Skidgell v. O'Connor

CourtSuperior Court of Maine
DecidedApril 9, 2018
DocketKENcv-16-137
StatusUnpublished

This text of Skidgell v. O'Connor (Skidgell v. O'Connor) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skidgell v. O'Connor, (Me. Super. Ct. 2018).

Opinion

STATE OF MAINE DISTRICT COURT KENNEBEC, SS. CIVIL ACTION DOCKET NOS. SC-16-61 & CV-16-137 CONSOLIDATED

SHELDON SKIDGELL, Plaintiff

v.

SHAUN O'CONNOR, Defendant

DECISION AND JUDGMENT SHAUN O'CONNOR, Plaintiff V.

SHELDON SKIDGELL, Defendant

CONSOLIDATED CASES

INTRODUCTION

These consolidated cases are before the court for resolution following a one­ day non-jury trial held on December 11, 2017. The cases arise out of a dispute between the parties concerning construction work Sheldon Skidgell performed for Shaun O'Connor in 2015 on Knowles Road in Belgrade. On February 22, 2016, Skidgell filed a small claims action in the District Court seeking $6000 as the balance he claimed was owned to him by O'Connor under a construction contract. (Docket No. SC-16-61). On September 6, 2016, O'Connor filed a two-count complaint in the District Court against Skidgell alleging violations of the Maine Home Construction Contracts Act (Count I) and seeking damages for the pouring of a concrete slab/pad in an allegedly negligent and unworkmanlike manner (Count II). The actions were consolidated on September 27, 2016 and transferred to the Superior Court on April 4, 2017. Trial was held on December 11, 2017, at which the court received the testimony of the following witnesses: Shaun O'Connor; Robert Greig; Terry Baker; Sheldon Skidgell; Larry Perkins; Gary Fuller, and; Michael Carrol. The court admitted into evidence Plaintiff's (O'Connor) Exhibits 1-7 and Defendant's (Skidgell) Exhibits 1-4, 6, 10-11. In lieu of oral argument the parties submitted post­ trial briefs, the last of which being received by the court on January 8, 2018. Based upon the evidence presented at trial, and after consideration of the written arguments, the court makes the following findings of fact. FINDINGS OF FACT In the spring of 2015 Shaun O'Connor and his wife were considering the purchase and installation of a double-wide mobile home on a piece of property owned by Mr. O'Connor on Knowles Road in Belgrade. A wastewater disposal system application was filed with the Town of Belgrade and approved by the code enforcement officer in May 2015. Plaintiff's Exhibit 1. Sometime thereafter (probably in July 2015) Mr. O'Connor and Mr. Skidgell spoke about Skidgell performing the work to install the septic system as well as clearing trees, putting in a driveway and pouring a concrete pad upon which the double-wide would be sited. Although the testimony was not entirely clear, the court finds that the parties had a conversation in Mr. O'Connor's garage and that Mr. Skidgell visited the site and was interested in doing work for O'Connor on this job.

2 Mr. O'Connor testified that Skidgell gave him an oral "quote" of $18,000. Mr. Skidgell testified that he worked up an estimate of roughly $18,500, but that it was difficult to arrive at a "firm" figure because Mr. O'Connor was not certain as to what he wanted to do. 1 Both parties recalled that Mr. O'Connor wanted to look at "Uncle Henry's" before deciding what he wanted to do. Mr. O'Connor denied ever hearing the figure $18,500 as an estimate and insisted that the quote from Skidgell was $18,000. After listening and viewing the testimony of both witness·es, the court finds that Mr. Skidgell gave Mr. O'Connor an estimate in the range of $18,500. Defendant's Exhibit 10 is dated July 20, 2015. On July 23, 2015 O'Connor gave Skidgell a check in the amount of $4,000 for "septic system." 2 Plaintiff's Exhibit 3. Within a week Skidgell began work on the project. No written contract was executed between the parties prior to the commencement of work. O'Connor planned on purchasing the double-wide from Champion Homes. Originally, a delivery date was expected in August 2015 but that later changed to September. O'Connor gave a copy of the double-wide plans to Skidgel!. The plans called for a cement pad of 42' X 26' 8". Plaintiff's Exhibit 2. On August 14, 2015, O'Connor issued a check to Skidgell for $5,000 for "earthwork slab." (Plt's Ex. 3). On August 19, 2015 O'Connor gave Skidgell another check for $5,000 for "material." (Id.) According to Mr. O'Connor's testimony, he asked Mr. Skidgell for a contract but was told that he (Skidgell) would get to it when he could. Mr. Skidgell, on the other hand, asserted that the delay in

