Slade v. McIntyre

11 Mass. L. Rptr. 79
CourtMassachusetts Superior Court
DecidedNovember 30, 1999
DocketNo. 971693
StatusPublished

This text of 11 Mass. L. Rptr. 79 (Slade v. McIntyre) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slade v. McIntyre, 11 Mass. L. Rptr. 79 (Mass. Ct. App. 1999).

Opinion

McDonald, J.

The plaintiffs, Christopher S. Slade and Crossed Streams, Inc. (collectively “Slade”), com[80]*80menced this action to assert claims for breach of contract, misrepresentation, promissory estoppel, impossibility, unjust enrichment, quantum meruit, mutual mistake, and violation of G.L.c. 93A, arising out of a 1988 agreement permitting Slade to remove sand and gravel from the property of the defendants, David L. (“McIntyre”) and Julie A. McIntyre (“the McIntyres”). The defendants asserted counterclaims for breach of contract and specific performance. This matter is now before the court on the plaintiffs’ motion for summary judgment on all counts. For the reasons set forth below, the motion is ALLOWED on Count VII (mutual mistake). The defendants are entitled to summary judgment on Count II (misrepresentation) and Count VIII (violation of G.L.c. 93A). The remaining counts are moot.

.BACKGROUND

The following facts are undisputed. On May 8, 1988, the parties entered into an agreement, memorialized by an unsigned memorandum of understanding (“Agreement”), providing that Slade could remove 184,000 cubic yards of sand and gravel from property behind the McIntyres’ home in the Town of Ashby (“Ashby”) in return for 36 monthly payments of $6,500.00.3 The Agreement, which gave Slade the exclusive right to remove sand and gravel from the property between June 1988 and June 1991, provided that the McIntyres would “maintain valid permits and pay all fees and expenses necessary for securing and maintaining all permits.” The Agreement indicated that the intent was to complete the removal operation in three years, but if material remained at the end of the initial three year period, the McIntyres would “work in good faith to have the permit renewed for another three year period.”

Before the parties entered into the Agreement, the McIntyres had obtained a Special Permit from Ashby’s Zoning Board of Appeals to excavate sand and gravel from the property. The Special Permit provided that the applicant “must request and receive a permit from the Board of Selectmen for excavation of sand and gravel pursuant to the town by-law adopted at the March 10, 1979 annual town meeting.” In April 1988, while the plaintiffs and defendants were negotiating the Agreement, the members of the Ashby Board of Selectmen (“Selectmen”) resigned, and were replaced with a new Board in July 1988.

When the parties entered into the Agreement, the McIntyres had not applied for an Earth Removal Permit from the Selectmen. The parties were aware, however, that other sand and gravel pits operated within Ashby. The McIntyres first submitted an application for an Earth Removal Permit to the Selectmen on July 14, 1988. The Selectmen denied the application on October 11, 1988. The McIntyres requested reconsideration of their application in January 1989, and the Selectmen upon reconsideration again denied the McIntyres’ permit application on May 12, 1989. After the Selectmen first denied their permit application in October 1988, the McIntyres sued the Selectmen in Middlesex Superior Court in December 1988. Judgment entered for the Selectmen in December 1989, and was affirmed by the Massachusetts Appeals Court on January 6, 1992. See McIntyre v. Board of Selectmen of Ashby, 31 Mass.App.Ct. 735 (1992).

To prepare the site for the mining operation, Slade constructed an access road and cleared a portion of the property. On or about May 16, 1989, Slade attempted for the first time to remove sand and gravel from the site. At that time, Ashby police stopped Slade’s vehicles and ordered Slade to stop removal of the sand and gravel because necessary permits were not in place. Between May 31, 1988 and December 1, 1989, Slade made 19 monthly payments to McIntyre totaling$123,500.00. In December 1989, following the unfavorable Superior Court decision, the parties amended the Agreement. The amendment noted that “the original memorandum did not provide for interruption of operation due to permit problems, which arise out of no fault of either party,” acknowledged Slade’s 19 payments, and suspended further monthly payments until “the permits are in place and hauling can resume.” While the amendment provided for suspension of further payment until permits were in place, it did not provide for any further extension of the time period encompassed by the Agreement.

