Sloan v. Greenville County

CourtCourt of Appeals of South Carolina
DecidedApril 22, 2004
Docket2004-UP-277
StatusUnpublished

This text of Sloan v. Greenville County (Sloan v. Greenville County) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sloan v. Greenville County, (S.C. Ct. App. 2004).

Opinion

THIS OPINION HAS NO PRECEDENTIAL VALUE.  IT SHOULD NOT BE CITED OR RELIED ON AS PRECEDENT IN ANY PROCEEDING EXCEPT AS PROVIDED BY RULE 239(d)(2), SCACR.

THE STATE OF SOUTH CAROLINA
In The Court of Appeals


Edward D. Sloan, Jr., individually, and a Citizen, Resident, Taxpayer and Registered Elector of Greenville County,        Appellant,

v.

Greenville County, a Political Subdivision of the State of South Carolina, Dozier Brooks, Scott Case, Bob Cook, Joseph Dill, Cort Flint, Lottie Gibson, Phyllis Henderson, Allen "Bunk" Johnson, Mark Kingsbury, Xanthene Norris, Stephen Selby, and Robert Taylor,        Respondents.


Appeal From Greenville County
John C. Few, Circuit Court Judge


Unpublished Opinion No. 2004-UP-277
Submitted April 6, 2004 – Filed April 22, 2004


AFFIRMED


James G. Carpenter and Jennifer J. Miller, both of Greenville, for Appellant.

Thomas H. Coker and Boyd B. Nicholson, Jr., both of Greenville, for Respondents.

PER CURIAM:  Edward D. Sloan, Jr., suing as a taxpayer and citizen of Greenville County, brought this action challenging the sufficiency of a written determination by the county for the procurement of design-build services for the county’s 2001-2002 Roads Paving Program.  Sloan alleged that the county’s written determination was insufficient and, was therefore “arbitrary, capricious, ultra vires and an abuse of discretion.”  He appeals the ruling of the trial court, finding the determination was sufficient, granting judgment to the County, and dismissing the case with prejudice.  We affirm.

FACTUAL/PROCEDURAL BACKGROUND

The Greenville County Code (“G.C.C.” or “the Code”) prescribes the methods the County may use in awarding contracts for construction services.  Generally, under the Code, the County must procure construction services that exceed $15,000 through the competitive sealed biding (“CSB”) process.  G.C.C. § 7-213.  However, the County may forego the CSB method and utilize an alternative procurement and construction method if one of several exceptions set out in the code applies.  One of these alternative methods is the “design-build services, turnkey management services, or construction management services” method (hereinafter collectively referred to as “design-build services”).  Specifically, Greenville County Code § 7-212 provides in pertinent part as follows:

Unless otherwise required by law, all county contracts shall be awarded by competitive sealed bidding, pursuant to section 7-213 (competitive sealed bidding), except as provided in:

. . .

(10) Section [7-242.5] [1] (design-build services, turnkey management services, or construction management services).

G.C.C. § 7-212.  The Code defines these services as “approaches to construction contract management that allow for the selection of a single firm to perform and/or manage the complete design and construction of a project.”  G.C.C. § 7-198. 

Greenville County Code § 7-242.5 sets out the guidelines that the county administrator shall follow when exercising his discretionary right to utilize the design-build construction method in lieu of the CSB method.  The administrator is to consider the method which, in his or her discretion, is “the most advantageous to the county and will result in the most timely, economical and successful completion of the construction project.”  This determination must be stated in writing and included as a part of the contract file.  G.C.C. § 7-242.5(a). [2]   If the county administrator determines use of design-build services is most advantageous, and the project exceeds $5 million, the administrator’s written determination must be submitted for review to the county council’s committee of the whole.  Notice of review must be presented to the public, and an interested party has fifteen days to submit written comments to the committee of the whole.  At the next committee meeting, members of the public who submitted written comments may address the committee.  Following comments, County Council may reject the design-build method.  If County Council does not vote to reject the design-build method, the project goes forward.  G.C.C. § 7-242.5(b). 

In October 2001, the county administrator of Greenville County made a written determination to use design-build service for the County’s 2001-2002 Roads Project. This determination called for the procurement of these services through the competitive sealed proposal (CSP) method.  The County gave public notice of the determination, inviting the public to make comment upon it.  The administrator submitted the determination to county council at its committee of the whole meeting and council did not reject the proposal.  Following a selection process pursuant to G.C.C. § 7-215, governing the CSP method, the County entered into a contract with a contractor for the performance of the project. 

In November 2001, Sloan filed a summons and complaint challenging the sufficiency of the determination and seeking declaratory and injunctive relief.  While admitting that the County had prepared a written determination, Sloan alleged that the County “failed to include sufficient facts and rationale based on those stated facts to justify an exception to competitive sealed bidding.”  Thus, he alleged that the determination was “arbitrary, capricious, ultra vires and an abuse of discretion.” 

The trial judge held that Sloan had “utterly failed to meet his burden of proof on [the] claim.”  Instead of concluding that the document arbitrarily triggered the exception, the trial judge found that the written determination contained several well-reasoned conclusions supported by empirical data and prior County experience to support the county administrator’s decision to use the design-build/CSP method.  This appeal followed.

LAW / ANALYSIS

The action before us now is nearly identical to a suit recently ruled on by this Court concerning the same parties of the present case.  The current case differs from the previous suit, also brought by Sloan against Greenville County, only in that it challenges a different written determination for use of the design-build/CSP method than the three determinations in prior years challenged by the previous case.  Sloan v. Greenville County, 356 S.C. 531, 590 S.E.2d 338 (Ct. App. 2003) (hereinafter “Sloan I

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Georgetown County Council
355 S.E.2d 864 (Court of Appeals of South Carolina, 1987)
Townes Associates, Ltd. v. City of Greenville
221 S.E.2d 773 (Supreme Court of South Carolina, 1976)
Sloan v. Greenville County
590 S.E.2d 338 (Court of Appeals of South Carolina, 2003)
Parker v. South Carolina Public Service Commission
342 S.E.2d 403 (Supreme Court of South Carolina, 1986)
Piedmont Natural Gas Co. v. Hamm
389 S.E.2d 655 (Supreme Court of South Carolina, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Sloan v. Greenville County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sloan-v-greenville-county-scctapp-2004.