Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C.

CourtOhio Court of Appeals
DecidedJune 15, 2026
Docket2025-G-0042
StatusPublished

This text of Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C. (Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C., (Ohio Ct. App. 2026).

Opinion

[Cite as Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C., 2026-Ohio-2249.]

IN THE COURT OF APPEALS OF OHIO ELEVENTH APPELLATE DISTRICT GEAUGA COUNTY

SLOCUM MAINTENANCE CASE NO. 2025-G-0042 INCORPORATED,

Plaintiff-Appellee, Civil Appeal from the Court of Common Pleas - vs -

400 WASHINGTON 44024, L.L.C., Trial Court No. 2023 M 000484 et al.,

Defendants-Appellants.

OPINION AND JUDGMENT ENTRY

Decided: June 15, 2026 Judgment: Reversed and remanded

Robert N. Farinacci, 65 North Lake Street, Madison, OH 44057 (For Plaintiff-Appellee).

James E. Grendell, Plunkett Cooney, 716 Mount Airyshire, Suite 150, Columbus, OH 43235 (For Defendants-Appellants).

JOHN J. EKLUND, J.

{¶1} Appellants, 400 Washington 44024, L.L.C. and Greg Vilk (“Vilk”), appeal the

jury verdict in the Geauga County Court of Common Pleas finding them liable for breach

of contract and awarding damages of $65,000.00 to Appellee, Slocum Maintenance

Incorporated (“SMI”).

{¶2} Appellants raise two assignments of error, arguing: (1) the trial court erred

by failing to grant Appellants’ motion for a directed verdict; and (2) the jury’s verdict was

against the manifest weight of the evidence as to both liability and the judgment amount. {¶3} Having reviewed the record and the applicable caselaw, we find Appellants’

first assignment of error to be without merit. There was sufficient, concrete evidence

presented for the jury to determine both liability and damages. However, we find that

Appellants’ second assignment of error has merit because the amount of damages the

jury awarded was against the manifest weight of the evidence.

{¶4} Therefore, we reverse the judgment of the Geauga County Court of

Common Pleas and remand the matter for a new trial as to damages.

Substantive and Procedural History

{¶5} On July 1, 2022, Appellants and SMI entered into a contract. Appellee,

owned and operated by Derin Slocum (“Slocum”), agreed to furnish materials and

improvements for a renovation of Appellants’ property located at 400 Washington Street,

Chardon, Ohio. Appellants agreed to pay $385,496.00 for the project, which was to

proceed in three phases.

{¶6} On August 16, 2023, Appellee filed a Complaint in the Geauga County Court

of Common Pleas for breach of contract seeking damages of $80,500.00.

{¶7} On September 26, 2023, Appellants filed their Answer and Counterclaims

against Appellee, asserting breach of contract, unjust enrichment, slander of title, and

tortious interference with business relationship/contract.

{¶8} On October 21, 2025, the case was tried to a jury where the following facts

and evidence were adduced:

Slocum’s testimony:

{¶9} Slocum owns SMI, which operated as a reconstruction and remodeling

business. Appellee entered into a contract with Appellants to renovate the property at 400

PAGE 2 OF 16

Case No. 2025-G-0042 Washington Street. The contract involved Appellee’s renovating the roof, removing

garage and bay doors, and installing wood framing to enclose the outside of the building.

The project commenced in three phases. Phase 1 was projected to take three months,

Phase 2 was projected to take one and a half months, and Phase 3 was projected to take

two weeks. Performance began in August 2022.

{¶10} Appellants paid SMI $160,496.00 when they completed Phase 1, which

involved the installation and framing for security doors and roll up doors. Phase 2 involved

the removal of all siding and roofing and installation of a radiant vapor barrier, metal trims,

and new roof panels. According to Slocum, SMI completed all Phase 2 requirements

except for the end-of-phase punch list, which was meant to identify any outstanding

issues or flaws in the project. Vilk complained of a dent in one of the bay doors, but

Slocum denied that the dent was present when the door was installed. However, SMI

received $110,500.00 for the completion of Phase 2 as outlined in the contract.