After the 1992 Appeals Court decision, in an effort to obtain permission to remove sand and gravel from their property, the McIntyres applied for a building permit to construct a single family home on their land.4 Site preparations for the proposed home and septic system purportedly required removal of a quantity of sand and gravel. The building permit was issued in May 1992. The McIntyres suggested Slade continue to remove sand and gravel from the property under the authority of the building permit. Although Slade removed some material, he did so on a limited and irregular basis. The Ashby Building Inspector voided the building permit in May 1993 for lack of activity, and reissued the permit in February 1994. In June 1994, the Ashby Board of Health decreed that new home construction would be permitted only upon installation and approval of a well. The building permit was again revoked pursuant to the new requirement, and reinstated in September 1994 after installation of a well. The Board of Health again revoked the permit in August 1995, because an area of the gravel pit was excavated that had been designated as the site for a sewage disposal system. Between 1988 and 1995, Slade removed approximately 16,000 of the 184,000 cubic yards of sand and gravel provided for in the Agreement.

DISCUSSION

Summary judgment is appropriate where there is no genuine issue as to any material fact, and the moving party is entitled to judgment as a matter of law. [81]*81Kourouvacilis v. General Motors Corp., 410 Mass. 706, 716 (1991). The moving party bears the burden of affirmatively demonstrating that there is no genuine issue of material fact. Pederson v. Time, Inc., 404 Mass. 14, 17 (1989). “If the moving party establishes the absence of a triable issue, the party opposing the motion must respond and allege specific facts which would establish the existence of a genuine issue of material fact in order to defeat a motion for summary judgment.” Pederson v. Time, Inc., supra at 17. The opposing party cannot rest on his or her pleadings and mere assertions of disputed facts to defeat the motion for summaryjudgment. LaLonde v. Eissner, 405 Mass. 207, 209 (1989).

A. Mutual Mistake

Massachusetts law regarding mutual mistake is substantially in accord with the articulation made in Restatement (Second) of Contracts §152 (1979) which provides: “ ‘(1) Mere mistake of both parties at the time a contract was made as to a basic assumption on which the contract was made has a material effect on the agreed exchange of performances, the contract is voidable by the adversely affected party unless he bears the risk of the mistake . . . ’ ” Maloney v. Sargisson, 18 Mass.App.Ct. 341, 345 (1984).

Here, it is undisputed that at the time the contract was entered into, both parties made the assumption that all necessary permits were in place or procurable to allow Slade to remove the contracted-for amount of sand and gravel. The defendant, David McIntyre, stated in his affidavit that “[I]n April of 1988,1 believed that all necessary permits were in place to proceed.”5 Aff. of Def. David L. McIntyre, Par.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pederson v. Time, Inc.
532 N.E.2d 1211 (Massachusetts Supreme Judicial Court, 1989)
LaLonde v. Eissner
539 N.E.2d 538 (Massachusetts Supreme Judicial Court, 1989)
Maloney v. Sargisson
465 N.E.2d 296 (Massachusetts Appeals Court, 1984)
McIntyre v. Board of Selectmen of Ashby
584 N.E.2d 1137 (Massachusetts Appeals Court, 1992)
Bellefeuille v. Medeiros
139 N.E.2d 413 (Massachusetts Supreme Judicial Court, 1957)
Kourouvacilis v. General Motors Corp.
575 N.E.2d 734 (Massachusetts Supreme Judicial Court, 1991)
Cherry v. Crispin
190 N.E.2d 93 (Massachusetts Supreme Judicial Court, 1963)
The DOVER POOL & RACQUET CLUB, INC. v. Brooking
322 N.E.2d 168 (Massachusetts Supreme Judicial Court, 1975)
Putnam v. Bolster
216 Mass. 367 (Massachusetts Supreme Judicial Court, 1914)
National Grange Mutual Insurance v. Walsh
535 N.E.2d 1277 (Massachusetts Appeals Court, 1989)
Fernandes v. Rodrigue
38 Mass. App. Ct. 926 (Massachusetts Appeals Court, 1995)
Ravosa v. Zais
661 N.E.2d 111 (Massachusetts Appeals Court, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
11 Mass. L. Rptr. 79, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slade-v-mcintyre-masssuperct-1999.