Skousen v. Herz

26 P.2d 408, 135 Cal. App. 116, 1933 Cal. App. LEXIS 129
CourtCalifornia Court of Appeal
DecidedNovember 6, 1933
DocketDocket No. 612.
StatusPublished
Cited by7 cases

This text of 26 P.2d 408 (Skousen v. Herz) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skousen v. Herz, 26 P.2d 408, 135 Cal. App. 116, 1933 Cal. App. LEXIS 129 (Cal. Ct. App. 1933).

Opinion

MARKS, J.

This action was brought by the respondent against appellants to recover money alleged to be due for labor performed under the terms of a subcontract which provided for the doing of portions of the work of construction of a section of the state highway between Black Butte and a point one and one-half miles west of Hopkins Wells in Riverside County. The Colton National Bank was joined as defendant under an allegation that it claimed some interest in the results of the controversy. Judgment was rendered in favor of respondent in the sum of l$2,575.29, and costs, and the Citizens National Bank of Colton, successor of the Colton National Bank, for $4,700.21, which has been paid, leaving only the judgment in favor of respondent involved here.

The complaint contained six causes of action, and the answer of appellants nine counterclaims. Only one of each *117 is considered in the briefs. The fourth cause of action of the complaint alleges that respondent performed extra work in preparing the roadbed for what was called “select materials”, which extra work was of the reasonable value of $3,744. The trial court found this sum to be its reasonable value but did not include the amount in the judgment. The counterclaim in question alleged that respondent abandoned his contract before its completion and that appellants were compelled to expend the sum of $2,352.94 in completing the work. The trial court found against this allegation.

Appellants had a contract with the department of public works, division of highways of the state of California, to do all of the work of grading and paving the road in question. Their subcontract with respondent made in November, 1928, is very brief and its very brevity is the seeming cause of this action. The sole description of the work to be performed by respondent is there set out as follows: “Whereas, the party of the first party (appellants) desires to sublet a portion of the work provided to be done in and by said contract to the party of the second part (respondent) ; now, therefore, it is agreed by and between the parties hereto as follows, to-wit: That the said party of the second part agrees to do all of the work provided for in and by said contract of said party of the first part with the State of California, designated therein as Items Nos. 1 and 2.”

In the “Standard Specifications” used for the work, we find this definition of the word “contract”: “The written agreement covering the performance of the work and the furnishing of labor and materials in the construction of the work. The Contract shall include the Notice to Contractors, the Proposal, Plans; Specifications, Special Provisions and Contract Bonds; also any and all Supplemental Agreements amending or extending the work contemplated and which may be required to complete the work in a substantial and acceptable manner.” Taking this broad definition of the contract we find the following explanation of “Items No. 1 and 2” in the “Notice to Contractors”: “Item 1. .139,000 cubic yards roadway embankment. Item 2. 550,000 station yards overhaul.” In the “Proposal” these items are set forth as follows: “Item 1—Approximate Quantity—139,000 cubic yards roadway embankment at twenty- *118 nine cents per cubic yard—Unit Price—$.29—Total $40,-310.00. Item 2.—Approximate Quantity — 550,000 station yards overhaul at one-half cent per station yard—Unit Price—$.005—Total — $2,750.00.” This is exactly repeated in the “contract”, by which word we now mean the instrument that was executed by appellants and the department of public works, division of highways.

There is no controversy here over the amount fixed and allowed by the trial court for “station yards overhaul”. (Item No. 2.) We are only concerned with that work which was included within Item No. 1. The contract, and subcontract, of themselves furnish no complete description of the work to be included under “Item No. 1”. Appellants contend that “Item No. 1” included the excavating of a rectangular depression twenty feet in width and between six and twelve inches in depth along the center of the entire roadway to receive “Imported Selected Materials” which were to furnish a foundation for the crushed rock or gravel or hard surface, and the shaping and finishing of the shoulders and gutters. Respondent contends that “Item No. 1” did not include either.

If we are to find any satisfactory description of the work which was to have been done by respondent under Item No. 1, we must look to the “General Specifications” for it. Under the heading “Embankment” we find nineteen paragraphs describing its construction. The only assistance we find there is the following: “Where immediate paving is contemplated, or whenever provided for in the special provisions, embankments shall be carried up in layers as above described, and in addition each layer shall be watered sufficiently to dampen the material. It shall then be thoroughly rolled with a roller complying with the requirements of article (y) of this section, and the surface of each layer shall be uniformly compacted before the next layer of embankment is placed thereon. Upon the completion of the embankment, preliminary to making subgrade, it shall be watered thoroughly by use of pipe-lines and hose.” Under “Subgrade” is the following: “(a) Description.—The sub-grade will be considered as that portion of the highway apon which surfacing or paving is to be placed. Before the surfacing or paving is placed, a subgrade shall be constructed, conforming to the grades and cross-sections shown *119 on the plans and in accordance with these specifications. The finished subgrade shall be true to cross-section, hard, uniform, smooth and must support without perceptible indentation, the wheels of heavily loaded trucks, except where the soil is too sandy, (b) When the surface of the grade is finished to a fiat cross-section, and is rolled smooth and compact, it will be considered as ready for the Engineer’s subgrade stakes. ... (g) Payment.—The cost of furnishing all labor, materials, tools, implements and equipment and of doing all work incidental to shaping the subgrade shall be considered as included in the price paid for macadam or crushed gravel or stone surfacing and no additional allowance will be made therefor.” Under the heading “Standard Road Surfacing, Crushed Gravel or Stone” the following appears: “ (h) Payment.—The price paid per ton or per cubic yard for crushed gravel or stone surfacing shall include preparing the subgrade, furnishing, hauling and placing the crushed gravel or stone and all incidental work.” Under the heading “Shoulders” is the following: “(b) Payment.-—The cost of furnishing all labor, materials, tools, implements, and equipment and doing all work incidental to constructing and shaping the shoulders shall be considered as included in the price paid for grading and no additional allowance will be made therefor.”

In the “Special Provisions” for the construction of the road there is a detailed drawing of a cross-section of the road. A straight line passes through what is marked “Imported Selected Materials” and is called “Plat Section for Rough Grading”. At a distance representing eighteen inches above is another straight line marked “Finished Grade”. Of course, the cross-section shows the shoulders and gutters finished to grade with the completed excavation for the “Imported Selected Materials”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hill v. Fowble
149 P.2d 862 (California Court of Appeal, 1944)
Commercial Discount Co. v. Cowen
116 P.2d 599 (California Supreme Court, 1941)
Grant v. Long
92 P.2d 940 (California Court of Appeal, 1939)
Edwards v. Lewis
76 P.2d 720 (California Court of Appeal, 1938)
Kohl v. Lytle Creek Water & Improvement Co.
75 P.2d 71 (California Court of Appeal, 1938)
Hill v. Industrial Accident Commission
51 P.2d 1126 (California Court of Appeal, 1935)
Robinson v. Arthur R. Lindburg, Inc.
35 P.2d 1057 (California Court of Appeal, 1934)

Cite This Page — Counsel Stack

Bluebook (online)
26 P.2d 408, 135 Cal. App. 116, 1933 Cal. App. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skousen-v-herz-calctapp-1933.