{¶11} Slocum addressed the cause of several delays in the project. There was a

one-month delay in installing the new siding because the City of Chardon requires new

colors to be approved. Other delays occurred. The demolition process took longer than

anticipated due to difficulties in removing concrete platforms around the bay doors.

Slocum said the original cost estimate for that work was $20,000.00. However, the

difficulties increased the expense by $10,000.00, which Vilk declined to pay.

{¶12} Another delay occurred when, according to Slocum, Vilk requested that

Slocum do emergency work on a condominium complex. Slocum said that Vilk was on

the board of the complex and his girlfriend was the president of the HOA. There had been

a fire at the site, and it needed emergency rehabilitation due to fire and smoke damage.

PAGE 3 OF 16

Case No. 2025-G-0042 He said that Vilk wanted him to prioritize that job and it halted work at the 400 Washington

Street site for approximately two months.

{¶13} Slocum testified that there was certain interior framing work that Vilk wanted

to be done. Slocum believed it was not part of the contract. Slocum raised that, and the

additional cost of this work with Vilk. Vilk’s position was that the framing had been

addressed in the contract implicitly because the contract discussed insulation and

electrical work that would necessarily be part of the interior framing job.

{¶14} Vilk sent Slocum a text message on April 14, 2023, stating that the electrical

work needed to be finished by April 21, 2023, and that the insulation would need to

proceed immediately after that. Vilk told Slocum not to hesitate to say if this could not be

completed. Slocum responded, “Yes, . . . I got it.”

{¶15} Slocum completed electrical work to support the interior framing and sent a

bill for $30,000.00. Vilk paid only $12,000.00 on that bill. Similarly, Slocum billed

$16,000.00 for framing work but was not paid for that work at all. Finally, Slocum had

scheduled and paid a subcontractor for anticipated insulation work to be done during

Phase 3. When Vilk cancelled the contractor, Slocum paid a subcontractor $5,000.00 for

the subcontractor to abandon the insulation job because the insulation had already been

ordered by the time Vilk cancelled the project.

{¶16} When Slocum found out that Vilk was selling the building, he sent a final bill

to Vilk on May 23, 2023. The bill stated that Vilk owed:

$14,500.00 for framing to allow for insulation and electrical work $18,000.00 for unpaid electrical work $50,000.00 for cancellation of Phase 3 of the project.

PAGE 4 OF 16

Case No. 2025-G-0042 For a total of: $80,500.00.1

{¶17} Also on May 23, 2023, Slocum placed a mechanic’s lien for $80,500.00 on

the property for the outstanding contract balance. Slocum said that he was not paid

anything for Phase 3 of the project. He said Phase 3 was to include insulation and labor

and was estimated to cost $50,000.00. The contract provided that Appellee would sell the

scrap metal from the project and credit the price to Appellants. Slocum testified that he

had not sold the scrap and that Vilk was free to sell the scrap metal from the project on

his own.

{¶18} On cross-examination, Slocum said that he did not have any

documentation, such as invoices, W2s, 1099s, or bills of lading, to support the damages

outlined in his testimony or demand letter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Martin
485 N.E.2d 717 (Ohio Court of Appeals, 1983)
Wrg Servs. v. Eilers, 2008-L-057 (11-7-2008)
2008 Ohio 5854 (Ohio Court of Appeals, 2008)
Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co.
86 N.E.2d 782 (Ohio Supreme Court, 1949)
Ultimate Salon & Spa, Inc. v. Legends Const. Group
2019 Ohio 2506 (Ohio Court of Appeals, 2019)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Cafaro-Peachcreek Joint Venture Partnership v. Spanggard
2022 Ohio 4468 (Ohio Court of Appeals, 2022)
State v. Thompkins
1997 Ohio 52 (Ohio Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/slocum-maintenance-inc-v-400-washington-44024-llc-ohioctapp-2026.