Skirvin v. Kidd

881 N.E.2d 914, 174 Ohio App. 3d 273, 2007 Ohio 7179
CourtOhio Court of Appeals
DecidedDecember 20, 2007
DocketNo. 06CA43.
StatusPublished
Cited by14 cases

This text of 881 N.E.2d 914 (Skirvin v. Kidd) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skirvin v. Kidd, 881 N.E.2d 914, 174 Ohio App. 3d 273, 2007 Ohio 7179 (Ohio Ct. App. 2007).

Opinion

Harsha, Judge.

{¶ 1} Alfred T. Skirvin appeals a judgment in his favor on his claim that Mark and Samantha Kidd (“the Kidds”) failed to make repairs to a septic system located on land Skirvin purchased from them. Skirvin contends that the contract required the Kidds to pay the cost of replacing the entire septic system. The trial court reviewed various “addenda” to the original contract and determined that the terms were clear and that the parties’ final intent was that the Kidds would complete and guarantee the leach field for only two years. The only guarantee relating to the rest of the septic system was for a one-year period.

{¶ 2} We agree with the trial court that the addenda, the stipulations, and the other documents the parties submitted reveal an intention that the Kidds would repair or replace the leach field and guarantee it for two years. We also agree with the trial court that the contract required the Kidds to guarantee the rest of the septic system for only one year from the date of closing. But because there is no evidence in the record to establish that the septic system failed in any respect other than the faulty leach field during the one-year period, the Kidds were not required to replace the entire septic system. Accordingly, we overrule Skirvin’s sole assignment of error.

I. Facts

{¶ 3} Skirvin filed a complaint that alleged that the Kidds had breached a real estate contract by failing to complete the existing septic system located on the residential property he purchased from them. He sought a judgment of $15,500, the amount he ultimately paid to replace the entire septic system, plus costs and interest. After the parties unsuccessfully filed cross-motions for summary judgment, they entered into various stipulations, which included several documents, and submitted the matter to the trial court for a decision.

{¶ 4} According to the evidence they submitted, on December 7, 2001, Skirvin agreed to purchase residential property the Kidds owned. At the time of the execution of the contract, the parties were aware of a problem with the existing leach lines of the septic system. As noted by the trial court, the copy of the original contract contained in the record is virtually illegible. However, the contract had three addenda, which are legible.

*276 {¶ 5} The first addendum contains multiple acknowledgment dates, interlineations, and deletions. 1 However, it clearly states: “The seller will complete the leach field to meet the local health codes. * * * The seller will guarantee the septic system for a period of one year from the date of closing.” The copy of this addendum in the record shows that it originally stated “buyer” will complete the leach field, but the word “buyer” was crossed out and replaced with “seller.”

{¶ 6} The second addendum states: “Please note addendum # 1 had buyer will complete leach field. This has been changed to seller. * * * Seller is to guarantee leach field for a period of one year from the date of closing. Septic system to be completed by closing weather permitting.”

{¶ 7} The first two addenda, which were signed by Skirvin and the Kidds, also contained the following provision: “This addendum becomes an integral part of the Contract. Except as amended or modified by this addendum, the Contract, in all other respects, remains the same.”

{¶ 8} Finally, the relevant portion of the third addendum, which was signed only by the Kidds, states: “The sellers Mark Kidd and Samantha Kidd have agreed to complete the leach field of 1084 DeHass Lane, Sardinia, Ohio. Their contractor, who is being paid by the sellers, will meet the requirements of the local health codes and will guarantee the leach field for a period of two years. Time is of the essence, weather permitting work must be completed as soon as possible.”

{¶ 9} There is no dispute that the Kidds did not complete repairs to the leach field. In the fall of 2005, over three years from the date of the closing, Skirvin paid WOW Plumbing $15,500 to replace the entire septic system, including an aeration tank, infiltrator leach lines, and 550 feet of curtain drain with a pumping station to a road ditch. WOW also collapsed and filled the old septic tank and topped off the leach field with 40 tons of top soil. Skirvin then filed the complaint, seeking to recover $15,500 in damages.

