SM 10000 Property, LLC v. Allianz Global Risks US Insurance Company

CourtDistrict Court, N.D. California
DecidedApril 7, 2021
Docket4:19-cv-03054
StatusUnknown

This text of SM 10000 Property, LLC v. Allianz Global Risks US Insurance Company (SM 10000 Property, LLC v. Allianz Global Risks US Insurance Company) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SM 10000 Property, LLC v. Allianz Global Risks US Insurance Company, (N.D. Cal. 2021).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA

7 SM 10000 PROPERTY, LLC, et al., Case No. 19-cv-03054-PJH 8 Plaintiffs,

9 v. ORDER GRANTING IN PART AND DENYING IN PART PLAINTIFFS' 10 ALLIANZ GLOBAL RISKS US MOTION FOR SUMMARY JUDGMENT INSURANCE COMPANY, AND GRANTING IN PART AND 11 DENYING IN PART DEFENDANT'S Defendant. MOTION FOR SUMMARY JUDGMENT 12 Re: Dkt. Nos. 63, 68 13

14 Plaintiff SM 10000 Property LLC’s (“SM”) and Swinerton Builders, Inc.’s 15 (“Swinerton”) (collectively, “plaintiffs”) motion for summary judgment came on for hearing 16 before this court on January 28, 2021. Defendant Allianz Global Risks US Insurance 17 Company’s (“defendant”) motion for summary judgment came on for hearing before this 18 court that same day. Plaintiffs appeared through their counsel, Valentine Hoy and Linda 19 Kornefeld. Defendant appeared through its counsel Matthew Ponzi and Christopher 20 Snow. Having read the parties’ papers and carefully considered their arguments and the 21 relevant legal authority, and good cause appearing, the court GRANTS IN PART and 22 DENIES IN PART plaintiffs’ motion for summary judgment and GRANTS IN PART and 23 DENIES IN PART defendant’s motion for summary judgment. 24 BACKGROUND 25 This case is an insurance coverage action arising out of an accident during the 26 construction of a luxury residential building west of downtown Los Angeles. On May 1, 27 2019, plaintiffs filed the action against defendant in the San Francisco County Superior 1 complaint, plaintiffs allege the following three claims: 2 • Breach of contract. Dkt. 1-1 at 31-42 (Compl.) ¶¶ 25-28. 3 • Breach of the implied covenant of good faith and fair dealing. Id. ¶¶ 29-34 (the 4 “bad faith claim”). 5 • Declaratory relief. Id. ¶¶ 35-37. 6 Plaintiffs seek punitive damages on their bad faith claim. Id. ¶ 34. In its answer, 7 defendant alleges reformation as an affirmative defense. Dkt. 1-1 at 2-28 ¶¶ 72-77 (the 8 “reformation defense”). 9 On December 2, 2020, the parties filed the instant cross-motions for summary 10 judgment. Dkt. 68 (plaintiffs’ motion); Dkt 63 (defendant’s motion); Dkt. 75 (defendant’s 11 opening brief errata). During their briefing, the parties filed multiple erratas to their briefs 12 and associated exhibits. Unless otherwise specified, the court will cite the revised filings. 13 The sequence of events, insurance policy provisions, and the parties’ prelitigation 14 communications are key to understand their dispute. The court will detail the relevant 15 facts as necessary below. 16 I. The Parties 17 SM is a limited liability company formed by principals of a firm that develops, 18 owns, and operates real property in major United States cities. Dkt. 71 (Palermo Decl.) ¶ 19 2. SM owns the real property (“Ten Thousand”) at issue. Id. In 2013, SM hired 20 Swinerton as a general contractor to build Ten Thousand. 21 Defendant is an insurer. It issued to plaintiffs the policy underlying plaintiffs’ 22 claims. Dkt. 68-2 (“Policy”) at 47, § 1B (endorsement adding SM and Swinerton as 23 additional insureds). 24 II. The Ten Thousand Building and Its Construction 25 Ten Thousand is a characteristically Los Angeles high-rise located at 10000 Santa 26 Monica Boulevard. Dkt. 71 ¶ 4. It comprises 40 floors and 283 units. Id. ¶ 4. It includes 27 an outdoor park, movie theaters, and an 80-person staff to “see to its residents’ every 1 construction cost was over $198 million. Dkt. 71 ¶ 5. 2 A. The Construction Agreement Between Plaintiffs 3 On November 14, 2013, plaintiffs entered an “Agreement Between Owner and 4 Contractor” (the “Construction Contract”). Dkt. 71 ¶ 6. Under the Construction Contract, 5 Swinerton would provide SM the complex’s units in multiple phases. Dkt. 71 ¶ 8. As part 6 of that plan, SM would gain early occupation of an on-site leasing office. Id. From there, 7 Swinerton would deliver the subject units on a lower floor to upper floor basis. Id. 8 Under the Construction Contract, Swinerton would begin working on the project on 9 November 18, 2013. Dkt. 71-2 (Construction Contract) at 12 ¶ 4.1.1. The Construction 10 Contract details four “completion deadlines/milestones.” Dkt. 71-2 at 13, ¶ 4.1.2. The 11 subject deadlines range from September 4, 2015 to May 10, 2016. Id. Each deadline 12 calls for the construction of a certain number of units in the building. Id. 13 The court will detail the milestones as necessary in its analysis below. 