' Offered and admitted into evidence was Defendant's Exhibit 10, which is a rough draft of an estimate prepared by Mr. Skidgel! dated July 20, 2015 in the amount of $18,470. Both parties agreed that this written estimate was not seen or given to Mr. O'Connor, and the court finds that it was prepared by Mr. Skidgell as a way to sketch out some numbers for himself so that he could provide an estimate to Mr. O'Connor. At the bottom of the document, Mr. Skidgel! wrote: "no house selected at this time, estimated by Shaun's rough measurements." 'Both parties agreed that Skidgel! wanted a $5,000 payment but O'Connor only paid $4,000.

3 getting a contract to Mr. O'Connor was due to the fact that (1) O'Connor left for a trip in August and (2) O'Connor was uncertain as to what he wanted. In any event, earthwork and tree cutting continued on the property but the concrete pad had not yet been poured. On or about September 11 or 12, 2015, Skidgell and O'Connor met and Skidgell presented O'Connor with a "Contract" for the total sum of $20,140. Plaintiff's Exhibit 4. Mr. O'Connor's signature on the contract is dated September 12, 2015. (Plt's Ex. 4; Def's Exh. 4). The cement pad was poured on or about September 14, 2015. O'Connor testified that he signed the "contract" under duress because Skidgell told him that if he did not sign it he (O'Connor) would be charged by the hour for the equipment on his property. Moreover, he testified that the cement pad was not poured at this time and it needed to be poured and cured soon before the double-wide was placed on top of it. O'Connor testified that when he signed the contract he told Skidgell that he was doing so under duress. Skidgell denied that O'Connor said any such thing and further claimed that the actual cost of the project was slightly higher than his estimate because of extra fill that was needed and additional trees that had to be cleared. The double-wide was delivered and placed on the pad by Champion Homes on October 2, 2015. The court finds that Mr. 0' Connor has failed to carry his burden of proving that he signed the contract "under duress." In the meantime, on September 18, 2015 Mr. O'Connor wrote a note to Mr. Skidgell which reads as follows: 18,000.00 as agreed PD. 2,140 bal due when the new contract is signed with the correct dates and amount of yards of fill. Under the added clause. The original contract was a handshake and was honored by both parties. (Plt's Ex. 5).

4 Mr. O'Connor enclosed a check for $4,000, also dated September 18, 2015, for "Final payment per original agreement." (Def's Ex. 7). Mr. Skidgell refused to accept the check as final payment because he believed he was entitled to $6,140 according to the contract signed by Mr. O'Connor on September 12, 2015. The relationship between the two men deteriorated quickly after that, although it is not clear to the court that it was ever cordial to begin with. There followed an exchange of insulting text messages between them. (Def's Ex. 1). On September 24, 2015 O'Connor filed a complaint with the Maine Attorney Generals' Consumer Protection Division alleging that Skidgell had taken advantage of him by having him sign a contract that was $2,140 more than what he considered the original price of $18,000. (Def's Ex. 2).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Runnells v. Quinn
2006 ME 7 (Supreme Judicial Court of Maine, 2006)
Paffhausen v. Balano
1998 ME 47 (Supreme Judicial Court of Maine, 1998)
Parker v. Ayre
612 A.2d 1283 (Supreme Judicial Court of Maine, 1992)
William Mushero, Inc. v. Hull
667 A.2d 853 (Supreme Judicial Court of Maine, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Skidgell v. O'Connor, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skidgell-v-oconnor-mesuperct-2018.