Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C.

2026 Ohio 2249
Ohio Court of Appeals·Decided June 15, 2026·No. 2025-G-0042·Published

Opinion

IN THE COURT OF APPEALS OF OHIO ELEVENTH APPELLATE DISTRICT GEAUGA COUNTY

SLOCUM MAINTENANCE CASE NO. 2025-G-0042 INCORPORATED,

Plaintiff-Appellee, Civil Appeal from the Court of Common Pleas

- vs -

400 WASHINGTON 44024, L.L.C., Trial Court No. 2023 M 000484 et al.,

Defendants-Appellants.

OPINION AND JUDGMENT ENTRY

Decided: June 15, 2026

Judgment: Reversed and remanded

Robert N. Farinacci, 65 North Lake Street, Madison, OH 44057 (For Plaintiff-Appellee).

James E. Grendell, Plunkett Cooney, 716 Mount Airyshire, Suite 150, Columbus, OH 43235 (For Defendants-Appellants).

JOHN J. EKLUND, J.

{¶1} Appellants, 400 Washington 44024, L.L.C. and Greg Vilk (“Vilk”), appeal the jury verdict in the Geauga County Court of Common Pleas finding them liable for breach of contract and awarding damages of $65,000.00 to Appellee, Slocum Maintenance Incorporated (“SMI”).

{¶2} Appellants raise two assignments of error, arguing: (1) the trial court erred by failing to grant Appellants’ motion for a directed verdict; and (2) the jury’s verdict was against the manifest weight of the evidence as to both liability and the judgment amount.

{¶3} Having reviewed the record and the applicable caselaw, we find Appellants’

first assignment of error to be without merit. There was sufficient, concrete evidence presented for the jury to determine both liability and damages. However, we find that Appellants’ second assignment of error has merit because the amount of damages the jury awarded was against the manifest weight of the evidence.

{¶4} Therefore, we reverse the judgment of the Geauga County Court of Common Pleas and remand the matter for a new trial as to damages.

Substantive and Procedural History

{¶5} On July 1, 2022, Appellants and SMI entered into a contract. Appellee, owned and operated by Derin Slocum (“Slocum”), agreed to furnish materials and improvements for a renovation of Appellants’ property located at 400 Washington Street, Chardon, Ohio. Appellants agreed to pay $385,496.00 for the project, which was to proceed in three phases.

{¶6} On August 16, 2023, Appellee filed a Complaint in the Geauga County Court of Common Pleas for breach of contract seeking damages of $80,500.00.

{¶7} On September 26, 2023, Appellants filed their Answer and Counterclaims against Appellee, asserting breach of contract, unjust enrichment, slander of title, and tortious interference with business relationship/contract.

{¶8} On October 21, 2025, the case was tried to a jury where the following facts and evidence were adduced: Slocum’s testimony:

{¶9} Slocum owns SMI, which operated as a reconstruction and remodeling business. Appellee entered into a contract with Appellants to renovate the property at 400

PAGE 2 OF 16

Washington Street. The contract involved Appellee’s renovating the roof, removing garage and bay doors, and installing wood framing to enclose the outside of the building. The project commenced in three phases. Phase 1 was projected to take three months, Phase 2 was projected to take one and a half months, and Phase 3 was projected to take two weeks. Performance began in August 2022.

{¶10} Appellants paid SMI $160,496.00 when they completed Phase 1, which involved the installation and framing for security doors and roll up doors. Phase 2 involved the removal of all siding and roofing and installation of a radiant vapor barrier, metal trims, and new roof panels. According to Slocum, SMI completed all Phase 2 requirements except for the end-of-phase punch list, which was meant to identify any outstanding issues or flaws in the project. Vilk complained of a dent in one of the bay doors, but Slocum denied that the dent was present when the door was installed. However, SMI received $110,500.00 for the completion of Phase 2 as outlined in the contract.

{¶11} Slocum addressed the cause of several delays in the project. There was a one-month delay in installing the new siding because the City of Chardon requires new colors to be approved. Other delays occurred. The demolition process took longer than anticipated due to difficulties in removing concrete platforms around the bay doors. Slocum said the original cost estimate for that work was $20,000.00. However, the difficulties increased the expense by $10,000.00, which Vilk declined to pay.

