Sledd v. Washington Metropolitan Area Transit Authority

439 A.2d 464, 28 A.L.R. 4th 741, 1981 D.C. App. LEXIS 416
CourtDistrict of Columbia Court of Appeals
DecidedNovember 9, 1981
Docket80-1424
StatusPublished
Cited by14 cases

This text of 439 A.2d 464 (Sledd v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sledd v. Washington Metropolitan Area Transit Authority, 439 A.2d 464, 28 A.L.R. 4th 741, 1981 D.C. App. LEXIS 416 (D.C. 1981).

Opinion

PER CURIAM:

It is alleged in this appeal that the trial court improperly granted appellee’s motion for summary judgment because (1) the measurements of the platform-to-train gaps at the Federal Triangle Metro Station taken by one Brian Moriarty raise an issue of material fact as to whether the actual gaps exceeded appellee’s design criteria, and (2) the evidence presented by appellant raised an issue of material fact as to whether the distance between the platform and the subway train at the Federal Triangle Metro Station is unreasonably dangerous. We affirm.

I

On June 8, 1978, at approximately 8:30 a. m., appellant Calvin Sledd entered the Federal Triangle Metro Station to service the automatic farecard machines owned by ap-pellee, Washington Metropolitan Area Transit Authority (WMATA). After appellant completed servicing the machines, he was dispatched to another station on the Blue Line in the direction of the Stadium-Armory Metro Station. He was carrying equipment with him which weighed approximately 155 pounds. When a Metro train pulled into the station, appellant placed his equipment inside the train and then boarded it before all of the passengers had exited. As the remaining passengers left the train, appellant, who was standing sideways in the doorway, placed one foot back on the platform. His foot twisted and slipped into the gap between the platform and the train, causing appellant’s leg to fall into the gap up to thigh level. He sustained a number of injuries.

Appellant’s counsel, to pursue a possible claim against appellee, hired a professional consultant, Brian Moriarty, a Senior Systems Assurance Engineer at DeLeuw, Cather & Company, who used a twelve inch ruler to take nine measurements of the platform-to-train gaps at the Federal Triangle Metro Station in the direction of the Stadium-Armory Metro Station. Three of these measurements revealed gaps of 4% inches and 4% inches, in excess of appellee’s design criteria which specified a gap of 2Vs inches to 4Vi inches. 1 On March 12, 1980, appellant filed a complaint alleging that appellee was negligent in failing to observe reasonable care in the design and/or acceptance of a “too wide” gap between the Metro train and platform and in failing to correct and warn of the dangerous condition.

In April of 1980, Mr. Moriarty learned that his employer, DeLeuw, Cather & Company, was a consultant for appellee’s subway system and advised appellant’s counsel that he could not continue their relationship.

On June 4, 1980, appellee filed a motion for summary judgment alleging that there was no genuine dispute of material fact inasmuch as the platform-to-train gap at the Federal Triangle Metro Station was within the established design criteria and was reasonably safe. 2 Appellant opposed the motion on the basis of the affidavit of Mr. Paul Gottfried, an electrical engineer, who stated that appellee’s design criteria exceeded those recommended by the Ameri *467 can Public Transit Association (APTA) in its 1979 guidelines, 3 that a review of preliminary measurements (those of Mr. Moriarty) indicated that from time to time the gap at the Federal Triangle Metro Station exceeded appellee’s maximum allowable gap and that further testing was necessary to determine whether the gaps were in conformance with appellee’s design specifications. Appellant then filed a Rule 34 request to enter the Federal Triangle Metro Station to measure the gap. Super.Ct.Civ.R. 34.

