicated in pencil on each day at the top and changed by an office employee in ink to falsely indicate a later week. The other time tickets (Plaintiff’s Exhibits 2 and 3) by the [545]*545same laborer clearly indicate he was not working on the Adams’s house a week earlier or a week later. The Court does not find a fraudulent attempt to alter records has been established but rather a routine correction as testified by the bookkeeper.

While both owners denied the installation of those four windows on June 16th (or thereafter), the Court finds as a fact that they were installed on that date as a part of the contract between the parties.

(3) The Court further finds that this installation was not a structured attempt to begin a new period to file a mechanic's lien: (1) by furnishing material not contemplated to be a apart of the completed structure after the former period had expired, as in the lower court opinion in Canton Roll & Machine Co. v. Rolling Mill Co. of America, et al., 155 F. 321, 332, et seq. (N.D. W.Va. 1907) (cited by the owners in this case), reversed as to the finding that the rolls were outside the contract and not a part of the structure and the lien reinstated in Canton Roll & Machine Co. v. Rolling Mill Co. of America, et al., 168 F. 465, 469, et seq. (4th Cir. 1909), or (2) making inconsequential repairs, condemned in Section 192 Am. Jur. 2d Mechanic's Liens, page 710.

Accordingly, the motion for summary judgment and to dismiss the bill of complaint in the mechanic’s lien suit (Chancery No. 10421) is denied.

(B) Are the defendants entitled to a jury triall

They assert the right is absolute on three theories.

(1) The mechanic's lien suit cannot proceed because the memorandum of lien was filed too late and therefore we should treat the suit as a law action with the right to a jury trial. This contention fails because of the ruling above.

(2) A jury trial is a matter of right under Article 1, Section 11, of the Constitution of Virginia and Section 8.01-336, Virginia Code. The contention is inapposite for several reasons.

(a) Contrary to the property owners’ assertion on page 3 of their memorandum of March 7, 1984, that "Section 8.01-336 of the Code of Virginia . . . guarantees the right to a trial by jury in all matters whether at [546]*546equity or at law unless that right be waived," the statute itself provides only for a waiver of the right to a jury trial "in any action at law" where no demand therefore is filed. Virginia Code Section 8.01-336(B). The principles of exclusion by enumeration would seem to deny any such right to a jury trial in equity in this subparagraph B, especially when we see that jury trials in equity are specifically treated in subparagraphs D and E thereof, discussed hereafter.

(b) Virginia Code Section 8.01-336(D) requires a jury trial in equity where "a plea has been filed to an equitable claim, and the allegations of such plea are denied by the plaintiff." That section codifies the parlier equity practice, Lite's Pleading and Practice, sect. 199 at p. 114 (3d ed. 1952), but the defendant must present "a single set of facts (although possibly made up of numerous circumstances) as a defense to the plaintiff’s suit." Ibid. Illustrative of that principle in cases construing Section 8.01-336(D) are Bolling v. General Motors Acceptance Corp., 204 Va. 4 (1963), and Campbell v. Johnson, 203 Va. 43 (1961). In Bolling an answer and a counterclaim were filed to a bill in equity seeking the enforcement of a conditional sales contract on a truck. The Supreme Court held that even if these pleadings had been put in the proper form so as to invoke the statute giving a right to a trial by jury on a plea in equity, they did not present a single issue of fact operating as a bar to the right of recovery, citing Lile, supra and Merwin, Equity and Equity Pleading, id., at 8. Since the pleadings admitted a default under the contract and set up a claim for breach of warranty as an offset, it did not qualify as "reducing the issue ... to a single point [so that] when issue is taken on such a plea and judgment entered on the jury’s favorable verdict thereon, the case [would be] at an end." Ibid.

In Campbell a trial judge erroneously submitted two issues to a jury in a suit in equity against a defaulting servant to trace funds and impress a lien on assets purchased with those funds. The issues were (1) whether the funds were unlawfully taken and, if so (2) the amount of money taken. When the jury "hung," the trial judge was sustained in removing the second issue from consideration and taking a verdict only on the first issue and [547]*547then concluding the case by deciding the amount taken itself and without a jury. The appellate court held that the only issue which should have been submitted to the jury was whether any money had been unlawfully taken and the amount then became a "matter of accounting." Id., at 46.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bolling v. General Motors Acceptance Corp.
129 S.E.2d 54 (Supreme Court of Virginia, 1963)
Stevens v. Sparks
135 S.E.2d 140 (Supreme Court of Virginia, 1964)
Campbell v. Johnson
122 S.E.2d 907 (Supreme Court of Virginia, 1961)
McCully v. McCully
78 Va. 159 (Supreme Court of Virginia, 1883)
Grubb v. Starkey
20 S.E. 784 (Supreme Court of Virginia, 1894)
Stevens v. Duckett
57 S.E. 601 (Supreme Court of Virginia, 1907)
Catron v. Norton Hardware Co.
96 S.E. 853 (Supreme Court of Virginia, 1918)
Hook v. Hook
101 S.E. 223 (Supreme Court of Virginia, 1919)
Bunkley v. Commonwealth
108 S.E. 1 (Supreme Court of Virginia, 1921)
Harris v. Citizens Bank & Trust Co.
200 S.E. 652 (Supreme Court of Virginia, 1939)
Canton Roll & Machine Co. v. Rolling Mill Co. of America
155 F. 321 (U.S. Circuit Court for the District of Northern West Virginia, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
11 Va. Cir. 543, 1984 Va. Cir. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-adams-vaccrockingham-1984.