Sloane v. United States

196 F. Supp. 643, 1961 U.S. Dist. LEXIS 4060
CourtDistrict Court, E.D. South Carolina
DecidedAugust 19, 1961
DocketCiv. A. No. 7029
StatusPublished
Cited by1 cases

This text of 196 F. Supp. 643 (Sloane v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sloane v. United States, 196 F. Supp. 643, 1961 U.S. Dist. LEXIS 4060 (southcarolinaed 1961).

Opinion

WYCHE, District Judge.

In this action plaintiff seeks damages for the negligent breach of a construction contract entered into with the defendant in the following particulars: (a) When the defendant became aware that it would be unable to receive delivery of the pontoons from the plaintiff, it failed to advise the plaintiff in sufficient time for him to change his schedule of construction accordingly; (b) Even though the defendant knew, or should have known, that it would be unable to receive delivery of the completed pontoons, it instructed the plaintiff to complete the construction of the pontoons as scheduled, and that it would receive and store the completed pontoons in the Charleston Navy Yard, and thereafter it failed and refused to receive the pontoons; (c) Even when the defendant knew, or should have known, that it would be unable to receive the completed pontoons, it instructed the plaintiff, by letter dated October 30, 1957, that the pontoons would be delivered at the job in “early spring, probably March.” In point of fact, the defendant refused to receive delivery of the pontoons until June, 1958; (d) The defendant failed and refused to accept delivery of the said pontoons and completion of the said contract on or before May 1, 1958, the completion date of the contract as modified by Change “B”.

This court has jurisdiction under the Tucker Act, 28 U.S.C.A. § 1346(a) (2).

The ease was tried before me without a jury.

At the close of plaintiff’s case the defendant moved for an involuntary dismissal. This motion was taken under advisement. The defendant then offered no testimony and renewed its motion for an involuntary dismissal.

In compliance with Rule 52(a), Rules of Civil Procedure, 28 U.S.C.A., I find the facts specially and state my conclusions of law thereon, in the above cause, as follows:

Findings of Fact

The basic facts in this case are not in dispute.

The plaintiff, Sam A. Sloane, doing business as Sam A. Sloane Construction [644]*644Company, on February 20, 1957, entered into Contract NBy-4999 with the Department of the Navy for the construction and installation of three floating boat piers to be installed on site at the United States Naval Minecraft Base, Charleston, South Carolina. The contract was executed on Standard Form 23A and the price agreed upon for the work to be furnished was $260,437. These three floating piers were to be installed in spud pile bents which were to be constructed under a separate contract by Manu-Mine Research and Development Company.

The contract between plaintiff and defendant provided in Specification 1-23 that the plaintiff submit a schedule of construction and installation for approval before commencement of construction. By letter dated April 12, 1957, plaintiff furnished the following schedule of construction: “1 — Poured concrete casting beds, carpentry shop, etc., complete by 15 April 1957. 2 — -Launching basin and canal from yard to Great Sound complete by 15 June 1957. 3- — -Build Pier and set up crane for launching by 1 July 1957. 4 — Build launching ramp, access roads, etc., by 1 July 1957. 5 — Form materials reinforcing and sleeves to arrive by 15 May 1957 and first cell form complete by June 1, 1957, nine forms to be built, balance complete by 1 July 1957. 6— Pour first cell no later than week of 18 June 1957, balance to be poured by 15 November 1957. All launched by 15 December 1957. 7 — Install first pier October 1957, second December 1957 and third January 1958.”

No objection to this work schedule was raised by the defendant but it retained the schedule and permitted plaintiff to proceed with the work on the basis of this schedule.

Specification 1-06 of the contract provided that the work be completed within 360 calendar days after the date of notice of award or other communication authorizing the plaintiff to proceed. The contract, as originally executed, provided for work to commence on February 25, 1957, and to be completed by February 20, 1958.

Specification 1-07 provided for liquidated damages of $100 per day for failure to complete the work within the time allowed.

Specification 1-25 provided that the actual construction of the pontoons and their assembly into piers could be performed at the Naval Base or elsewhere at the option of the plaintiff, but further provided that the final acceptance was to be conditioned on their installation within and connection to the spud piles at the Naval Base.

In view of the conditions existing at the Naval Base, the plaintiff, in preparing his bid, planned to construct the pontoons on a site owned by him. Plaintiff probably would have gotten the bid had he planned to construct them at the Naval Base because his price would have been much higher, as it was cheaper to build a basin on his property to do the work. In connection with their construction, plaintiff dredged a basin on his property on James Island which was large enough to accommodate three assembled pontoons and would have been sufficient to meet the needs of plaintiff under the work schedule submitted to the defendant.

The contract between the defendant and Manu-Mine Research and Development Company, which had been entered into on May 18, 1956, was declared in default by the defendant approximately March 30, 1957. A completion contract for the incompleted portion of the ManuMine contract was awarded to Tidewater Construction Company, Norfolk, Virginia, on April 15,1957.

In a conversation with agents of the defendant during the early part of October, 1957, plaintiff advised that the spud pile bents were not ready for the installation of the pontoons and that he would not be able to deliver because the bents were not in place. By letter dated October 15, 1957, plaintiff advised defendant as follows: “Gentlemen: On April 12, 1957, we furnished you with a [645]*645letter covering schedule of construction. ‘Item 7. Install first pier October 1957.’ It is our understanding that the pile work has not been started, therefore, we will be unable to maintain our schedule. Please advise immediately as to your pleasure in this matter. It will be necessary for us to remove from our basin some of these units in order that we have room to complete the assembly of the balance. Yours truly, Sam A. Sloane Construction Co. Sam A. Sloane”.

Thereafter, the plaintiff discussed the delay in the construction of the pile work verbally with the Resident Officer in Charge of Construction, and this officer advised the plaintiff to go forward with his work as scheduled, and that provisions would be made to receive and store the completed floating boat piers at the Naval Base.

By letter dated October 30, 1957, defendant advised plaintiff that the pontoons were not to be delivered to the job before early spring, probably March. By letter dated November 2, 1957, plaintiff advised defendant that, in order to continue work, it would be necessary to enlarge plaintiff’s wet basin to accommodate all pontoons and further provide insurance coverage because of the added element of risk of having to wait to install the pontoons. Plaintiff further presented a cost breakdown for this additional expense in the amount of $6,600. This claim for additional expense was denied by letter dated May 9, 1958. The claim was then properly presented through administrative channels to the Armed Services Board of Contract Appeals where it was dismissed for lack of jurisdiction by order dated September 18, 1958.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicora Construction Co. v. United States
252 F. Supp. 910 (E.D. North Carolina, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
196 F. Supp. 643, 1961 U.S. Dist. LEXIS 4060, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sloane-v-united-states-southcarolinaed-1961.