{¶ 10} Based on its review of the evidence, including the three addenda and the parties’ stipulations, the trial court determined that the contract only required the Kidds to complete the leach field to meet local health codes and to guarantee it for a period of two years. The trial court awarded Skirvin $3,600 in damages based on the parties’ stipulation that the cost of replacing the leach lines in January 2002 would have been $3,600.

{¶ 11} Skirvin assigns the following error:

*277 The trial court’s determination that the contract only obligates the seller to repair the leach field and not the entire septic system is against the manifest weight of the evidence and the law.

II. Standard of Review

{¶ 12} In his sole assignment of error, Skirvin contends that the trial court’s judgment is against the manifest weight of the evidence and the law.

{¶ 13} An appellate court will not reverse a trial court’s judgment as being against the manifest weight of the evidence so long as it is supported by any competent, credible evidence going to all of the essential elements of the case. Sec. Pacific Natl. Bank v. Roulette (1986), 24 Ohio St.3d 17, 20, 24 OBR 14, 492 N. E.2d 438; C.E. Morris Co. v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 280, 8 O.O.3d 261, 376 N.E.2d 578. Under this highly deferential standard of review, a reviewing court does not decide whether it would have come to the same conclusion as the trial court. Rather, we are required to uphold the judgment so long as the record, as a whole, contains some evidence from which the trier of fact could have reached its ultimate factual conclusions. Bugg v. Fancher, Highland App. No. 06CA12, 2007-Ohio-2019, 2007 WL 1225734, at ¶ 9. When conducting its review, an appellate court must make every reasonable presumption in favor of the trier of fact’s findings of fact. Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 80, 10 OBR 408, 461 N.E.2d 1273.

{¶ 14} In construing any written instrument, the primary and paramount objective is to ascertain the intent of the parties, and the general rule is that contracts should be construed so as to give effect to the intention of the parties. Aultman Hosp. Assn. v. Community Mut. Ins. Co. (1989), 46 Ohio St.3d 51, 53, 544 N.E.2d 920.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marietta v. Professional Serv. Industries, Inc.
2025 Ohio 1530 (Ohio Court of Appeals, 2025)
Jones v. Dlugos
2022 Ohio 1076 (Ohio Court of Appeals, 2022)
B.T. Environmental Solutions, L.L.C. v. B.T. Energy Group, Inc.
2018 Ohio 5113 (Ohio Court of Appeals, 2018)
In re J.R.P.
2018 Ohio 3938 (Ohio Court of Appeals, 2018)
Gutierrez-Gordillo v. Tomo Hibachi Rest. & Lounge, L.L.C.
118 N.E.3d 301 (Court of Appeals of Ohio, Eighth District, Cuyahoga County, 2018)
In re J.B.
2011 Ohio 4830 (Ohio Court of Appeals, 2011)
Youngstown v. Huffman
2011 Ohio 4753 (Ohio Court of Appeals, 2011)
In re Estate of French
2011 Ohio 422 (Ohio Court of Appeals, 2011)
In re Estate of Boone
2010 Ohio 6269 (Ohio Court of Appeals, 2010)
McClure v. Davis
926 N.E.2d 333 (Ohio Court of Appeals, 2010)
McFall v. Watson
899 N.E.2d 158 (Ohio Court of Appeals, 2008)
McFall v. Watson, 08ca667 (10-2-2008)
899 N.E.2d 158 (Ohio Court of Appeals, 2008)
Turner v. Salvagnini America, Inc., Ca2007-09-233 (7-21-2008)
2008 Ohio 3596 (Ohio Court of Appeals, 2008)
Nolfi v. OHIO KENTUCKY OIL CORP.
562 F. Supp. 2d 904 (N.D. Ohio, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
881 N.E.2d 914, 174 Ohio App. 3d 273, 2007 Ohio 7179, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skirvin-v-kidd-ohioctapp-2007.