{¶12} Another delay occurred when, according to Slocum, Vilk requested that Slocum do emergency work on a condominium complex. Slocum said that Vilk was on the board of the complex and his girlfriend was the president of the HOA. There had been a fire at the site, and it needed emergency rehabilitation due to fire and smoke damage.

PAGE 3 OF 16

He said that Vilk wanted him to prioritize that job and it halted work at the 400 Washington Street site for approximately two months.

{¶13} Slocum testified that there was certain interior framing work that Vilk wanted to be done. Slocum believed it was not part of the contract. Slocum raised that, and the additional cost of this work with Vilk. Vilk’s position was that the framing had been addressed in the contract implicitly because the contract discussed insulation and electrical work that would necessarily be part of the interior framing job.

{¶14} Vilk sent Slocum a text message on April 14, 2023, stating that the electrical work needed to be finished by April 21, 2023, and that the insulation would need to proceed immediately after that. Vilk told Slocum not to hesitate to say if this could not be completed. Slocum responded, “Yes, . . . I got it.”

{¶15} Slocum completed electrical work to support the interior framing and sent a bill for $30,000.00. Vilk paid only $12,000.00 on that bill. Similarly, Slocum billed $16,000.00 for framing work but was not paid for that work at all. Finally, Slocum had scheduled and paid a subcontractor for anticipated insulation work to be done during Phase 3. When Vilk cancelled the contractor, Slocum paid a subcontractor $5,000.00 for the subcontractor to abandon the insulation job because the insulation had already been ordered by the time Vilk cancelled the project.

{¶16} When Slocum found out that Vilk was selling the building, he sent a final bill to Vilk on May 23, 2023. The bill stated that Vilk owed:

$14,500.00 for framing to allow for insulation and electrical work $18,000.00 for unpaid electrical work $50,000.00 for cancellation of Phase 3 of the project.

PAGE 4 OF 16

For a total of: $80,500.00.1

{¶17} Also on May 23, 2023, Slocum placed a mechanic’s lien for $80,500.00 on the property for the outstanding contract balance. Slocum said that he was not paid anything for Phase 3 of the project. He said Phase 3 was to include insulation and labor and was estimated to cost $50,000.00. The contract provided that Appellee would sell the scrap metal from the project and credit the price to Appellants. Slocum testified that he had not sold the scrap and that Vilk was free to sell the scrap metal from the project on his own.

{¶18} On cross-examination, Slocum said that he did not have any documentation, such as invoices, W2s, 1099s, or bills of lading, to support the damages outlined in his testimony or demand letter.

{¶19} He said that his profit margin on Phase 1 was “maybe” $10,000.00 after paying for all material and labor. He could not recall his profit margin on Phase 2. He acknowledged that he had not done any work on Phase 3. He said that he was seeking the entire $50,000.00 provided for in the contract for Phase 3 because Vilk “was in breach of contract for that.” When pressed on what the profits from Phase 3 would have been, Slocum said that he underbid the project. He never provided a response to what his losses were for not performing Phase 3. He did not explain why he was entitled to receive the full $50,000.00 for work that had not been performed, nor did he state what his expected material or labor costs would have been for Phase 3.

{¶20} At the close of Appellee’s case, Appellants moved for a directed verdict.

Free access — add to your briefcase to read the full text and ask questions with AI

Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C., 2026 Ohio 2249 (Ohio Ct. App. 2026).

2026 Ohio 2249 (Slocum Maintenance, Inc. v. 400 Washington 44024, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Martin
485 N.E.2d 717 (Ohio Court of Appeals, 1983)
Wrg Servs. v. Eilers, 2008-L-057 (11-7-2008)
2008 Ohio 5854 (Ohio Court of Appeals, 2008)
Allen, Heaton & McDonald, Inc. v. Castle Farm Amusement Co.
86 N.E.2d 782 (Ohio Supreme Court, 1949)
Ultimate Salon & Spa, Inc. v. Legends Const. Group
2019 Ohio 2506 (Ohio Court of Appeals, 2019)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Cafaro-Peachcreek Joint Venture Partnership v. Spanggard
2022 Ohio 4468 (Ohio Court of Appeals, 2022)
State v. Thompkins
1997 Ohio 52 (Ohio Supreme Court, 1997)