Smith Engineering Co. v. Pray

61 F.2d 687, 1932 U.S. App. LEXIS 4384
Court of Appeals for the Ninth Circuit·Decided November 7, 1932·No. No. 6821·Published·Cited by 7 cases

Opinion

WILBUR, Circuit Judge.

Petitioners’ application for rehearing having been granted, and the opinion heretofore rendered having' been reported [58 F. (2d) 926, 927], we refer to that opinion for a statement of the facts.'

In petitioners’ application for rehearing, the applicability of the hypothetical 'question stated by the court in the former opinion is vigorously assailed. This hypothetical question is as follows; “Will a court of equity in a suit to foreclose a mechanic’s lien, asserted upon the ground that the contractor has completed the contract as far as possible for him to do so, and has been prevented from entire, completion. by the owner, not only entertain the defense of á breach of the contract by the contractor, biit also entertain a cross-complaint seeking damages for the breach of the contract by the contractor?”

The question is hardly apposite to the point involved on this application for a writ of mandamus, for the reason that we are considering the right of the petitioners to a jury.trial on the legal issues and not the right of the owner. Undoubtedly the owner by the consolidation of the two actions at its request, is in substantially the position as to its right to a jury trial as it would have been had it pleaded its claim for damages by cross-complaint in the court of equity in the first action to foreclose the mechanic’s lien. We are not concerned with its right to do so under Equity Rule 30 (28 USCA § 723), which, as petitioners contend, requires or permits equitable, and not legal, set-offs or counterclaims to be pleaded by a defendant in a suit in equity [Brewster-Greene et ux. v. Scott (C. C. A.) 41 F.(2d) 165; Fleming Bros. Lbr. Co. v. McDonald Amusement Co. (D. C.) 36 F.(2d) 483; Summit Coal Co. v. Southern Cotton Oil Co. (C. C. A.) 24 F.(2d) 48; American Mills Co. v. American Surety Co., 260 U. S. 360, 43 S. [689] Ct. 149, 67 L. Ed. 306; Stephens et al. v. Howells Sales Co. (D. C.) 16 F.(2d) 805; Nowata Oil & Refining Co. v. Elliott (D. C.) 32 F.(2d) 349]; but with the fact that it has done so and thereby waived its right to a trial by jury [Clifton v. Tomb (C. C. A.) 21 F.(2d) 893]. However, this conclusion as to the right of the owner to a jury trial on the legal issues does not determine the corresponding right of the petitioners which would not be affected by the fact that the owner had improperly pleaded its legal cause of action for damages as a counterclaim in the action to foreclose the mechanic’s lien. Nowata Oil & Ref. Co. v. Elliott (D. C.) 32 F.(2d) 349, supra. The question upon this application for writ of mandamus is whether or not the petitioners are entitled to a jury trial upon the legal action brought by the owner against the petitioners for damages for nonperformance o£ the contract. That question must be answered in the negative, if the whole controversy is properly before a court of equity sitting as such; that is to say, if the legal issues are so interwoven with the equitable issues as to require the chancellor to consider both in arriving at his conclusion so that he had jurisdiction of the whole controversy under the practice at common law, as the Constitution does not accord to the petitioners, under such circumstances, a right to trial of the legal issues by jury. In our former opinion, we did not perhaps give due weight to the fact that the consolidation of the two actions was over the objection of the petitioners, and that they contended in support of their petition for mandamus that the order of consolidation was unauthorized. Eor the purpose of determining the right of petitioners to-a mandamus, we assumed in the question stated that the error in consolidating the two actions, if it was an error, was not properly reviewable on such an application.

The question before us is whether or not the petitioners, by their conduct, have waived their right to have the legal issues in the consolidated action tried before a jury. In the legal action they pleaded the pendency of the equitable action to foreclose the mechanic’s lien and asked that the trial of the legal action be suspended until the trial of the same issues involved in the action to foreclose the mechanic’s lien which was first brought. Thus, in effect, they invoked the power of the court of equity to enjoin the prosecution of the legal action until after the determination of the equitable action in which the issue of prevention of

Free access — add to your briefcase to read the full text and ask questions with AI

Smith Engineering Co. v. Pray, 61 F.2d 687, 1932 U.S. App. LEXIS 4384 (9th Cir. 1932).

61 F.2d 687 (Smith Engineering Co. v. Pray) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related