Slaughter v. Crisian Nesbit

152 S.W. 205, 1912 Tex. App. LEXIS 1202
CourtCourt of Appeals of Texas
DecidedDecember 4, 1912
StatusPublished
Cited by7 cases

This text of 152 S.W. 205 (Slaughter v. Crisian Nesbit) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slaughter v. Crisian Nesbit, 152 S.W. 205, 1912 Tex. App. LEXIS 1202 (Tex. Ct. App. 1912).

Opinion

MOURSUND, J.

C. C. Slaughter, appellant, made a written contract with Crisman *206 & Nesbit, appellees, by which the latter were to destroy an. old building on a lot belonging to Slaughter and erect a new one in place of it, and to make alterations and extensions to the existing building adjoining. At the conclusion of the work Slaughter held a percentage of the contract price stipulated to be reserved upon current payments and some items of extras done by the contractors were unsettled, and also items of credits owing Slaughter for work omitted by agreement; also Slaughter’s claim for damages for loss suffered because of the contractor’s failure to finish the work within the time stipulated in the contract. These matters, under a written agreement, were submitted to three arbitrators, two of whom were named in the agreement, and the third to be selected by them. An award was made by a majority of the arbitrators.

On April 22, 1910, appellees sued Slaughter on said award, attaching to their petition copies of the original contract, the agreement of arbitration, and the award. Defendant’s amended answer consisted of exceptions, a special plea that the arbitrators did not comply with the terms of the arbitration agreement in that two of them, without having selected the third arbitrator, determined such of the matters in controversy as they could agree upon, and then selected O. A. Gill as ■an umpire to determine such matters only as they had been unable to agree upon; also that the arbitrators did not place any witnesses under oath or affirmation; that said agreement provided that they should determine what amount Slaughter was entitled to by reason of plaintiffs’ failure to complete their contract within the time prescribed, namely, 217 days after getting full possession of No. 253 Main street, Dallas, Tex., which possession they procured March 15, 1909, thus making their time expire on October 18, 1909; that the work, was not completed until March 26, 1910, but arbitrators Gill and Watson permitted plaintiffs to plead and heard statements from them in evidence to the effect that defendant agreed with them orally before the signing of the contract that no damages would be claimed by him for a breach of said contract as to the time within which the work should be completed, and upon said plea and statement said two arbitrators held the written contract not binding upon plaintiffs as to such time limit for completing the work, and that the legal effect of said oral agreement was to abrogate the stipulation in the written contract requiring plaintiffs to complete the work in 217 days; that therefore plaintiffs were not liable for delay in completing the work, and said two arbitrators refused to consider Slaughter’s claim for damages on account of delay or the evidence offered thereon. Defendant further alleged that such construction of the contract was flagrantly erroneous and in contravention of the well-established rules of law that the terms of a written contract cannot be set aside or altered by proof of contemporaneous or antecedent oral agreements between the parties; that such construction of the contract, if enforced, would inflict serious damage to defendant, namely, in the sum of ?12,000, the amount he was entitled to have awarded by said arbitration. Defendant prayed that said award be vacated and set aside and plaintiffs relegated to whatever cause of action they had prior to the submission to arbitration. Defendant further answered with general denial allegation of delay by plaintiffs in completing the work, causing damage to defendant in the sum of 812,000, the value of the use of the building during the time of the delay; also claiming $997.75 for work omitted • by agreement and $80 for work which plaintiffs failed to perform and which defendant had done.

Plaintiffs filed a supplemental petition containing exceptions and setting up numerous claims of obstructions encountered by them in performing their work, and also setting up a claim for extras. A supplemental answer was filed consisting of exceptions which were sustained. Thereupon plaintiffs filed a trial amendment, to which the same exceptions were urged, but overruled. The Texas Glass & Paint Company filed an intervention for work done under contract with Crisman & Nesbit. The case was submitted to the jury upon special issues, together with special instructions, and verdict returned sustaining the award of the arbitrators and also finding on the special issues submitted with reference to the work done under the contract independent of the award. Judgment was entered in accordance with the award of the arbitrators, ignoring the findings of the jury in other respects; also foreclosing mechanics’ lien on the property, and giving interveners judgment for $1,615.68, and foreclosure of mechanics’ lien. Defendant appealed.

[1] The first assignment of error complains of the'overruling of exceptions to plaintiffs’ petition; the second complains of the admission in evidence of the award of the arbitrators. The proposition submitted under these assignments is as follows: “One of the conditions to the validity of the award, as shown by 'the agreement to arbitrate set out in plaintiffs’ amended petition, was that the matters submitted should be heard and determined by three arbitrators. The award showing on its face that before the selection of the third arbitrator the two arbitrators ' named by the parties investigated and tried the case in part, the award was void on its face and not binding on, nor admissible in evidence against, the defendant.”

The agreement to arbitrate reads as follows: “Whereas, certain differences have arisen between O. C. Slaughter and Crisman & Nesbit, growing out of the written contract of March 6, 1909, between said parties, relating to the building of the Slaughter Annex *207 and alterations to the Slaughter building on Main street, Dallas, Texas; and, whereas, the matters in dispute relate to the following items: (1) The amount of extras, if any, to which Crisman & Nesbit are entitled. (2) The amount of deductions, if any, to which C. C. Slaughter is entitled. (3) The amount of damages, if any, to which C. C. Slaughter is entitled on account of delay in the prosecution and completion of the Work. Now, it is agreed -that the parties hereto will submit' to arbitration the said three matters in controversy between them. There is no dispute as to the amount of the original contract or the payments made thereon, and balance still unpaid upon the contract amounting to $18,-181.27. Erom that amount there is to. be added or deducted the amounts that may be found due by the arbitrators from C. C. Slaughter to Crisman & Nesbit and from Crisman & Nesbit to C. C. Slaughter, on account of the three items in controversy submitted to arbitration. And for the purpose of carrying out the arbitration, the matters in controversy, as aforesaid, are hereby submitted to three arbitrators, two of whom shall be W. Illingworth and A. Watson; these two shall select a third disinterested arbitrator. The three arbitrators shall proceed, in such manner as they may deem most convenient, to determine the said matters in controversy between the parties hereto; and for that purpose they may examine the building, plans, specifications, and other papers, and may hear such testimony, under oath or affirmation, as they may deem relevant. If, upon any matter in controversy, the arbitrators cannot all agree, the majority shall govern.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Paul Ouzenne v. Carnell Haynes
Court of Appeals of Texas, 2012
Emerald Forest Utility District v. Simonsen Construction Co.
679 S.W.2d 51 (Court of Appeals of Texas, 1984)
Leigland v. Rundle Land & Abstract Co.
208 P. 1075 (Montana Supreme Court, 1922)
Slaughter v. Crisman Nesbit
178 S.W. 1 (Court of Appeals of Texas, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
152 S.W. 205, 1912 Tex. App. LEXIS 1202, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slaughter-v-crisian-nesbit-texapp-1912.