14 B. Pre-December 2, 2015 Delays 15 Aspirations aside, plaintiffs encountered a handful of delays during construction. 16 First, because of SM’s unspecified delays in obtaining loans, Swinerton did not break 17 ground until April 2, 2014, Dkt. 71 ¶ 7, thereby adding around 4.5 months to the original 18 break ground date. Second, because of the discovery of methane gas on some 19 unspecified date, Swinerton had to install a vapor barrier. Dkt. 69 ¶ 3. That installation 20 delayed the project by approximately 30 days. Id. 21 C. The Revised November 30, 2015 Construction Schedule 22 On November 30, 2015, just days before the accident giving rise to this action, 23 Swinerton issued a revised construction schedule to SM. Dkt. 69 ¶ 4 (attaching revised 24 schedule, Dkt. 69-1). Under that schedule, Swinerton’s delivery on the four milestones 25 referenced above was extended approximately five to six months, respectively. Id. ¶ 5. 26 D. The December 2, 2015 Concrete Accident 27 On December 2, 2015, workers poured concrete into a wooden frame outlining the 1 Id. Two tons of concrete cascaded into the elevator shaft, smashing numerous wooden 2 crash decks along the way. Id. The wet concrete and wood fell to the pit of the elevator. 3 Id. While money was lost, nobody was hurt. 4 E. The Dates of Actual Completion and Delivery of the Milestones 5 On July 1, 2016, Swinerton completed and delivered Ten Thousand’s leasing 6 office. Dkt. 71 ¶ 11. In January 2017, Swinerton completed and delivered the 1st 7 through 21st units to SM. Id. ¶ 12. Between January 2017 and March 9, 2017, 8 Swinerton completed and delivered the 22nd through 96th units. Id. ¶ 13. Between 9 March 9, 2017 and April 20, 2017, Swinerton delivered the 97th through 225th units. Id. 10 Between April 20, 2017 and April 27, 2017, Swinerton delivered the 226th through 275th 11 units. Id. The delivery dates for the remaining eight units are not at issue. 12 A wait list of prospective tenants formed before Swinerton completed the above 13 units. Dkt. 71 ¶ 12. SM leased the units as quickly as Swinerton delivered them. Id. 14 III. The Parties’ Post-Accident Communications and Tendered Claims 15 On December 21, 2015, SM, through its broker of record the Aon company 16 (“Aon”), emailed defendant a notice of loss concerning the damage caused by the 17 December 2, 2015 accident. Dkt. 64 (Reyes Decl.) ¶ 9. Defendant opened a claim. 18 On December 22, 2015, defendant’s adjuster, Lourdes Reyes (“Reyes”), spoke 19 with Swinerton’s project manager for Ten Thousand, Keith Dancey (“Dancey”), about the 20 accident and resulting damage. Id. ¶ 10. That same day, Reyes inspected the scene of 21 the accident. Id. ¶¶ 11-12. In 2016, Reyes sent Swinerton several requests for 22 information “relevant to the evaluation” of its claim under the policy. Id. ¶¶ 14, 16-24. 23 On January 3, 2017, Reyes received a link with various documents concerning 24 Swinerton’s tendered claim (the “Property Damage Claim”). Id. ¶ 25. Swinerton initially 25 sought $2,695,241.56 in property damage related costs. Id. Reyes, Aon, and Swinerton 26 engaged in numerous follow-up conversations. Id. ¶¶ 26-31. Reyes later received an 27 updated claim from Swinerton seeking an additional $10,014,930.92. Id. ¶ 31. 1 claim (the “Delay Claim”). Dkt. 64 ¶ 36. SM sought $19,169,367 in loss purportedly 2 resulting from Ten Thousand’s delayed opening. Id. Reyes sought and received 3 additional information from both plaintiffs through 2017. Id. ¶¶ 38-44, ¶¶ 49-50.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Harris
25 F.3d 1275 (Fifth Circuit, 1994)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Marian Fontenot, Etc. v. The Upjohn Company
780 F.2d 1190 (Fifth Circuit, 1986)
United States v. Ralph R. Ross
9 F.3d 1182 (Seventh Circuit, 1993)
KG Urban Enterprises, LLC v. Patrick
693 F.3d 1 (First Circuit, 2012)
Love v. Fire Insurance Exchange
221 Cal. App. 3d 1136 (California Court of Appeal, 1990)
Getty v. Getty
187 Cal. App. 3d 1159 (California Court of Appeal, 1986)
Shupe v. Nelson
254 Cal. App. 2d 693 (California Court of Appeal, 1967)
CHATEAU CHAMBERAY HOA v. Associated Internat. Ins. Co.
108 Cal. Rptr. 2d 776 (California Court of Appeal, 2001)
Hess v. Ford Motor Co.
41 P.3d 46 (California Supreme Court, 2002)
Tolan v. Cotton
134 S. Ct. 1861 (Supreme Court, 2014)
South Coast Framing, Inc. v. Workers' Compensation Appeals Board
349 P.3d 141 (California Supreme Court, 2015)
Friedman v. Live Nation Merchandise, Inc.
833 F.3d 1180 (Ninth Circuit, 2016)
Innis v. Steamboat Senator
4 Cal. 5 (California Supreme Court, 1852)
Stufflebeem v. Arnold
57 Cal. 11 (California Supreme Court, 1880)
Leslie v. Grupo ICA
198 F.3d 1152 (Ninth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
SM 10000 Property, LLC v. Allianz Global Risks US Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sm-10000-property-llc-v-allianz-global-risks-us-insurance-company-cand-2021.