At the summary judgment hearing on September 19, 1980, the trial court deferred resolution of appellee’s motion to provide appellant an opportunity to make the requested measurements. The court ordered that the measurements be taken while both parties’ experts were present. On October 2, 1980, representatives of appellant and appellee met at the Federal Triangle Metro Station to take gap measurements. To ensure the accuracy of the measurements, each train was stopped and not permitted to proceed until each party’s expert had obtained his own independent measurement. No measurement taken by either party exceeded the design criteria maximum of 4V2 inches. 4

A second hearing on appellee’s motion for summary judgment took place on October 20, 1980. At this hearing, appellant sought to rely on Brian Moriarty’s measurements to defeat the motion. The court postponed ruling on the motion until an affidavit of Mr. Moriarty arrived on the next day. Mr. Moriarty’s affidavit however did not help appellant; it stated that his preliminary measurements were “imprecise,” “unscientific” and “isolated” and that “no reliance” should be placed on them.

On October 21, 1980, the court held a third summary judgment hearing. Appellant’s counsel requested an opportunity to take Mr. Moriarty’s deposition on the ground that he was surprised and angry at the substance of the affidavit. The court granted the request.

At his deposition, Mr. Moriarty reaffirmed the statements in his affidavit. He confirmed that the statements were his own and that the affidavit was drafted, prepared and executed by him alone. He denied that his employer had forced or ordered him to prepare the affidavit.

On October 28, 1980, a fourth summary judgment hearing was held. The court granted appellee’s motion, concluding that there was no evidence genuinely raising the issue that appellee’s actual gaps had exceeded the design criteria. The court found that (1) the preliminary measurements taken by Mr. Moriarty were contrary to those taken by appellant’s own expert witness, Mr. Gottfried; (2) Mr. Gottfried’s measurements were consistent with those gathered by appellee’s experts; and (3) Mr. Moriarty’s statements in his affidavit, reaffirmed at his deposition, indicated that the measurements he took were “inherently untrustworthy.”

The trial court also disposed of appellant’s other contention that the gap was unreasonably dangerous, holding that the record established “that at the time of the design and the time of construction [of the Federal Triangle Metro Station], the [appel-lee] was in conformity with industry standards and the state of the art.” Applying the standard set forth in Westinghouse Electric Corp. v. Nutt, D.C.App., 407 A.2d 606 (1979), the court concluded that appellant had failed to introduce any evidence that the gap at Federal Triangle was not reasonably safe for its intended use. This appeal followed.

II

Summary judgment may be granted in an action “if the pleadings, depo *468 sitions, answers to interrogatories, and admissions on file, together with the affidavits ... show that there is no genuine issue as to any material matter of fact and that the moving party is entitled to judgment as a matter of law.” Super.Ct.Civ.R. 56(c); Nader v. de Toledano, D.C.App., 408 A.2d 31, 41 (1979), cert. denied, 444 U.S. 1078, 100 S.Ct. 1028, 62 L.Ed.2d 761 (1980); Reichman v. Franklin Simon Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

R & A, INC. v. Kozy Korner, Inc.
672 A.2d 1062 (District of Columbia Court of Appeals, 1996)
Gatling v. Washington Metropolitan Area Transit Authority
866 F. Supp. 28 (District of Columbia, 1994)
Mattox v. Metropolitan Atlanta Rapid Transit Authority
409 S.E.2d 267 (Court of Appeals of Georgia, 1991)
Jones v. Washington Metropolitan Area Transit Authority
742 F. Supp. 24 (District of Columbia, 1990)
Wolf v. Regardie
553 A.2d 1213 (District of Columbia Court of Appeals, 1989)
Stanley Foshee v. Consolidated Rail Corporation
849 F.2d 657 (D.C. Circuit, 1988)
Boykin v. District of Columbia
484 A.2d 560 (District of Columbia Court of Appeals, 1984)
Taylor v. Eureka Investment Corp.
482 A.2d 354 (District of Columbia Court of Appeals, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
439 A.2d 464, 28 A.L.R. 4th 741, 1981 D.C. App. LEXIS 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sledd-v-washington-metropolitan-area-transit-authority-dc-1981.