Skycasters v. J.W. Didado Elec. Inc., 23901 (9-24-2008)

2008 Ohio 4849
CourtOhio Court of Appeals
DecidedSeptember 24, 2008
DocketNo. 23901.
StatusUnpublished
Cited by1 cases

This text of 2008 Ohio 4849 (Skycasters v. J.W. Didado Elec. Inc., 23901 (9-24-2008)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skycasters v. J.W. Didado Elec. Inc., 23901 (9-24-2008), 2008 Ohio 4849 (Ohio Ct. App. 2008).

Opinion

INTRODUCTION
{¶ 1} Skycasters LLC hired J. W. Didado Electric Inc. to provide power to its new satellite dish. It also hired Didado to install two generators and two uninterrupted power supplies to provide its computers and the satellite dish with backup power. When Didado failed to complete the project in the time Skycasters thought was required under their contract, Skycasters refused to let it complete the project and sued for breach. Didado counterclaimed, seeking to recover for additional work it had performed for Skycasters outside the written contract. A jury found in favor of Didado, awarding it $66,384.70 in damages. This Court affirms because the jury's verdict was not against the manifest weight of the evidence, and because Skycasters failed to establish that Didado's attorneys should have been disqualified. *Page 2

FACTS
{¶ 2} Skycasters is an internet service provider that provides internet access to its customers via satellite. At first, it did not own its own satellite dish, but rented space on a dish from a company in New Jersey. In the spring of 2005, it decided to buy its own satellite dish. Because its rental contract renewed on a year-to-year basis, Skycasters had to have its dish operational by July 1, 2005, to avoid having to renew its lease for another full year. Skycasters purchased the dish from Vertex RSI, which also connected all of the communications cables that were necessary to operate the dish to Skycasters' computer system. Vertex did not connect the dish to Skycasters' electrical system.

{¶ 3} On May 20, 2005, Skycasters entered into a contract with Didado to bring power to the dish. The contract provided that Didado would purchase and install a 35 KW natural gas generator, an 80 KW diesel generator, a 12 KW uninterrupted power supply, and a 60 KW uninterrupted power supply. An uninterrupted power supply is a set of batteries that provides immediate backup power during a power outage until a generator can turn on. The natural gas generator and smaller uninterrupted power supply were to provide backup power for Skycasters' computers. The diesel generator and larger uninterrupted power supply were to provide backup power for the dish. The contract also provided that Didado would supply and install all the conduits and wiring that needed to be run from Skycasters' building out to the satellite dish. Didado promised "to be substantially completed on or before June 21, 2005. Project will be completed with exception of Generator and UPS for Dish."

{¶ 4} In order to run electrical conduits out to the dish, Didado had to dig a trench across Skycasters' property. It also had to install conduits through part of Skycasters' building. Although the contract was only for one satellite dish, Skycasters anticipated buying additional *Page 3 dishes in the near future. It, therefore, requested that Didado install enough conduits to supply power for up to three satellite dishes. By having Didado install additional conduits at the same time it installed the conduits for the first satellite dish, Skycasters could prevent future disruptions to its employee work areas and avoid having to dig additional trenches across its property. Skycasters agreed to pay extra for the additional work.

{¶ 5} Because of the additional work, Didado could not install all of the conduits and wiring by June 21, 2005. It requested a ten day extension, which Skycasters granted. Didado also encountered a problem when it tried to hookup the natural gas generator. According to Skycasters' natural gas company, the building's gas line did not have enough pressure to run the generator. Didado did install the uninterrupted power supply for the computer system and did provide power for the satellite dish by July 1, 2005.

{¶ 6} According to Skycasters, although the satellite dish had power by the deadline, it was not safe to operate the dish without a working backup system. It claimed that operating the dish without backup power available voided its warranty. Skycasters knew that Didado had ordered a diesel generator that was not scheduled to ship until August 5, 2005. It believed, however, that Didado could have hooked up the satellite dish's uninterrupted power supply so that it could at least have obtained the protection of the power supply's batteries until the generator arrived.

{¶ 7} According to Didado, it did not install the uninterrupted power supply for the satellite dish because the engineering plans it was following for the project required it to wait until a transfer switch arrived to install it. The transfer switch was being shipped with the diesel generator. Throughout July 2005, the unassembled parts for the satellite dish's uninterrupted power supply were in Skycasters' employee kitchen. Skycasters' owner became upset that, even *Page 4 though his satellite dish was at risk, Didado's employees did not seem to be doing much work. At the end of the month, Skycasters kicked Didado off the project. When the diesel generator arrived a few days later, Skycasters refused to accept it. Skycasters subsequently hired a different electrical contractor to purchase and install a diesel generator and uninterrupted power supply for the satellite dish.

{¶ 8} On August 9, 2005, Skycasters sued Didado for breach of contract. Didado filed a counterclaim, seeking payment for its additional work. Before trial, Skycasters moved to disqualify Didado's attorneys because they had helped an agent for Skycasters obtain a zoning variance to allow it to install the satellite dish. The trial court denied the motion. At trial, a jury found for Didado and awarded it $66,384.70 in damages. Skycasters has appealed, assigning two errors.

MANIFEST WEIGHT
{¶ 9} Skycasters' first assignment of error is that the jury's verdict was against the manifest weight of the evidence. In State v.Wilson, 113 Ohio St. 3d 382, 2007-Ohio-2202, at ¶ 26, the Ohio Supreme Court held that the test for whether a judgment is against the weight of the evidence in civil cases is different from the test applicable in criminal cases. According to the Supreme Court in Wilson, the standard applicable in civil cases "was explained in C.E. Morris Co. v. FoleyConstr. Co., 54 Ohio St.2d 279." Id. at ¶ 24. The "explanation" inC.E. Morris was that "[j ]udgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence." Id. (quoting C.E. Morris Co., 54 Ohio St. 2d at 279); but see Huntington Nat'l Bank v. Chappell, 9th Dist. No. 06CA008979, 2007-Ohio-4344, at ¶¶ 17-75 *Page 5 (Dickinson, J., concurring). This Court, therefore, must affirm if the jury's verdict "is supported by some competent, credible evidence."Wilson, 2007-Ohio-2202, at ¶ 32.

{¶ 10}

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Guardianship of Bakhtiar
2021 Ohio 2629 (Ohio Court of Appeals, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
2008 Ohio 4849, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skycasters-v-jw-didado-elec-inc-23901-9-24-2008-ohioctapp-2008.